How to Build a Shed from Scratch: A Beginner's Guide

A step-by-step walkthrough of shed construction, from permits and foundations through framing, siding, roofing, doors, and a lumber takeoff you can price.

Quick answer

To build a shed from scratch, pick a level site, confirm permit limits, and choose a foundation (skids, piers, or slab). Frame the floor with pressure-treated rim joists and joists on 16-inch centers, frame walls flat, raise and brace them, then set rafters on a ridge board. Sheathe, side, roof, and hang the door.

  • Most jurisdictions allow sheds under 100–200 sq ft without a permit, but setbacks and HOA rules still apply.
  • Skid and pier foundations suit most backyard sheds; slabs cost more but handle heavy loads and equipment.
  • Order lumber from a takeoff, not a guess: count plates, studs, joists, rafters, and sheathing by area.
  • Roof pitch, rafter span, and header size drive the framing; check a span table or an engineer before you cut.

How to Build a Shed from Scratch: Step-by-Step

Building a shed from scratch means you take the project from bare ground to a finished, weathertight structure. The work breaks into a fixed sequence: site prep, foundation, floor framing, wall framing, roof framing, sheathing, siding, roofing, door and window installation, then trim. Skipping ahead in that order costs you time, because each stage sets the geometry the next one depends on.

The order of operations matters more than speed. You level and compact the ground first, then set the foundation, then build the floor deck square and flat. Walls go up on that deck, the roof frames on top of the walls, and only then do you close the shell with sheathing and siding. Roofing, openings, and trim come last so you are not cutting into a finished surface to fix framing.

A typical 10x12 gable shed takes a beginner 3–5 weekends, depending on weather, daylight, and how much help you have. Two people move sheet goods and raise walls far faster than one, and a second set of hands makes roof framing much safer. If you are pricing the work before you start, residential estimating services can turn your sketch into a material and labor budget.

You can set the shed on skids, piers, or a concrete slab, and that choice drives the rest of the build. Skids suit small movable sheds, piers handle frost and uneven ground, and a slab gives you a durable floor for heavy storage or a workshop. The foundation also sets your door threshold height and how you anchor the walls. Track each stage against a shed construction checklist so nothing gets missed between weekends, and use construction cost estimating if you want a second opinion on your numbers before you buy lumber.

Build the floor deck square before you frame walls. A deck that is out of square by 1/2 inch will show up as a racked roof and misaligned siding later.

Shed Building Permit Requirements

Shed building permit requirements vary by state, county, and city, so the only reliable answer comes from your local building department. Common triggers include a footprint over 120 sq ft, a height over 10 ft, or placement in a flood zone or utility easement. Some jurisdictions exempt small sheds entirely, while others require a permit for anything with a permanent foundation.

Before you buy materials, check zoning setbacks, HOA covenants, frost depth, snow load, and wind exposure. Setbacks tell you how close the shed can sit to a property line, and HOA rules can be stricter than the code. Frost depth and snow load drive your foundation and roof framing, and wind exposure affects how you anchor the structure. A call to the planning desk usually answers all of these in one conversation.

A typical permit submittal includes a site plan showing the shed location and setbacks, an elevation, framing details, and sometimes engineered drawings for larger sheds. If you are working through a designer or architect, estimating for architects can help you price the approved scope accurately. On public or institutional projects, government contractor estimating covers the compliance and prevailing-wage side.

Unpermitted sheds can trigger fines, forced removal, or problems at resale when a buyer's inspector flags the structure. If you plan to run power for lights or outlets, many jurisdictions require a separate electrical permit and an inspection. Add the permit and inspection steps to your shed construction checklist so they happen before you close up the walls.

Never assume a small shed is exempt. Ask the building department in writing and keep the reply with your project file.

Shed Foundation Options: Skids, Piers, or Slab

Shed foundation options come down to three practical choices: skids, pier and beam, or a concrete slab. Each one changes cost, difficulty, and what the shed is good for. The table below compares them on the factors that matter most when you are deciding.

Foundation typeTypical costDifficultyBest use
Skid foundationLowestLowSmall sheds, movable structures, tight budgets
Pier and beamModerateModerateFrost-prone ground, uneven sites, raised floors
Concrete slabHighestHighHeavy storage, workshops, durable floors
Slab with thickened edgeHighestHighLarger sheds that need a stiff, crack-resistant base

A skid foundation uses pressure-treated 4x4 or 6x6 beams on compacted gravel. It is the fastest option and lets you move or reposition the shed later, which is why it suits small garden sheds. The trade-off is that the floor sits close to the ground and needs good drainage to stay dry.

Pier and beam uses concrete piers or deck blocks set below frost depth, with a treated girder carrying the floor joists. It handles frost heave and sloped sites well and keeps the wood floor above splash zone. A concrete slab is a 4–6 inch reinforced slab on compacted gravel, and it is the right call for heavy storage, workshops, or anywhere you want a hard, durable floor. Whichever you pick, the foundation affects floor framing, door threshold height, and anchoring, so decide before you frame the floor. If you want the foundation priced properly, foundation estimating services and concrete estimating services can build the takeoff from your drawings.

Set piers below your local frost depth. A pier that heaves in winter will rack the floor and crack the wall sheathing.

Shed Floor Framing: Rim Joists and Joist Hangers

Floor framing is the first structural layer above the foundation, and it has to be flat, square, and strong before you frame walls. Work through this sequence and check your dimensions at every step.

  1. Set the skids or piers. Level and square them first. Any twist or out-of-level condition in the foundation shows up as a racked floor later. For a lumber takeoff you need the actual foundation layout, not a guess.
  2. Install the rim joist. The rim joist is the perimeter board that caps the joist ends and carries the wall load above. Fasten it to the skids or the band with galvanized fasteners.
  3. Lay out joists at 16 in. on center. Mark the rim joist with a tape and speed square, and keep the layout consistent from one end. This spacing matches standard sheathing and flooring modules.
  4. Install joist hangers. A joist hanger is a metal connector that supports the joist end where it meets the rim or a beam. Use galvanized hangers and the approved fasteners specified by the manufacturer, not whatever nails are in your pouch. For a full framing takeoff, see framing estimating services.
  5. Deck with 3/4 in. tongue-and-groove plywood or OSB. Glue and nail per the panel manufacturer's schedule. Stagger the panel joints so four corners do not meet at one point.

As a rule of thumb for a typical shed floor, use 2x6 joists for spans up to 8 ft, 2x8 for up to 10 ft, and 2x10 for up to 12 ft. Those numbers assume a common species and grade and a normal floor load; verify against your local code and the lumber supplier's span table before you cut. The floor framing must be square and level before walls go up, because shed wall framing amplifies any error in the deck. These diy shed construction steps—from setting skids to decking—set the stage for accurate wall layout and a shed that stays true for years.

Check diagonal measurements corner to corner before you deck. If the two diagonals are not equal, the floor is not square, and the walls will fight you all the way up.

How to Frame a Shed: Walls, Headers, and Sheathing

Once the floor is square and level, wall framing goes quickly if you build the walls flat on the deck and tilt them up. Each wall has a bottom plate, studs, and a top plate. Studs run at 16 in. on center, and a double top plate ties the walls together at corners and adds stiffness. Blocking goes in at door and window openings to give the sheathing and trim something solid to land on.

A header is a built-up beam over a door or window that carries the load above the opening. Header size depends on the span and the load, so use a span table or an engineer's direction rather than guessing. A short shed door header may be two 2x6s; a wide opening may need two 2x10s or a manufactured header. This is one place where a framing takeoff pays for itself, because header material is easy to under-buy.

Sheathing goes on with 7/16 in. OSB or 1/2 in. plywood. Nail at 6 in. on center at the panel edges and 12 in. on center in the field, and leave a small gap between panels for expansion. Over the sheathing, install house wrap to manage moisture, lapped shingle-style so water sheds down and out. Tape the seams and flash the openings. If you want the moisture-control layer priced correctly, thermal and moisture protection estimating covers the assemblies.

Before you sheath, check that each wall is plumb, square, and braced. A diagonal brace or a temporary stake keeps a wall from folding while you work. Sheathing a wall that is out of plumb locks the error in place.

Build walls on the deck, not in the air. Laying out and nailing a wall flat is faster and safer than framing it standing up.

Shed Roof Framing: Rafters, Ridge Board, and Collar Ties

A gable roof is the most common shed roof, and it starts with a ridge board and common rafters. The ridge board is the horizontal member at the peak; rafters notch over it and bear on the top plate below. Gable end framing closes the triangle at each end so the roof has something to attach to and the siding has a flat surface.

Each rafter gets a plumb cut at the ridge and a birdsmouth cut where it sits on the top plate. The birdsmouth gives the rafter a flat bearing surface and keeps it from rolling. Cut one rafter as a pattern, test-fit it, then use it to mark the rest so every rafter matches. Collar ties hold opposing rafters together and prevent wall spread. Place them in the upper third of the rafter span, and use them in addition to, not instead of, a properly sized ridge and ceiling joists where required.

A shed roof, meaning a single-slope roof, is simpler to frame than a gable but needs correct flashing and drainage at the low edge and where it meets a wall. Slope matters: too little pitch and water backs up under the roofing. For roof assembly pricing, see roofing estimating services.

Roof sheathing is typically 7/16 in. OSB or plywood, with H-clips between panels to keep the edges aligned and support the panel edges between rafters. Nail per the schedule for your wind zone, and leave the panel gaps the manufacturer calls for. If you need a full material list for the roof, a framing takeoff will give you rafter counts, sheathing sheets, and fastener quantities.

Cut and test one rafter before you cut the whole set. A pattern rafter that is off by a quarter inch will throw the ridge and the eaves off across the entire roof.

Send Your Shed Plans for a Free Takeoff

Upload your shed drawings and get a same-day quote, with bid-ready lumber and sheathing quantities back in 24–48 hours.

Same-Day QuotesBid-Ready in 48 Hrs20% Off
Upload plans

Shed Siding Installation: Materials and Methods

Siding choices for a shed come down to wood lap, engineered wood, vinyl, and metal. Wood lap (cedar or pine) offers a traditional look but needs painting or staining every few years. Engineered wood, such as hardboard or OSB with a factory finish, costs less than cedar but swells if edges stay wet. Vinyl is the lowest-maintenance option and snaps together, though it can crack in extreme cold. Metal panels, often 29-gauge or 26-gauge ribbed steel, last decades and go up fast with exposed fasteners and neoprene washers.

Installation follows the same logic regardless of material. Start at the bottom with a starter strip or a level course, then lap each course over the one below so water sheds outward. Follow the manufacturer's lap and nailing pattern exactly; over-driving nails or nailing tight to the sheathing causes buckling. Leave a 1/4 in. gap at inside corners and where siding meets trim to allow for expansion. Flash all openings—windows, doors, and utility penetrations—with self-adhered membrane or metal flashing before siding covers them. Siding attaches to wall sheathing or to furring strips if you need a rain screen. Use hot-dip galvanized, stainless, or ceramic-coated fasteners; plain electroplated nails rust and stain the wall within a season. Corner trim and J-channel finish the edges and direct water away from the framing. Material choice moves shed building cost per square foot more than most beginners expect, so price all four options before you commit. If you need help pricing siding quantities, see our siding estimating services and interior and exterior finishes estimating pages.

Leave a 1/4 in. gap at inside corners and trim—siding expands and contracts with temperature and moisture.

Shed Roofing: Asphalt Shingles, Drip Edge, and Flashing

  1. Install drip edge at the eave. Nail drip edge along the eave edge of the roof deck before underlayment. It protects the sheathing edge and directs water into the gutter or away from the shed.
  2. Roll out underlayment. Cover the deck with felt or synthetic underlayment, lapping each course over the one below. In cold climates, add ice and water shield along the eaves and in valleys.
  3. Add ice and water shield in cold climates. Self-adhered membrane goes at the eave, in valleys, and around penetrations before shingles cover them.
  4. Nail the starter strip. A starter course of shingles or starter strip along the eave sets the first course and seals the edge.
  5. Install shingles in courses. Work bottom to top and stagger the joints. Asphalt shingles are the most common shed roofing, but metal panels are also popular for their lifespan and ease of installation.
  6. Flash wall intersections, valleys, and penetrations. Flashing prevents leaks where the roof meets a wall, at valleys, and around vents or chimneys.
  7. Cap the ridge. Ridge cap shingles or a metal ridge cover finish the peak and close the roof.
  8. Ventilate the roof. A ridge vent, gable vents, or soffit vents reduce moisture and heat buildup in the shed.

Drip edge protects the sheathing edge and directs water into the gutter or away from the shed. For pricing help, see our roofing estimating services and thermal and moisture protection estimating pages.

In cold climates, ice and water shield at the eave is not optional—it is the difference between a dry shed and a rotted deck.

Shed Door and Window Installation

Doors and windows must be flashed and sealed to prevent water intrusion. Before you set the unit, wrap the rough opening with self-adhered flashing or building wrap, then add a sill pan or sloped sill flashing at the bottom. Set the door or window plumb, level, and square, shim it at the hinge and lock points, and fasten through the nailing fin or frame per the manufacturer's instructions. Seal the perimeter with exterior-grade sealant, then install the head flashing and siding so water sheds over the top flange.

Rough opening sizing matters. A door rough opening is typically 2 in. wider and 2.5 in. taller than the door slab; a window rough opening is usually 1/2 in. larger than the window unit. Always confirm against the manufacturer's published rough opening dimensions before framing. Headers are required above every opening to carry roof loads; size them to the span and load, not by guess. Hardware includes hinges, latches, handles, and locks, and all of it should be exterior-rated—stainless or powder-coated steel resists rust far better than interior hardware. Double doors are common for sheds to allow equipment access, and they need a heavier jamb and a center astragal to seal the gap. For takeoff support on openings and millwork, see our openings estimating services and millwork and casework estimating pages.

Never rely on the door or window frame alone to shed water—flash the rough opening and the head before the unit goes in.

Shed Material Calculator: How to Estimate Lumber and Sheathing

Studs = Wall length (ft) × 0.75 + extrasAssumes 16 in. on center; add for corners, openings, and plates.

You can estimate lumber and sheathing for a shed with a few simple formulas. Work through wall framing, floor framing, roof framing, and sheathing one at a time, then round up to whole pieces. A shed material calculator, whether a spreadsheet or an online tool, speeds this up, but always verify quantities with a manual takeoff before ordering.

Example: 10 ft × 12 ft shed with 8 ft walls

  1. Studs. Wall length (ft) × 0.75 gives studs at 16 in. on center. Total wall length = 2 × (10 + 12) = 44 ft. 44 × 0.75 = 33 studs. Add 3 for corners, 4 for a 3 ft door and two windows, and 3 for top plates (44 ft ÷ 16 ft per plate, rounded up). Total ≈ 43 studs. Order 44 to allow for defects.

  2. Sheathing. Wall area = 44 ft × 8 ft = 352 sq ft. Each 4×8 sheet of OSB or plywood covers 32 sq ft. 352 ÷ 32 = 11 sheets. Add 10% waste: 11 × 1.10 = 12.1 → 13 sheets.

  3. Floor joists. Floor length (12 ft) ÷ 16 in. on center + 1 = 12 ÷ 1.333 + 1 = 10 joists. Add rim joists: 2 × 12 ft = 24 linear ft, plus blocking. Order 10 joists at 10 ft, plus 24 linear ft of rim material.

  4. Roofing. Roof area (two slopes) ≈ 2 × 12 ft × 6 ft = 144 sq ft. 144 ÷ 32 = 4.5 sheets. Add 10% waste: 4.5 × 1.10 = 4.95 → 5 sheets.

A material takeoff service can double-check your list and catch missed items like hangers, fasteners, and flashing. For larger sheds or complex roofs, consider a professional material takeoff or quantity takeoff to avoid over- or under-ordering.

Always round up to the next whole sheet or piece, and keep a 10% waste factor for cuts and defects.

How Much Does a Shed Cost?

Shed cost per sq ft = Total cost ÷ Shed floor area (sq ft)Use this to compare options on a common basis.

Shed costs vary widely by size, materials, and whether you build it yourself or hire a pro. For a DIY shed, material costs typically run $15–$40 per square foot. A professionally built shed installed on your site typically runs $50–$150 per square foot. These are ranges only; your actual cost depends on region, site work, and finishes.

Cost FactorTypical RangeNotes
DIY materials (per sq ft)$15–$40Includes lumber, sheathing, roofing, siding, fasteners.
Professional installed (per sq ft)$50–$150Includes labor, equipment, overhead, and profit.
Foundation (skids, piers, or slab)$500–$3,000Slab costs more; skids and piers are less.
Siding (per sq ft)$2–$10Vinyl, wood, fiber cement, or engineered wood.
Roofing (per sq ft)$2–$8Asphalt shingles, metal, or architectural shingles.
Doors and windows$200–$1,500 eachPre-hung doors and insulated windows cost more.
Electrical (if needed)$500–$2,500Includes wiring, outlets, lights, and panel tie-in.
Permit$50–$500Varies by jurisdiction and shed size.

Shed building cost per square foot decreases as size increases because fixed costs like foundation, doors, and permits are spread over more area. For example, a 10×10 shed (100 sq ft) might cost $3,000 in materials ($30 per sq ft), while a 12×20 shed (240 sq ft) might cost $5,500 ($23 per sq ft).

To get a reliable budget, use a budget estimating service or residential estimating service that can price your specific design and local market.

These ranges are for planning only. Get local quotes and verify with a detailed takeoff before committing to a budget.

Common Shed Building Mistakes to Avoid

  • Skipping site prep. Building on uncompacted ground leads to settling and racking. Remove organic material, grade, and compact before placing your foundation.
  • Using untreated lumber at grade. Any wood that contacts concrete or ground must be pressure-treated. Untreated lumber wicks moisture and rots within a few years.
  • Forgetting to flash openings. Doors and windows need head flashing and sill pans. Without flashing, water gets behind the siding and causes rot.
  • Under-sizing headers over wide doors. A 6 ft door opening needs a properly sized header. An undersized header sags and cracks finishes. Check span tables or have an engineer size it.
  • No gap between siding and trim. Siding expands and contracts with temperature. Leave a 1/8 in. gap and caulk it to prevent buckling.
  • Ignoring permit requirements. Many jurisdictions require a shed building permit based on size and height. Skipping it can lead to fines or forced removal. Check local rules before you dig.

If you are unsure about any of these details, a construction estimating consultant can review your plans, or an estimate review service can catch costly omissions before you build.

A few hours of planning and a second opinion on your material list can save you thousands in rework.

Shed Construction Checklist

  • Confirm planning and permits. Verify setbacks, height limits, and whether a building permit is required; check your local jurisdiction before you buy materials.
  • Prep the site. Clear and level the footprint, strip topsoil, and confirm positive drainage away from the shed.
  • Build the foundation. Set skids, piers, or a slab; check level and square diagonally before loading it.
  • Frame the floor. Install rim joists, joists at 16 in. on center, and blocking; verify square by measuring both diagonals.
  • Frame the walls. Lay out plates, cut studs, assemble, and raise; check plumb and square as you go. This is one of the most critical diy shed construction steps, so take your time and verify each wall before moving to the next.
  • Frame the roof. Set the ridge board, cut and install rafters, and add collar ties; verify the ridge is level.
  • Sheath and wrap. Install wall and roof sheathing, then house wrap with laps shingled from bottom to top.
  • Install siding. Start at the bottom, maintain a consistent reveal, and flash openings as you go.
  • Roof it. Install drip edge, underlayment, and shingles; flash valleys and penetrations.
  • Set doors and windows. Shim, plumb, level, and flash the openings before trim.
  • Trim and finish. Install corner boards, fascia, and rake trim, then caulk and paint.
  • Inspect after the first rain. Walk the interior and check the floor, wall bases, and roof penetrations for water intrusion.

Use a construction scheduling service to sequence these steps and keep the project on schedule. A written checklist also helps you track material orders and stay within budget, especially on projects by type where shed work is one line item among many. Verify dimensions and squareness at every stage; catching a 1/4 in. error early is far cheaper than rebuilding a wall. When you reach the wall phase, remember that shed wall framing sets the geometry for everything above it, so double-check your layout before you raise the first wall.

Check squareness by measuring diagonals from opposite corners. If they differ by more than 1/4 in. over 12 ft, adjust before sheathing.

When to Get a Professional Estimate or Takeoff

If you are building a shed for a client or as part of a larger project, a professional estimate ensures accurate pricing. It also gives you a defensible basis for change orders and progress billing. For a homeowner-built shed, a material list may be enough, but once labor, permits, and sitework enter the picture, a line-item estimate pays for itself.

If you need a permit, an estimate can support the permit application and budget. Many jurisdictions ask for a construction value or cost breakdown, and a takeoff-backed number is easier to defend than a rough guess. If you are comparing bids from contractors, a third-party takeoff helps you evaluate them. It shows whether a low bid omitted sheathing, flashing, or disposal, and it protects you from scope gaps.

Scope Precision Estimate offers same-day quotes, bid-ready in 48 hours, and 20% off for new clients. Our residential estimating services cover sheds, garages, and accessory structures, while our material takeoff services produce quantity lists you can hand to a lumber yard. For a full project budget, see our construction cost estimating team. A shed material calculator gets you close; a professional takeoff gets you bid-ready.

If your shed is part of a larger scope, get the takeoff before you sign a contract. Retrofitting a missing line item after the fact is harder than pricing it upfront.

Frequently asked questions

How long does it take to build a shed from scratch?

A two-person crew typically builds an 8x10 or 10x12 shed in three to five working days: one day for site prep and foundation, one to two days for floor and wall framing, one day for roof framing and sheathing, and one to two days for siding, roofing, and the door. Weather, inspections, and material deliveries add time. A first-time builder working alone should plan on two to three weekends.

Do I need a permit to build a shed on my property?

It depends on your jurisdiction, the shed size, and whether it has power. Many areas exempt accessory structures under 100 or 200 square feet, but you still have to meet zoning setbacks and height limits, and HOAs often have their own rules. Call your local building department before you buy lumber and ask about size thresholds, setbacks, frost depth, and inspection requirements.

What is the best foundation for a shed?

For most backyard sheds, pressure-treated skids on a compacted gravel pad are the cheapest and simplest option, and they let you move or relevel the building later. Piers or deck blocks work on sloped or soft ground and keep wood off the soil. A reinforced concrete slab costs the most but handles heavy loads, vehicles, and equipment. Compare shed foundation options against your soil, frost depth, and intended use before you commit.

How do I calculate how much lumber I need for a shed?

Work member by member. For walls, add the perimeter in feet and divide by stud spacing, then add two studs per corner, one per opening, and plates at 3x the wall length. For the floor, divide the width by joist spacing and add one, then multiply by the joist length. For rafters, count pairs along the ridge. A shed material calculator or a lumber takeoff service catches the pieces most builders forget.

Can I build a shed without a concrete slab?

Yes. Skid, pier, and gravel-pad foundations are common and usually cheaper than a slab. Build a pressure-treated floor frame with joists on 16-inch centers and cover it with 3/4-inch tongue-and-groove plywood or OSB. Keep wood at least 6 inches above grade, ventilate the crawl space, and use ground-contact-rated lumber anywhere it touches soil. Slabs make sense when you need a rigid floor for heavy tools or equipment.

What is the cheapest way to build a shed?

Keep it small, simple, and gable-roofed. Use pressure-treated skids on a gravel pad instead of a slab, 2x4 wall framing on 16-inch centers, OSB sheathing, and asphalt shingles. Skip windows, run a single door, and buy standard 8-foot lengths to cut waste. Reclaimed or cull lumber can cut cost further if you inspect it for straightness. Cheap framing still has to meet span and header requirements.

How do I frame a shed roof?

Set a ridge board at the peak, then cut common rafters to length with a plumb cut at the ridge and a birdsmouth notch where they bear on the top plate. Space rafters 16 or 24 inches on center depending on span and load, and tie opposing rafters with collar ties in the upper third. Sheathe with 1/2-inch OSB or plywood, then apply underlayment, drip edge, and shingles. Check a rafter span table for your pitch and snow load.

How much does it cost to build a 10x12 shed?

A 10x12 shed (120 square feet) typically runs about $20 to $50 per square foot in materials, or roughly $2,400 to $6,000, depending on foundation type, siding, roofing, doors, and region. Add labor if you hire out framing, roofing, or electrical. A slab, windows, and a steel door push the number toward the high end. Get a material takeoff before you buy so the estimate reflects your actual design.

RH

Written by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review

Keep reading

Send Your Shed Plans for a Free Takeoff

Same-day quotes, bid-ready in 48 hours, and 20% off.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.
Upload plans for a quote
Call Us