Quick answer
Construction financing is short-term, interest-only debt that funds a project in draws as work is completed, then is repaid or rolled into permanent financing at completion. Qualification usually turns on appraised value, a detailed budget and cost breakdown, verified draws, borrower credit and reserves, and a signed contract with a licensed builder.
- Construction loans disburse on a draw schedule tied to inspected progress, not a lump sum at closing.
- Lenders approve the lesser of appraised value or cost, so your budget and cost breakdown drive the loan amount.
- Most residential programs want 20–25% down or equity, plus 6–12 months of interest reserves.
- A line-item estimate with quantities and unit costs is the fastest way to survive underwriting.
What Is Construction Financing and How Does It Work?
Construction financing is short-term, draw-based debt used to pay for land improvement and vertical construction. Most facilities run 12–24 months and are interest-only during the build, with the full principal due at maturity or converted to permanent debt. The lender does not hand you a lump sum at closing. Instead, it disburses funds in draws as work is completed and inspected, so the outstanding balance tracks the value already built into the project.
The core mechanic is the draw. Your general contractor bills completed work, the lender's inspector verifies it against the approved plans and budget, and the draw administrator releases funds — typically on a monthly cycle. That means your construction cost estimating has to be detailed enough to survive line-by-line inspection, because a soft or lumped cost line is the first thing a draw reviewer questions.
Construction financing is not a permanent mortgage. Construction debt is underwritten on cost and completion risk: can you finish the building for the budgeted number and on schedule? Permanent debt is underwritten on stabilized value and borrower income. The parties differ too. A construction loan involves the borrower/owner, the general contractor, the lender's inspector, the title company, and the draw administrator. Sizing follows the same split: construction loans are usually sized on loan-to-cost ratio (LTC), often 65–80% of total project cost, while permanent loans are sized on loan-to-value ratio (LTV).
Ask for the lender's draw schedule and inspection cadence before you sign. A lender that inspects monthly and pays 10 days later changes your working capital needs more than the interest rate does.
Construction Loan vs Conventional Loan: Key Differences
The table below compares the two on the terms that drive your cash flow and closing costs.
| Feature | Construction Loan | Conventional Mortgage |
|---|---|---|
| Term | 12–24 months, interest-only | 15–30 years, fully amortizing |
| Disbursement | Draws as work is completed and inspected | Single lump sum at closing |
| Interest structure | Interest-only on the drawn balance; often variable | Amortizing principal and interest; fixed or adjustable |
| Collateral | Land plus improvements as built | Existing structure and land |
| Underwriting basis | Loan-to-cost ratio (LTC), cost and completion risk | Loan-to-value ratio (LTV), borrower income and stabilized value |
| Condition to fund | Approved plans, budget, permits, builder contract | Certificate of occupancy or existing structure |
A conventional mortgage funds once at closing and then amortizes over 15–30 years. A construction loan funds in draws and matures in 12–24 months, which is why construction loan interest rates typically run higher than conventional mortgage rates — the lender is carrying completion and repayment risk with no income-producing asset yet.
A conventional loan also requires a certificate of occupancy or an existing structure to appraise and secure. A construction loan is secured before the build starts, against land value plus the improvements as they go in. Many borrowers avoid a second closing and a second set of closing costs by using a construction to permanent loan, which converts the construction balance into a permanent mortgage at completion under one set of documents.
Compare total closing costs, not just the rate. A single-close construction to permanent loan can save a full set of origination, title, and appraisal fees, but the permanent rate is often locked later, so read the conversion terms.
Construction Loan Types: Which One Fits Your Project?
The main categories are construction-to-permanent (single-close), standalone construction loans, renovation loans, owner-builder loans, and hard money construction loans. A construction to permanent loan closes once and converts to a permanent mortgage at completion. A standalone construction loan matures at 12–24 months and requires you to refinance or pay off the balance separately. Renovation loans fund improvements to an existing structure, often tied to the after-repair value. Owner-builder loans let you act as your own general contractor, but lenders usually cap LTC lower and require more documentation.
Hard money construction loans are short-term, asset-based, faster to close, and priced higher. They are used mostly by investors and flippers who need speed or who cannot meet bank documentation requirements. Bank and savings-and-loan construction loans are relationship-based, require full documentation — plans, budget, builder contract, financials — and are typically priced off the prime rate plus a spread.
Government-backed options exist for some residential builds, such as FHA and VA construction-to-perm programs, but they carry stricter borrower and contractor requirements, including approved builder status and capped fees. Commercial projects usually pair a construction loan with a mini-perm or bridge facility, so the construction debt rolls into short-term permanent financing while you lease up or stabilize. Investors weighing speed against rate should run the numbers through real estate investor estimating before choosing a lender type, and developers stacking multiple phases should align the facility with the phase schedule using developer and owner estimating.
Whichever type you choose, the lender will want the same core document: a cost breakdown that answers what is a construction loan in dollar terms, line by line. That breakdown should follow CSI MasterFormat divisions so the reviewer can compare your numbers to regional cost data without translation. Division 01 General Requirements should carry general conditions, permits, temporary utilities, and closeout. Division 03 Concrete should show foundations, slabs-on-grade, and any structural concrete with quantities and unit costs. Division 05 Metals should separate structural steel from miscellaneous metals, because the two are often bid and scheduled differently. Division 26 Electrical should show power, lighting, low-voltage, and any site electrical, and it should note what is base-building versus tenant scope. When the estimate is formatted this way and paired with an AIA G703 continuation sheet, the draw schedule and the loan budget are the same document, and the lender's reviewer has nothing to reconcile. For contractors who carry the loan and the risk, construction financing for contractors works best when the estimate, the schedule of values, and the subcontracts all use the same division structure from day one.
Match the facility to your exit. If you cannot show a take-out lender or a stabilization plan at maturity, a standalone construction loan is a refinance risk, not a financing strategy.
Construction Loan Requirements Lenders Actually Check
Lenders underwrite construction financing on the borrower, the project and the team. Each item below is reviewed before a term sheet is issued.
- Credit score. Most residential construction lenders look for a mid-600s score or higher. Commercial and investor loans often require 700+.
- Down payment. Expect 20–30% of total project cost, plus reserves for interest carry and contingency.
- Debt service coverage ratio (DSCR). Commercial construction typically needs 1.20x–1.35x, calculated on stabilized net operating income (NOI) divided by annual debt service.
- Experience. Lenders review completed projects of similar type, size and complexity. First-time borrowers may need a seasoned partner or guarantor.
- Plans and specs. A complete set is required. Incomplete drawings stall underwriting.
- Scope of work. A written scope of work that matches the plans and specs, with no gaps between trades.
- Construction contract. A signed AIA A101, A102 or equivalent agreement with a fixed or GMP price.
- Line-item budget. A detailed budget with a contingency line, typically 5–10% for commercial work.
- Contractor documentation. License, bond, insurance certificates and, for larger jobs, the GC's financial statements.
- Schedule. A realistic construction schedule that supports the interest carry calculation.
A complete, trade-by-trade budget is the document lenders scrutinize most. If your numbers are thin or missing divisions, expect conditions before closing. A general contractor estimating package and a full construction cost estimating file give underwriters the detail they need to approve without re-trades.
A missing contingency line is one of the most common reasons a construction loan budget gets kicked back. Budget 5–10% for commercial and 10%+ for renovation or adaptive reuse.
How to Qualify for Construction Financing: Step by Step
Qualification runs from pre-approval to closing. Each step builds on the last, and missing documents at any stage slow the file.
- Pre-approval. Submit a short project summary, borrower financials and a target loan amount. The lender issues a preliminary term sheet with rate, fees and leverage.
- Documentation package. Provide plans and specs, the construction contract, a line-item budget, a schedule, entity documents, tax returns and a personal financial statement.
- Underwriting. The lender reviews credit, liquidity, experience and the project's feasibility. This is where the construction loan down payment, usually 20–30% of total project cost, is confirmed along with reserves for interest and contingency.
- Appraisal. For construction, this is typically an as-completed appraisal based on plans and specs. It establishes the stabilized value the loan is sized against.
- Third-party review. Many lenders order a feasibility study or an independent cost estimate to validate the budget before final approval.
- Closing. Loan documents are signed, the title policy is issued, and the first draw is scheduled.
A complete, accurate budget and a realistic schedule are the strongest qualification tools you have. A feasibility study estimating report and a clean budget estimating services package often shorten underwriting by weeks.
Lenders size the loan on the lower of cost or as-completed appraised value. If your budget is inflated, you may qualify for less than you need.
Send Your Plans for a Bid-Ready Estimate
Upload your drawings and we will return a line-item estimate you can hand to a lender for underwriting, with same-day quotes available and most projects bid-ready in 48 hours.
The Construction Loan Draw Schedule and Lien Waivers
A construction loan draw schedule maps every loan disbursement to a milestone of completed work. Lenders build it from the line-item budget, usually organized by CSI MasterFormat divisions, so each draw corresponds to a measurable stage such as foundations, framing, rough-in or drywall. The schedule doubles as a cash-flow plan, and it controls how much interest accrues before the project stabilizes.
Each draw request is a package, not a single form. The core documents are the AIA G702 application and G703 continuation sheet, a sworn statement, conditional and unconditional lien waivers from the GC and its subcontractors, and an inspection report. The lender's inspector verifies that the work billed is actually in place. If work is incomplete or does not match the plans and specs, the draw is reduced or held until the deficiency is corrected.
In states with mechanics lien statutes, a lien agent may be designated on the project so that subcontractors and suppliers can serve preliminary notices. The lender typically requires a title insurance update or endorsement at each draw to confirm no liens have been filed against the property. That endorsement is what protects the lender's position and, indirectly, the owner's equity.
A clean draw schedule depends on a clean schedule of values. If the line items in your schedule of values preparation do not match the budget, draws will be delayed and interest carry will grow. Tight construction cost control keeps billings, waivers and inspections aligned from the first draw to the last.
Never release an unconditional lien waiver before funds clear. Use conditional waivers at the time of the draw request and swap them for unconditional waivers only after payment is received.
Construction Loan Interest Rates and What Drives Them
Construction loan interest rates are almost always variable. Most banks price them off the prime rate plus a margin, and many note a floor below which the rate will not drop even if prime falls. That floor protects the lender if short-term rates collapse mid-build. Because the loan term is short, typically 12 to 24 months, the rate you close at is not the rate you will pay for the whole project.
Several factors move your construction loan interest rate. A higher credit score lowers the margin. A lower loan-to-cost ratio or loan-to-value ratio signals more equity and lowers the rate. Project type matters: a build-to-rent townhome project may price differently than a custom home or a ground-up retail shell. Borrower experience in similar projects is a major lever, and market conditions move the index itself. Expect a spread of several percentage points between the best and worst pricing on the same deal.
Interest is usually paid monthly on the outstanding balance, not on the full committed amount. Some lenders allow an interest reserve, meaning they set aside a portion of the loan to cover interest payments during construction. If you take a reserve, you are borrowing money to pay interest on money you borrowed, so the total cost rises.
Hard money construction loans carry higher rates and points than bank loans. They close faster and rely more on the real estate than on your income, but the trade-off is cost. When you compare offers, look at the annual percentage rate (APR) and every fee, not just the headline rate. A lower rate with a 2% origination fee and monthly draw fees can cost more than a slightly higher rate with clean terms.
Ask each lender for a full fee sheet and a sample interest calculation on a realistic draw schedule before you compare rates.
Construction Financing Cost per Square Foot: What to Expect
Lenders do not quote construction financing cost per square foot. They quote fees and rates. You can still build a per-square-foot number by adding every financing cost and dividing by the building area. That number is useful for feasibility work because it lets you compare financing cost across projects of different sizes and check it against your construction cost estimating budget.
The main components are origination fees (often a percentage of the loan), interest carry during construction, appraisal, title insurance, inspections, and draw fees. Some lenders also charge a commitment fee, a document preparation fee, or a broker fee. Add them all before you divide.
Example (illustrative, not a quote). A 10,000 SF building with a $1,000,000 project cost. Origination fee at 1% = $10,000. Interest carry of $45,000. Appraisal $4,000, title insurance $3,500, inspections $2,500, draw fees $1,500. Total financing cost = $10,000 + $45,000 + $4,000 + $3,500 + $2,500 + $1,500 = $66,500. Per square foot: $66,500 ÷ 10,000 SF = $6.65 per SF. As a percentage of project cost: $66,500 ÷ $1,000,000 = 6.65%.
That percentage is a reasonable planning band for many bank construction loans. Hard money and bridge financing can run higher. Costs vary widely by region, lender, project type, and loan term, so treat any single number as a starting point. Run a construction loan calculator with your own rate, term, and draw schedule to see how sensitive the total is to each input.
Interest carry usually dominates the total, so a one-point rate change often moves your per-square-foot cost more than any single fee.
Using a Construction Loan Calculator to Size Your Loan
A construction loan calculator needs five inputs: total project cost, loan-to-cost ratio, interest rate, loan term, and draw schedule. Loan-to-cost ratio is the loan amount divided by total project cost, including land, hard costs, soft costs, and contingency. The draw schedule matters because interest is charged on the outstanding balance, not the full loan, so a project that draws evenly pays less interest than one that draws all at once.
To size the loan: Loan amount = Total project cost × Loan-to-cost ratio. To estimate interest carry, multiply the average outstanding balance by the rate and the term in years. The average outstanding balance is roughly half the loan amount if draws are evenly spread.
Example (illustrative, not a quote). Project cost $1,000,000, loan-to-cost ratio 70%, interest rate 8%, 12-month term, even draws. Loan amount = $1,000,000 × 0.70 = $700,000. Average outstanding balance ≈ $700,000 ÷ 2 = $350,000. Annual interest = $350,000 × 0.08 = $28,000. Over 12 months, interest carry ≈ $28,000. Monthly interest at the midpoint ≈ $28,000 ÷ 12 = $2,333. If the lender requires an interest reserve, that $28,000 (plus a cushion) is added to the loan, which raises the balance and the interest slightly.
Your calculator should also carry a contingency line, typically 5% to 10% of hard costs, and show whether the interest reserve is inside or outside the loan amount. Online calculators are estimates. Lenders apply their own draw rules, fees, and rate floors, so use the calculator to screen deals, then confirm terms in writing. A detailed budget from a construction cost estimating service makes the inputs far more reliable than a rough square-foot guess.
If your draw schedule is front-loaded, use a higher average balance. Many projects draw 40% or more in the first third of the schedule.
The Construction Financing Process from Application to Close
- Pre-qualification: You provide basic project details—location, scope, estimated cost, and your financial standing—so the lender can indicate whether your request fits its program.
- Application and documentation: You submit the full loan application with plans, specifications, a line-item budget, a construction schedule, contractor information, and personal and business financial statements.
- Underwriting: The lender reviews your credit, liquidity, experience, and the project’s feasibility, often ordering an appraisal and a third-party plan review.
- Appraisal and approval: An appraiser values the completed project; the lender issues a commitment letter with terms, conditions, and any required reserves.
- Closing: You sign the note, mortgage, and construction contract assignment; the lender funds an initial draw and sets up the escrow account.
- Draws: During construction, you request disbursements per the draw schedule, supported by invoices, lien waivers, and inspection reports.
The timeline varies with lender workload, project complexity, and how quickly you return documents, but 30–60 days from application to closing is common. The construction financing process is document-heavy: missing a single item—an updated budget, a signed construction contract, or a schedule that matches the budget—can push closing by weeks. Your plans, specs, budget, and schedule must tell one consistent story, because the lender’s underwriter will cross-check them line by line.
The construction contract is central. It must align with the loan budget: the contract sum, allowances, and payment terms should match the draw schedule and the scope of work the appraiser reviewed. If the contract includes vague allowances or excludes items the budget covers, the lender may require a revised contract or hold back funds. Any change order that affects the budget or scope during construction may need lender approval before work proceeds, and unapproved changes can delay draws or trigger a default. Keep every change documented and priced, and route it to the lender before you commit to the work.
Draw requests are where most of the friction shows up. Each request should tie back to the original line-item budget, show the scheduled value, the work completed to date, and the retainage held, and be supported by conditional lien waivers from every subcontractor who worked that period. The AIA G703 continuation sheet is the standard format for this: it lists each line item with its scheduled value, previous applications, this period, and balance to finish, and it rolls up into the G702 application and certificate for payment. Lenders and title companies read the G703 first because it shows, at a glance, how much of each division has been billed. If your budget was built by division, the G703 practically writes itself. If it was built as a lump sum, you will spend closing week rebuilding it.
Scope gaps between divisions are the other common delay. A missing Division 01 line for temporary power or final cleaning, an underfunded Division 03 concrete package, or a Division 05 metals allowance that does not match the steel subcontract all surface during underwriting or at the first draw. Division 26 electrical is frequently split between a base-building contract and a tenant fit-out, and if the loan budget does not show that split, the reviewer cannot tell which scope the loan is funding. For contractors carrying the loan on their own books, construction financing for contractors adds a second layer: you must match your pay application to the lender's draw cycle, because your subs expect payment on their terms, not the bank's. Aligning your schedule of values, your subcontracts, and the lender's G703 format before closing is the single most effective way to keep draws on schedule.
Lenders fund against the approved budget, not the contract alone. If your contract and budget do not match, expect a funding hold until they do.
Builder Financing Options for Contractors and Developers
Builders and developers rarely rely on a single source of capital. You might use your own equity, a joint venture partner, a private lender, or an institutional bank, depending on project size, risk, and how long you can carry the asset. A joint venture can bring capital and share risk, but it also dilutes control and profit, so the operating agreement matters as much as the money.
A common path for a builder is to use a construction loan to finance a spec home. The lender advances funds as the home progresses, and you repay the loan when the home sells. The risk is obvious: if the market cools or the home sits, you carry interest, taxes, insurance, and maintenance with no buyer. Lenders price that risk into the loan-to-cost ratio, often requiring more equity for spec projects than for pre-sold homes. Your home builder estimating services should reflect a realistic sales timeline and carrying costs, not just hard construction costs.
Some builders offer financing to their clients through an affiliated lender, which can simplify the client’s process and keep the build on schedule. For developers, a construction loan often pairs with mezzanine debt to fill the gap between senior debt and equity; mezzanine carries higher rates and sits behind the senior loan in priority. Strong financials, a track record of completed projects, and clean draw history improve access to better terms, including higher leverage and lower fees. If you are a smaller contractor, small contractor estimating services can help you present a credible budget that supports your loan request.
Common Mistakes in Construction Financing and How to Avoid Them
- Underestimating costs: A budget built from square-foot rules of thumb or outdated pricing often falls short once subcontractor bids arrive. Use a line-item estimate with current material and labor pricing before you apply.
- Missing or inadequate contingency: Lenders typically want to see a contingency line, often 5–10% of hard costs, and will not fund overruns beyond it. Without enough contingency, a single unforeseen condition can stall the project and force you back to the lender for more money.
- Incomplete draw documentation: Missing lien waivers, sworn statements, or invoices is the most common reason draws are delayed. Build a draw package checklist and submit every item the lender requires, every time.
- Contract and budget misalignment: If the construction contract does not match the approved budget, the lender may hold funds or require a revised contract. Reconcile both documents before closing.
- Unapproved change orders: A change order that alters scope or budget without lender approval can create a compliance issue and delay funding. Route every change through the lender before work starts.
- Ignoring lien deadlines: Preliminary notices and lien filing deadlines are strict. Missing one can weaken your payment rights and complicate the lender’s title position.
The best defense against most of these mistakes is a budget you can defend. An estimate review service can catch gaps, double-counted items, and unrealistic allowances before you submit to a lender. If your project is complex, a construction estimating consultant can align the estimate, contract, and draw schedule so the loan closes and funds without surprises.
Lenders do not fund problems; they fund documented progress. Keep your budget, contract, and draw package consistent from day one.
When to Get a Professional Estimate for Construction Financing
Lenders rarely take your word for what a project will cost. For most construction financing, especially on larger or non-residential projects, the bank orders a third-party cost review or requires an independent estimate before it will issue a commitment. Some lenders maintain a list of approved reviewers; others accept a stamped estimate from a qualified estimating firm. Either way, the number that drives your construction loan approval is usually not the one you wrote on the application — it is the one an independent party can defend.
A professional estimate supports underwriting in two ways. First, it validates the total budget against the lender's own cost benchmarks, so the loan amount, equity requirement, and contingency line are sized to reality rather than optimism. Second, it gives the lender a defensible basis for the draw schedule. Draws are released against completed work, and if your scope of work is not broken into measurable line items with quantities and unit costs, the inspector has nothing to measure against and the draw stalls.
Accurate takeoffs and cost estimates also reduce the two risks that sink construction loans: shortfalls and change orders. A shortfall happens when the loan is sized below what the work actually costs, and you cover the gap in cash or stop work. Change orders happen when scope was unclear at underwriting and gets priced later, often at a premium. A line-item estimate with quantities, waste factors, and clear inclusions narrows both gaps before closing.
For owners, developers, and contractors who need a lender-ready number, Scope Precision Estimate offers same-day quotes, bid-ready estimates in 48 hours, and 20% off for new clients. Our construction estimating services produce line-item costs that hold up to third-party review, our quantity takeoff services give the lender measurable quantities for draw verification, and our schedule of values preparation formats those costs into a draw schedule the inspector can walk. Upload your plans through our estimate request page and you will have a document you can hand to the bank.
If you are new to the process, start with a clear answer to what is a construction loan: a short-term, interest-only facility secured by the property and disbursed in draws as work is completed. Lenders underwrite that facility against a cost breakdown that follows CSI MasterFormat divisions, so your estimate should be organized the same way. Division 01 General Requirements carries the general conditions, supervision, temporary facilities, and closeout costs that many borrowers forget to fund. Division 03 Concrete covers foundations, slabs, and structural concrete, and it is often the first large draw. Division 05 Metals covers structural steel and miscellaneous metals, which drive both schedule and early material commitments. Division 26 Electrical covers power, lighting, and related systems, and it is a common source of scope gaps between the electrical subcontract and the general contract. When your estimate is formatted to these divisions and paired with an AIA G703 continuation sheet, the lender's reviewer can trace every line from budget to draw request without asking you to reformat anything. That formatting discipline is what makes construction financing for contractors move faster, because the bank sees a document it already knows how to read.
Ask the lender early whether it requires a third-party estimate or accepts one from your estimator. The format matters as much as the number — a draw schedule built on unmeasured lump sums is the most common reason draws get held up.
Frequently asked questions
Can I use a construction loan to buy land?
Sometimes, but usually not on its own. Many lenders allow land to be rolled into a construction-to-permanent loan if you already own it free and clear or can show the purchase as part of the total project cost. Land loans, which are separate and typically shorter term with higher rates, are the more common route. If the land carries a mortgage, expect the lender to require it be paid off or subordinated before closing. Equity in the land often counts toward your down payment.
What credit score do I need for a construction loan?
Most conventional construction loan programs look for a 680–720 middle credit score, and government-backed options such as FHA and VA construction programs can go lower. Portfolio and community bank programs vary widely and may approve lower scores with larger down payments or additional collateral. Beyond the score, lenders weigh tradeline history, recent derogatory marks, and how many properties you already finance. A 760 score with thin reserves can still be declined.
How long does it take to get approved for construction financing?
Plan on 30–60 days from application to closing for a residential construction loan, and 60–90 days for larger commercial projects. The schedule is driven by the appraisal, title work, environmental review, and underwriting of your budget and builder. Incomplete plans and a vague cost breakdown are the most common causes of delay. Submitting a line-item budget, a signed contract, and a realistic draw schedule up front can cut weeks off the process.
What happens if I go over budget on a construction loan?
You pay the overage, because the lender's commitment is capped at the approved loan amount. Most loans include a contingency line, commonly 5–10% of hard costs, and that contingency is usually the first money spent on overruns. Once it is exhausted, you fund the difference in cash or through a change order that the lender approves. Unapproved scope changes can stall a draw, so document every change before the work is installed.
Do construction loans require a down payment?
Yes, in most cases. Residential construction loans commonly require 20–25% down or equivalent equity, while commercial construction loans often run 25–35% loan-to-cost depending on the asset type and lender. The down payment can sometimes be satisfied by land equity rather than cash. Lenders also typically require interest reserves, closing costs, and a contingency line funded inside the loan budget, so your total cash need is higher than the down payment alone.
Can I be my own general contractor for a construction loan?
Some lenders allow owner-builder or self-contractor construction loans, but the pool is small and the terms are stricter. Expect a larger down payment, a higher rate, a licensed builder of record for permitting, and a detailed cost breakdown you can defend line by line. Lenders also want to see your experience with comparable projects. If you have not built before, a licensed general contractor on the loan documents is usually the only path.
How are construction loan draws inspected?
Each draw request is matched against the approved budget and draw schedule, then verified by a third-party inspector or the lender's own representative who visits the site and confirms the work is in place. The inspector reports the percentage of completion per line item, and the lender funds only the verified portion, minus retainage where applicable. Lien waivers from the general contractor and each paid subcontractor are normally required before the next draw is released.
What is a construction-to-permanent loan and how does it work?
A construction-to-permanent loan, often called a single-close or one-time-close loan, funds the build and then converts to a permanent mortgage at completion without a second closing. During construction you typically pay interest only on drawn funds; at conversion the balance amortizes over the permanent term. The advantage is one set of closing costs and a locked takeout, but the permanent rate is often set at conversion rather than at application, so rate risk stays with you.