Change Order Estimating

Send the change directive, revised sheets, and original contract documents. We return a marked-up, ZIP-code-adjusted cost delta you can attach to a COR or CCO.

24–48 hours for most projectsTypical turnaround
Excel + marked-up PDFsOrganized by CSI section
ZIP-code pricingLocal material and labor
Price confirmed firstBefore any work starts
Sample estimate sheet
Division 03 — ConcreteSample format
Line itemQtyUnitConcrete
Spread footing 8' × 8' × 24"6EA21.3 CY
Slab-on-grade 6" thick4,200SF77.8 CY
Grade beam 18" × 24"320LF35.6 CY
Column pier 30" × 30" × 4'4EA4.4 CY
Equipment pad 10' × 12' × 12"2EA7.4 CY
Total concrete146.5 CY
Illustrative quantities. Waste factor applied as a separate line.
Rebar dowels included

What is change order estimating?

Change order estimating prices the delta between original contract documents and revised drawings, organized by CSI MasterFormat division. We take off only affected quantities—concrete CY, partition LF, device EA—and apply ZIP-code-adjusted material and labor pricing. Deliverables are Excel and PDF backups with marked-up plan sets, typically in 24–48 hours.

  • Quantities are tracked in CY, LF, EA, SF, and tons by CSI division.
  • Typical waste factors for concrete range from 5% to 10%.
  • The most common costly miss is omitted general conditions extension and remobilization.

A change order is not a new project estimate. It is a priced delta: the difference between what the contract documents showed and what the revised drawings now require. You send the change directive or variation request, the revised sheets, and the original drawings and specifications. We isolate the added, deleted, and resequenced work, take off only the affected quantities, and apply ZIP-code-adjusted material and labor pricing. The result is a line-by-line backup you can attach to a COR or CCO without rebuilding the full estimate.

Deliverable
Excel estimate + marked-up PDF plans
Organized by
CSI MasterFormat section
Turnaround
24–48 hours for most projects
Pricing
ZIP-code-adjusted material and labor pricing
Software
Bluebeam Revu, PlanSwift, RSMeans data

We organize every change order by CSI MasterFormat division, matching the original estimate structure, and return Excel and PDF files with marked-up plan sets. Most change orders turn around in 24–48 hours. If you are pricing a design change, a differing site condition, or a field change order, we can also coordinate with your Construction Estimating Services team to keep the original and revised scopes aligned. For changes that affect the project schedule or cash flow, our Project Cost Control & Reporting service tracks the cumulative impact. We also flag when a change should be priced as a standalone estimate, such as a major scope addition that alters the project's square footage or structural system. In those cases, we may recommend our Preliminary & Conceptual Estimating service to establish a new baseline before pricing the delta. Our goal is to give you a defensible number that holds up to owner review, with every quantity traceable to a sheet and detail.

As an outsourced change order estimating company, we treat each request as a self-contained cost breakdown structure: added scope, deleted scope, and the markup percentage applied to each. We read the request for information (RFI) log and addendum set alongside the revised sheets, because a scope change is often defined in writing before it appears in the model. Where a BIM takeoff or on-screen takeoff in Bluebeam Revu or PlanSwift is faster than scaling paper, we use it, then reconcile the quantities against the original estimate. Every backup line carries a unit price, a material cost, and an equipment cost where applicable, so your team can defend the number line by line.

Services

What our change order cost estimating covers

We price the delta, not the whole job. Every takeoff starts with a side-by-side review of the original and revised documents. We tag each line as added, deleted, or modified, then build the cost from the affected quantities only. That keeps the change order defensible and avoids double-counting work already in the base contract.

Concrete & Rebar Delta

Added or deleted concrete volume and rebar tonnage from revised foundation, slab, or grid dimensions.

CY · tons

Partition & Framing Changes

Added or relocated interior partition LF by wall type, including head, base, and jamb counts.

LF · EA

Door & Window Revisions

Added or deleted door and window units by mark, with frames, hardware sets, and glazing.

EA

Electrical Plan Changes

Added branch conduit LF and device counts from revised electrical plans or panel schedules.

LF · EA

Mechanical & Ductwork Delta

Added ductwork LF and diffuser counts from revised mechanical layouts or equipment schedules.

LF · EA

Fire Protection Adjustments

Added sprinkler head counts and main run LF from revised fire protection plans.

EA · LF

Structural Steel Changes

Added structural steel tonnage and connection count from revised framing plans.

tons · EA

Sitework & Roofing Deltas

Added excavation, backfill, and haul-off CY from revised site plans; added roofing area SF by assembly.

CY · SF

What every change order estimating takeoff includes

  • Added concrete volume and rebar tonnage from revised foundation or slab dimensions
  • Deleted and re-poured slab-on-grade areas from a revised grid layout
  • Added or relocated interior partition LF by wall type, with head, base, and jamb counts
  • Added door and window units by mark, including frames, hardware sets, and glazing
  • Added branch conduit LF and device counts from a revised electrical plan
  • Added ductwork LF and diffuser counts from a revised mechanical layout
  • Added sprinkler head counts and main run LF from a revised fire protection plan
  • Added structural steel tonnage and connection count from revised framing
  • Added excavation CY, backfill CY, and haul-off CY from a revised site plan
  • Added roofing area SF by assembly type from a revised roof plan
  • Labor hours for the added work at the applicable trade rate
  • Equipment hours for added crane, excavator, or pump time
How we work

How we take off a construction change order

  1. Compare original and revised sheetsWe overlay the revised sheets on the original set in Bluebeam Revu, cloud every changed area, and assign a change tag. Each tag gets a CSI section number and a short description. This step catches deleted scope that is easy to miss when you are focused on additions. We also check for subtle changes like shifted grid lines or revised notes that affect multiple sheets.
  2. Isolate added, deleted, and modified workFor each clouded area, we take off only the affected quantities. If a revised grid shifts a column line, we measure the deleted footing and the added footing separately. That prevents double-counting and gives you a clean credit line for removed work. We also track modified items where the quantity changes but the unit remains the same.
  3. Apply ZIP-code-adjusted pricingWe price the delta using RSMeans data adjusted to the project ZIP code. Material and labor rates reflect the local market. For change-order material, we add small-quantity premiums and restock fees where the quantity falls below a full pallet or bundle. We also check for any agreed unit rates in the contract that override market pricing.
  4. Build the labor and equipment backupLabor hours come from the same crew rates used in the base estimate. We add hours for supervision, layout, and cleanup on the changed work. Equipment hours are logged for crane, excavator, or pump time, with mob and demob separated when the trade has already left the site. We also note any productivity adjustments for out-of-sequence work.
  5. Extend general conditions and markupWe calculate the general conditions impact for the added duration: supervision days, temporary facilities, and final cleanup. Then we apply the contract markup structure, stacking subcontractor markup under GC markup where the change order passes through multiple tiers. We also include bond and insurance costs on the increased contract value.
  6. Deliver the marked-up backupYou receive an Excel workbook and PDF organized by CSI division, with the clouded plan set attached. Each line shows quantity, unit, unit cost, and extended total. The summary page separates added cost, deleted credit, and net change so you can attach it directly to a COR or CCO. We also include a one-page summary for owner review.

What we need from you

  • Change directiveThe written directive, variation request, or field order that defines the changed scope. This sets the boundary for what we price.
  • Revised drawingsThe latest issued sheets with revision clouds or delta markers. We need the full sheet, not just the detail, to check adjacent scope.
  • Original contract documentsThe drawings and specifications the base contract was priced from. We compare against these to isolate the delta.
  • Specification sectionsThe spec sections covering the changed work, including any addenda or substitutions. This tells us the specified material and installation method.
  • Contract markup termsYour overhead and profit tiers, subcontractor markup rules, and any agreed unit rates for force-account work.
  • Schedule impact notesAny known resequencing, trade stacking, or out-of-sequence work that affects labor productivity on the change.
Sample output

Sample change order quantity takeoff

A partial takeoff from a revised foundation plan. Each line is tagged to the change directive and priced with ZIP-code-adjusted rates.

Sample format — illustrative quantities
SectionLine itemQtyUnitRef.
03 30 00Spread footing 8' × 8' × 24", 4,000 psi6EAS-101
03 30 00Slab-on-grade 6" thick, WWF 6×6-W2.9×W2.94,200SFS-102
03 30 00Grade beam 18" × 24", #5 top and bottom320LFS-103
03 30 00Column pier 30" × 30" × 4', #6 verticals4EAS-104
03 30 00Equipment pad 10' × 12' × 12", 3,500 psi2EAS-105
03 20 00Rebar, #5, including laps and dowels3.8TONS-101
31 23 16Excavation for revised footings, 4' depth48CYC-101
03 30 00Added concrete pump rental for placement1EAS-101
03 30 00Formwork for added footings, 4' height320SFS-101
03 30 00Curing compound for added slab area4,200SFS-102
03 30 00Vapor barrier under added slab4,200SFS-102
03 20 00Rebar dowels into existing footing24EAS-101

Unit price, units, and how we measure them

Change order quantities are measured from the revised documents and cross-checked against the original takeoff. We use the same units as the base estimate so the delta drops straight into your cost report.

ItemUnitHow it's measured
Added concrete volumeCYMeasured from revised footing, slab, or grade beam dimensions, with formwork and rebar separated
Added pipe or conduitLFMeasured along the revised centerline, including fittings, hangers, and terminations
Added floor or wall finishSFMeasured from the revised room finish schedule, with base and trim taken separately
Added fixtures or devicesEACounted by mark from the revised plan, including rough-in and trim-out labor
Added structural steelTONMeasured from revised framing plans, with connection count and detail weight added
Added excavation or fillCYMeasured from revised site plan contours, with haul-off and backfill separated
Force-account laborHRTracked by trade and cost code for T&M change work, with equipment hours logged separately

Worked example: pricing a revised slab-on-grade area

The dimensions below are illustrative. They show the step-by-step takeoff we run on a change order for a slab area that grew after a revised grid layout. The original contract showed a 60' × 40' slab. The revised sheet shows the same slab extended to 60' × 46'.

Step 1 — Establish the original quantity.

  • Original area: 60.0 LF × 40.0 LF = 2,400 SF.
  • Original volume at 6" thick: 2,400 SF × 0.50 ft = 1,200 CF.
  • Convert to CY: 1,200 CF ÷ 27 = 44.4 CY.

Step 2 — Establish the revised quantity.

  • Revised area: 60.0 LF × 46.0 LF = 2,760 SF.
  • Revised volume: 2,760 SF × 0.50 ft = 1,380 CF.
  • Convert to CY: 1,380 CF ÷ 27 = 51.1 CY.

Step 3 — Isolate the delta.

  • Added area: 2,760 SF − 2,400 SF = 360 SF.
  • Added volume: 51.1 CY − 44.4 CY = 6.7 CY.

Step 4 — Add waste as a separate line.

  • Typical waste factor for slab concrete is 5%. We do not bury it in the quantity.
  • Waste volume: 6.7 CY × 0.05 = 0.34 CY.
  • Priced concrete: 6.7 CY + 0.34 CY = 7.04 CY.

Step 5 — Take off the dependent items.

  • Vapor barrier: 360 SF (no waste, cut and lapped per spec).
  • Welded wire fabric: 360 SF × 1.10 lap allowance = 396 SF.
  • Curing compound: 360 SF.
  • Formwork at the new edge: 60.0 LF × 0.50 ft = 30.0 SF.
  • Dowels into the existing slab: 60.0 LF ÷ 2.0 ft spacing = 30 EA.

Step 6 — Price the delta.

  • Concrete: 7.04 CY × local ZIP-adjusted unit cost.
  • Vapor barrier: 360 SF × unit cost.
  • WWF: 396 SF × unit cost.
  • Curing: 360 SF × unit cost.
  • Formwork: 30.0 SF × unit cost.
  • Dowels: 30 EA × unit cost.
  • Labor: place and finish crew hours for 360 SF, plus layout and cleanup.
  • Equipment: pump or conveyor time for 7.04 CY.

Step 7 — Check for deleted scope.

  • The revised grid removed two original dowel locations. We credit 2 EA and the associated labor.
  • The original slab edge form at the 46' line is deleted: 60.0 LF × 0.50 ft = 30.0 SF credited.

Step 8 — General conditions and markup.

  • If the added 360 SF extends the pour day by half a day, we add supervision and cleanup at the daily rate.
  • Subcontractor markup is applied first, then GC markup on the pass-through amount, then bond and insurance on the net increase.

The final backup shows added cost, deleted credit, and net change on one summary line, with every quantity traceable to the revised sheet and the original contract drawing.

Cost drivers

What drives change order pricing

Relative impact on a typical estimate for this trade, based on estimator judgment. Select a bar for details.

Scale: 1 = minor, 5 = major relative impact. Estimator judgment, not measured data.
Relative impact 5 / 5

Resequencing

When a change pushes work out of sequence, labor productivity drops. A wall that was scheduled before the ceiling grid now has to be built after, which means working around hangers and diffusers. We add productivity loss hours where the change affects unchanged work. We compare the original schedule sequence to the revised sequence to quantify the impact.

Quantity threshold

Small-quantity material carries a premium. A change order for 3 doors costs more per door than the original 30-door package because the supplier adds a restock or small-order fee, and the installer loses the economy of a full run. We add these premiums as a separate line so they are visible and defensible.

Resequencing

When a change pushes work out of sequence, labor productivity drops. A wall that was scheduled before the ceiling grid now has to be built after, which means working around hangers and diffusers. We add productivity loss hours where the change affects unchanged work. We compare the original schedule sequence to the revised sequence to quantify the impact.

Remobilization

If a trade has already left the site, bringing them back costs more than keeping them. We add mob and demob, minimum crew hours, and any equipment re-delivery charges to the change order. We also check if the trade's contract includes a remobilization fee that should be applied.

General conditions extension

Every day added to the schedule carries supervision, temporary facilities, and cleanup cost. We calculate the daily general conditions rate and multiply by the added duration shown on the revised schedule. We also include any additional temporary utilities or security required for the extended period.

Markup stacking

On a pass-through change order, the subcontractor applies markup, then the GC applies markup on top. We model the contract's specific tiers so the total submitted cost matches what the owner will see. We also apply bond and insurance to the increased contract value using the rates stated in the contract.

Material price volatility

Commodity materials like steel, copper, and lumber can fluctuate between the original bid and the change order date. We use current market pricing from RSMeans and note any escalation clauses in the contract. If the change order is priced months after the original bid, we may add an escalation factor.

Permit and inspection fees

Changes that affect permitted scope may require revised permits, re-inspections, or plan review fees. These costs come from the local building department, not the drawings. We flag them and note that you should confirm the local fee schedule with the authority having jurisdiction.

Scope gaps

Common change order scope pricing gaps we catch

Most change orders lose money in the same places. These are the items that hide in the documents or get left out because they are not visible on the revised sheet.

  • General conditions impact: added supervision, temporary power, and cleanup days for the extended duration. This hides in the schedule update, not the drawings. We calculate the daily rate and multiply by the added days.
  • Labor productivity loss on unchanged work from resequencing and trade stacking. The revised plan shows the new layout but not the lost efficiency. We compare the original sequence to the revised sequence and add hours where trades now overlap.
  • Restock, handling, and small-quantity material premiums. These appear on the supplier quote but are easy to drop when the change order is typed up. We add them as a separate line so they are visible and defensible.
  • Remobilization and demobilization of trades that had already left the site. The change directive may not mention it, but the trade's schedule shows they were gone. We add mob and demob plus minimum crew hours.
  • Disposal and dumpster fees for demolished or removed material. Deleted scope often generates waste that is not in the original contract. We add dumpster pulls and disposal fees to the credit side.
  • Permit revision, re-inspection, and plan review fees where the change is permit-affecting. These come from the building department, not the drawings. We flag them and note that you should confirm the local fee schedule with the authority having jurisdiction.
  • Bond and insurance cost on the increased contract value. This is a percentage of the net change and is often overlooked. We calculate it using the rates stated in the contract.
  • Temporary protection and weather enclosure for work performed out of sequence. If a change forces work into a different season, we add temporary heat, hoarding, or dewatering as applicable. These costs are rarely shown on the revised drawings.
  • Extended equipment rental for tools or machines left on site longer than planned. We log daily, weekly, and monthly rental rates and add the difference between the original and revised durations.

Pricing the material cost delta

A change order is priced on the difference between the original specified material and the substituted or added material. We compare four things on every line.

Material comparisonUnit cost basisWaste factor treatmentLabor and lead-time effect
Specified vs. substituted concrete mixCompare 4,000 psi to 5,000 psi on a per-CY basis, including admixtures.Waste stays at the typical 5% for slab; higher for formed walls.Higher strength may require different cure time and finishing window.
Rebar grade change (#5 to #6)Compare per-TON cost including laps and dowels.Typical 3% for rebar cut and lap waste.Larger bar diameter increases tying hours per ton.
Door and hardware substitutionCompare per-EA cost by mark, including frame and hardware set.No waste factor; count by mark.Lead time may drive a temporary door or a schedule extension.
Duct material change (sheet metal to spiral)Compare per-LF cost by diameter, including fittings and hangers.Typical 10% for sheet metal fittings; spiral is lower.Spiral installs faster but requires different hanger spacing.
Sprinkler head substitutionCompare per-EA cost including escutcheon and trim.No waste factor; count by head.Different head type may change the required branch line spacing.
Roof assembly upgradeCompare per-SF cost by assembly, including membrane, insulation, and cover board.Typical 5% for membrane; insulation waste can run higher on cut-up roofs.Additional layers add labor passes and may affect the roof warranty.
Paint system changeCompare per-SF cost by system, including primer and finish coats.No waste factor; price by SF of surface.Extra coat adds a full labor pass and dry time between coats.
Structural steel section changeCompare per-TON cost including connections and detail weight.Typical 2% for steel; connections priced separately.Heavier sections may require a larger crane and different erection sequence.
Codes and standards

Codes, standards, and specs that affect change order quantities

Model codes

Changes that touch permitted scope must be checked against the adopted model code family: IBC for commercial, IRC for residential, IECC for envelope and energy, NEC for electrical, IPC or UPC for plumbing, and NFPA 13 for sprinkler layout. A revised occupancy, a new wall that creates an exit access issue, or an added electrical load can change quantities beyond what the revised sheet shows. Confirm the adopted code edition and any local amendments with the local building department before you price the change, because the same drawing can require different work under different editions.

Industry standards

Standards govern how the changed work must be installed, which changes labor hours and material quantities. ACI 318 and ACI 301 affect concrete mix, curing, and tolerances. ASTM standards cover rebar, welded wire, and membrane materials. SMACNA governs duct construction and hanger spacing. GA-216 covers gypsum board application. NRCA details govern roof assembly and flashing. When a change substitutes a material, check the standard the original spec referenced; the substitute may require a different fastener, spacing, or substrate prep.

Specification sections

Every change order line should trace to a specification section. Division 01 sections 01 26 00, 01 26 13, and 01 26 16 define how the change is priced, what markup applies, and what backup is required. The changed work itself falls under its own division: Division 03 for concrete, Division 05 for steel, Division 08 for doors, Division 09 for finishes, Division 22 and 23 for plumbing and HVAC, Division 26 for electrical, Division 31 for earthwork. Read the section for submittals, testing, and warranty language, because those items carry cost that is not on the drawing.

Local amendments

Adopted code editions and amendments vary by state, county, and city. A jurisdiction may be on an older IBC edition with local amendments for seismic, wind, or energy requirements. Permit revision and re-inspection fees are set locally and are not on the drawings. Confirm the adopted edition, any amendments, and the current fee schedule with the local building department before you submit the change order. If the project is in a state we cover often, our regional pages for Texas, California, Florida, New York, and North Carolina estimating note common local practices, but the authority having jurisdiction is the final source.

Who we provide estimates for

Who uses our change order estimate for contractors

General contractors

You need a defensible backup to submit to the owner or architect. We price the delta and organize it by CSI division so it drops into your COR format. The marked-up plan set shows exactly what changed.

Subcontractors

You are asked to price a change before the GC has issued a formal directive. We take off the affected scope from the revised sheets and give you a number you can submit with confidence, including the small-quantity premiums that protect your margin.

Owners and developers

You receive a change order from the GC and need a second opinion before you approve it. We review the backup, check the quantities against the revised drawings, and flag missing credits or overstated labor.

Architects and engineers

You issue a revision and want to understand the cost impact before the owner asks. We price the change from your revised sheets and return a summary you can share with the project team.

Where we provide estimates

Change Order Estimating in 20 states

Pricing is adjusted to the project ZIP code. Select a highlighted state to see the cities we cover there.

States we coverSelected
TX

Change Order Estimating in Texas

Nation's largest construction market; Sun Belt population growth, data centers, semiconductor plants, and single-family home building.

Texas estimating services
Property types

Change order types we price

The takeoff method changes with the type of change. These are the common ones we see, and what to watch for in each.

Design revision (architect-issued)

Re-takeoff only the clouded areas on the revised sheets; compare to the previous issue, not the original bid set.

Watch for: Check for scope shifted to another sheet; a deleted detail on one sheet may reappear on another.

Differing site condition

Measure actual excavation, backfill, and haul-off quantities from the field survey or geotech report.

Watch for: Confirm the geotech baseline in the contract; rock removal and dewatering may be separate line items.

Owner-directed upgrade

Compare the specified material to the substituted material on unit cost, waste, and labor rate.

Watch for: Watch for lead-time changes and any restocking fee on the original material already ordered.

Field directive / minor change

Price as a lump sum or T&M; track labor hours by trade and equipment hours separately.

Watch for: Confirm the contract's minor-change threshold and whether markup applies to T&M work.

Unforeseen structural repair

Take off added steel tonnage, connection count, and shoring LF from the engineer's repair detail.

Watch for: Check for temporary shoring and engineering hours that belong in the change, not the base contract.

MEP coordination change

Re-measure conduit LF, duct LF, and sprinkler head counts from the revised coordinated model or plans.

Watch for: Watch for hanger and support changes that follow the rerouted runs but are not shown on the plan.

Sitework revision

Re-measure cut, fill, and haul CY from the revised grading plan and compare to the original contours.

Watch for: Confirm whether unsuitable soil disposal is a separate pay item and who bears the haul distance.

Tenant improvement change

Re-takeoff partition LF, door counts, and finish SF by room from the revised tenant plan.

Watch for: Check the landlord's work letter for what is base-building versus tenant scope.

Deliverables

What you receive

  • Excel workbook organized by CSI MasterFormat division, with added, deleted, and net change columns.
  • PDF summary with a cover page showing the change directive number, project name, and total cost delta.
  • Marked-up plan set with revision clouds tagged to each line item in the takeoff.
  • Line-item detail showing quantity, unit, unit cost, and extended total for every affected scope item.
  • Labor and equipment backup with crew rates, hours, and productivity notes for the changed work.
  • General conditions extension calculation showing daily rate and added duration.
  • Markup summary showing subcontractor markup, GC markup, bond, and insurance applied to the net change.
Checklist

Pre-submission checklist for a change order proposal

  • Confirm the change directive number and the contract clause it falls under.
  • Verify the revised sheet is the latest issued revision, not a superseded one.
  • Cloud and tag every changed area on the revised set before taking off.
  • Compare the revised sheet to the original contract drawing, not the previous revision.
  • Separate added, deleted, and modified quantities into distinct columns.
  • Check for scope shifted to another sheet or discipline.
  • Confirm the contract's agreed unit rates for force-account work.
  • Add small-quantity and restock premiums as visible lines.
  • Calculate general conditions for the added duration at the daily rate.
  • Apply subcontractor markup, then GC markup, then bond and insurance.
  • Flag any permit revision or re-inspection fee for the authority having jurisdiction.
  • Attach the marked-up plan set and a one-page summary for owner review.
Client reviews

What clients say about Scope Precision Estimate

10 client reviews
BT
Brian TaylorProject Estimator

Fast, accurate, and dependable estimating service. They understood the project requirements quickly and provided a detailed estimate without unnecessary delays.

RW
Robert WilliamsEstimating Manager

Professional and reliable estimating service. The detailed quantity takeoff helped us reduce pricing errors and submit our proposal on time.

JR
James RichardsonConstruction Project Manager

Excellent construction estimating service. The team provided a comprehensive takeoff and cost breakdown that saved us hours of manual work.

KM
Kevin MartinezCivil Contractor

Great experience from start to finish. The detailed material takeoff and cost estimate helped us prepare a much more accurate project budget.

DT
Daniel ThompsonCommercial Contractor

Very impressed with the accuracy and turnaround time. Their estimate gave us a clear picture of material and labor costs before starting the project.

SH
Steven HarrisCommercial Builder

The quality of the estimate exceeded our expectations. Their detailed breakdown of labor, materials, and project costs gave us confidence in our bid.

FAQ

Change Order Estimating questions

How is a change order estimate different from a full project estimate?

A full estimate prices the entire contract scope from the drawings and specifications. A change order prices only the difference between the original documents and the revised ones. We take off the affected quantities, tag each line as added, deleted, or modified, and price the delta. That keeps the change order defensible and prevents double-counting work already in the base contract. The backup is organized by CSI division so it drops into your COR or CCO format without rework.

What documents do you need to price a change order?

We need the written change directive or variation request, the revised drawings with revision clouds or delta markers, the original contract drawings and specifications, the spec sections covering the changed work, your contract markup terms, and any schedule impact notes. If the change is a differing site condition, send the geotech report or field survey. If the change is a substitution, send the proposed material data so we can compare it to the specified product.

How do you handle deleted scope and credits?

Deleted scope is priced as a credit line, not netted silently into the added cost. We take off the removed quantity, apply the same unit cost basis used in the base estimate, and show it separately. If the deleted material was already ordered or installed, we note the restock or removal cost. The summary page shows added cost, deleted credit, and net change on separate lines so the owner can see the full picture.

Do you include general conditions and markup in the change order?

Yes. Every day added to the schedule carries supervision, temporary facilities, and cleanup cost. We calculate the daily general conditions rate and multiply by the added duration shown on the revised schedule. Then we apply the contract markup structure, stacking subcontractor markup under GC markup where the change passes through multiple tiers, and add bond and insurance on the increased contract value using the rates stated in the contract.

Can you price a change order on a T&M or force-account basis?

Yes. For force-account work, we track labor hours by trade and cost code, and log equipment hours separately. We apply the agreed labor rates and equipment rates from the contract, plus the markup the contract specifies for T&M work. If the contract has a not-to-exceed cap, we note when the tracked hours approach it. The backup shows hours, rates, and extended totals so the owner can audit the ticket.

How do you handle small-quantity material premiums?

Small-quantity material carries a premium because the supplier adds a restock or small-order fee and the installer loses the economy of a full run. We add these premiums as a separate line so they are visible and defensible, rather than burying them in the unit cost. If the change order material falls below a full pallet or bundle, we note the threshold and the premium. That protects your margin without overstating the base unit cost.

What if the change affects work that was already scheduled or installed?

We add remobilization and demobilization for trades that have left the site, minimum crew hours, and any equipment re-delivery charges. If the change forces work out of sequence, we add productivity loss hours where trades now overlap. We compare the original schedule sequence to the revised sequence to quantify the impact. These costs are real but rarely shown on the revised drawing, so we call them out explicitly.

How do you price material price escalation on a change order?

Commodity materials like steel, copper, and lumber can move between the original bid date and the change order date. We use current market pricing from RSMeans adjusted to the project ZIP code and note any escalation clause in the contract. If the change order is priced months after the original bid, we may add an escalation factor and show it as a separate line so the owner can see the basis.

Do you mark up the revised drawings so we can see what changed?

Yes. We cloud and tag every changed area on the revised set in Bluebeam Revu and link each tag to the corresponding line item in the takeoff. You receive the marked-up plan set as a PDF with the Excel workbook. That lets your project manager, superintendent, or owner's representative trace any line in the change order back to the exact location on the drawing.

What is your turnaround time for a change order estimate?

Most change orders turn around in 24–48 hours. Rush service is available for bid day or negotiation deadlines. Turnaround depends on the number of revised sheets, the number of disciplines affected, and whether the original contract documents are complete. A single-discipline change on a few sheets moves faster than a multi-discipline change that touches structural, MEP, and finishes at the same time.

Can you review a change order the GC submitted to us before we approve it?

Yes. Owners and developers use us for a second opinion. We review the GC's backup, check the quantities against the revised drawings, verify the labor and equipment hours, and flag missing credits or overstated quantities. We return a short memo with our findings and a revised total where the backup does not hold. This is similar to our Estimate Review & Second-Opinion Audit service.

How do you handle changes that affect the permit or require re-inspection?

Changes that affect permitted scope may require revised permits, re-inspections, or plan review fees. These costs come from the local building department, not the drawings. We flag them in the change order and note that you should confirm the current fee schedule with the authority having jurisdiction. We do not guess at local fees; we show them as a flagged allowance so you can fill in the confirmed amount.

What does change order cost estimating include beyond the direct cost?

We build the direct cost first: quantities from the revised sheets, a unit price for each line, and material cost, equipment cost, and labor where the work requires it. Then we add the indirect pieces your contract allows, such as general conditions, a markup percentage, and any delay cost tied to resequencing. Each item sits in its own row of the cost breakdown structure, so you can strip out anything the owner disputes without rebuilding the estimate.

Can you act as an outsourced change order estimator on a retainer?

Yes. Send the change order request, the revised sheets, and the original estimate, and we take off only the affected scope. We work in Bluebeam Revu, PlanSwift, and RSMeans data, and we return Excel and PDF files with marked-up plan sets. A retainer suits contractors who issue several change order proposals a month, because we keep your division structure and markup percentage consistent from one change order log entry to the next.

How do you handle change order markup estimating and retainage?

We separate the direct cost from the markup percentage, so you can see the bare cost and the applied rate on separate lines. If your subcontractor quote already carries its own markup, we strip it out and reapply your contract rate to avoid stacking. Retainage is shown as a deduction line rather than buried in the total. Confirm the allowable markup and retainage terms in your contract before you submit.

RH

Reviewed by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning. is a Senior Estimator with more than 15 years of professional experience in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review
  • Project budgeting

Guides on this topic

Send the change directive and revised sheets

Send the change directive, revised sheets, and original contract documents, and we will return a marked-up, ZIP-code-adjusted cost delta you can attach to your COR or CCO.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.