Scope Precision EstimateContact Us

Schedule of Values Preparation

Send your plans, specs, and contract budget. We return a line-item schedule of values in Excel and PDF, ready to load into your pay application.

24–48 hours for most projectsTypical turnaround
Excel + marked-up PDFsOrganized by CSI section
ZIP-code pricingLocal material and labor
Price confirmed firstBefore any work starts
Sample estimate sheet
Division 03 — ConcreteSample format
Line itemQtyUnitConcrete
Continuous footing 24" × 12"1,240LF91.9 CY
Spread footing 6' × 6' × 18"42EA84.0 CY
Slab-on-grade 5" thick18,400SF284.0 CY
Elevated deck 8" thick9,800SF241.9 CY
Foundation wall 12" thick2,150SF—
Total concrete701.8 CY
Illustrative quantities. Waste factor applied as a separate line.
Formwork and rebar separate

What is schedule of values preparation?

Schedule of values preparation builds the billing structure for your contract, organized by CSI MasterFormat division with units, quantities, and a defensible basis for percent-complete. We return Excel and PDF files with marked-up plan sets showing where each quantity came from, ready for AIA G702/G703 pay applications and lender review.

  • Line items carry units such as CY, SF, TON, LS, and EA for field-measured work.
  • Typical waste factors for concrete, masonry, and drywall range from 5–10% depending on material and site conditions.
  • The most common costly miss is burying allowances and mobilization in lump sums with no separate billing line.

A schedule of values is the billing structure for your contract, not a copy of the estimate. We build it from the same quantity takeoff that produced your budget, so every line has a unit, a quantity, and a basis you can defend when the architect or lender asks how you arrived at 62% complete on Division 09. If your current SOV was assembled by pasting budget totals into a spreadsheet, the first pay application usually exposes the gaps: allowances buried in lump sums, mobilization billed ahead of field progress, and change orders with no line to land on.

Deliverable
Excel estimate + marked-up PDF plans
Organized by
CSI MasterFormat section
Turnaround
24–48 hours for most projects
Pricing
ZIP-code-adjusted material and labor pricing
Software
Bluebeam Revu, PlanSwift, RSMeans data

You need this service when you are setting up AIA G702/G703 billing, when a lender requires a cost-loaded schedule tied to the CPM, or when a previous SOV triggered a dispute over percent complete. We organize line items by CSI MasterFormat division, matching the format of your estimate and your subcontracts, and we keep unit-price lines open for field-measured work such as rock excavation by CY. Our quantity takeoff services feed the quantities, and our project cost control team can reconcile the SOV against actual job cost each month.

We work from your construction documents, specifications, and contract, and we return Excel and PDF files with marked-up plan sets showing where each quantity came from. Turnaround is 24–48 hours for most projects, with rush available. If you are comparing an in-house schedule of values template against outsourced schedule of values preparation, send us the same takeoff and we will show you where the line-item granularity differs. For a second opinion on an existing SOV, our estimate review services can check it against the contract and the schedule.

Services

What a construction schedule of values covers

We structure the SOV around how you actually bill: general conditions by time elapsed, trade work by installed quantity, allowances held as separate lines, and change orders added as new items rather than absorbed into original scope. Each line carries a CSI section, a unit, a quantity, and a billing basis.

Division 01 General Conditions

General conditions and supervision billed as LS lines by percentage of time elapsed, not front-loaded.

LS · MO

Mobilization and Demobilization

Mobilization capped at 1–3% of contract value for lender-funded work, with demobilization as a separate line.

% · LS

Concrete Trade Breakdown

Concrete broken to placement by CY, formwork by SF contact area, and reinforcing by TON placed.

CY · SF · TON

Unit-Price Lines

Field-measured work such as rock excavation and unsuitable backfill carried as unit-price lines for later measurement.

CY · LF

Allowances

Allowances from 012100 carried as separate SOV lines with the owner's selection date noted for billing.

LS · EA

Change Orders

Change orders set up as new line items with their own CSI section and retainage treatment.

LS · EA

Retainage and Stored Materials

Retainage applied per line on G703 column E; stored materials lines require bill of sale, photos, and insurance rider.

% · EA

Schedule Linkage and Closeout

SOV tied to the CPM so percent-complete reconciles to earned value; closeout, as-builts, O&M, and training as dedicated lines.

LS · MO

What every schedule of values preparation takeoff includes

  • Division 01 general conditions and supervision as LS lines billed by percentage of time elapsed
  • Mobilization and demobilization capped at 1–3% of contract value for lender-funded work
  • Trade lines broken to sub-trade level: concrete by CY placement, formwork by SF, reinforcing by TON
  • Unit-price lines for field-measured work such as rock excavation CY and unsuitable backfill CY
  • Allowances from 012100 carried as separate SOV lines with the owner's selection date noted
  • Change orders set up as new line items with their own CSI section and retainage treatment
  • Retainage applied per line on G703 column E at the rate stated in the contract
  • Stored materials lines with the bill of sale, photos, and insurance rider required to bill them
  • Schedule tied to the CPM so percent-complete reconciles to earned value each period
  • Closeout, as-builts, O&M manuals, and training as dedicated lines rather than absorbed cost
How we work

How to prepare schedule of values from your takeoff

  1. Reconcile contract and budgetWe compare the contract sum, the estimate, and the buyout to find where they disagree. A $40,000 gap between the concrete budget and the concrete subcontract usually means an allowance or a change order was never broken out. We flag every variance before the first pay application goes out. This step catches front-end loading early, when it is still a spreadsheet fix rather than a draw rejection.
  2. Set line-item granularityWe break work to the level your subs bill at. Concrete becomes separate lines for footings CY, slab-on-grade CY, elevated deck CY, formwork SF, and reinforcing TON. If a sub bills per fixture, we set electrical rough-in by EA of device rather than one lump sum for the division. Granularity is set to match your subcontracts, so your PM can reconcile invoices to SOV lines without re-keying.
  3. Assign CSI sectionsEvery line gets a MasterFormat section: 03 30 00 for cast-in-place concrete, 05 12 00 for structural steel, 09 21 16 for gypsum board assemblies. This lets your project manager map SOV lines to subcontracts and change orders without re-keying anything. It also speeds architect review, because the SOV reads in the same order as the specification book and the estimate.
  4. Load quantities and unitsQuantities come from our takeoff, not from the budget total. A slab-on-grade line reads 18,400 SF at 5 inches thick, which equals 284 CY of concrete. Keeping the SF and CY relationship visible lets the architect check your math on the G703. We note the drawing reference for each quantity, so field verification is a matter of opening the right sheet.
  5. Apply billing rulesWe cap mobilization at the contract limit, set general conditions to bill by time elapsed, and separate stored materials from installed work. Retainage is applied per line at the contract rate. Unit-price lines stay open so field overruns can be billed without a change order. These rules are documented line by line, so your billing clerk knows exactly what can be billed each period.
  6. Tie to the CPM scheduleEach SOV line is mapped to the activities that install it. When the scheduler reports 40% complete on elevated deck activities, the SOV line for elevated deck should read 40%. This is the check that catches front-end loading before the lender does. The mapping table becomes your monthly reconciliation tool between job cost, schedule, and pay application.
  7. Deliver Excel and PDFYou receive an Excel file formatted for G703 import, a PDF for submission, and marked-up plan sets showing where each quantity came from. We note any line where the quantity is estimated rather than measured so you know what to verify in the field. The Excel file includes a tab for change orders and a tab for allowance tracking, so your team can update the SOV as the job progresses.

What we need from you

  • Contract and budgetThe executed contract sum, the original estimate, and the buyout log so we can reconcile scope and identify allowances.
  • Plans and specsCurrent architectural, structural, civil, and MEP drawings plus the specification book for CSI section references.
  • SubcontractsExecuted subcontracts and purchase orders showing how each sub bills: lump sum, unit price, or cost-plus.
  • Billing requirementsLender or owner requirements for mobilization caps, stored materials, retainage, and pay application format.
  • ScheduleThe CPM schedule or a milestone list so SOV lines can be mapped to installation activities.
  • Change ordersApproved and pending change orders with their CSI sections so they can be added as new SOV lines.
Sample output

Schedule of values example: sample SOV line items

This is the format we deliver. Each line carries a CSI section, a measurable quantity, a unit, and the drawing reference for the takeoff.

Sample format — illustrative quantities
SectionLine itemQtyUnitRef.
03 30 00Continuous footing 24" × 12", 4,000 psi1,240LFS-101
03 30 00Slab-on-grade 5" thick, WWF 6×6-W2.918,400SFS-102
05 12 00Structural steel, columns and beams, erected86TONS-201
09 21 16Gypsum board, 5/8" Type X, 1-hr wall22,600SFA-301
23 00 00HVAC rough-in, VAV terminal units34EAM-401
26 00 00Electrical rough-in, duplex receptacles412EAE-501
31 23 00Rock excavation, unclassified, unit price320CYC-101
03 30 00Elevated deck 8" thick, 4,000 psi9,800SFS-103
05 12 00Metal deck, 1.5" composite, 20 ga.12,500SFS-202
09 21 16Acoustic ceiling, 2×2 lay-in, ACT8,200SFA-302

Units of measure and billing basis by line type

The unit on the SOV line determines how you bill it. We match units to the subcontract so your pay application and your sub's invoice use the same basis.

ItemUnitHow it's measured
General conditionsLSBilled by percentage of contract time elapsed, not by field progress
MobilizationLSBilled once at notice to proceed, capped per contract or lender requirement
Cast-in-place concreteCYMeasured by placement area and thickness from the structural drawings
FormworkSFMeasured as contact area of concrete surface, separate from concrete CY
Reinforcing steelTONMeasured from placing drawings including laps, hooks, and waste
Structural steelTONMeasured from shop drawings with detailing, fabrication, and erection separated
Gypsum boardSFMeasured by wall and ceiling area, split by board type and fire rating
RoofingSQMeasured in 100 SF squares by system, with insulation and flashing separate
Site pavingSYMeasured by finished surface area, with base course by TON
AllowancesLSHeld as separate lines until the owner makes the selection
Change ordersLSAdded as new lines with their own CSI section and retainage treatment

Worked example: SOV line for a slab-on-grade

This example shows how we build a single SOV line for a concrete slab-on-grade, from dimensions to billing unit. The dimensions are illustrative and do not represent a specific project.

Given: A rectangular building 120 ft long by 80 ft wide. Slab thickness 5 inches, placed on grade. Concrete waste factor 5%. The slab will be billed as a separate SOV line in cubic yards (CY).

Step 1 — Calculate area.

  • Area = 120 ft × 80 ft = 9,600 SF.

Step 2 — Convert thickness to feet.

  • 5 inches ÷ 12 inches/ft = 0.4167 ft.

Step 3 — Calculate volume in cubic feet.

  • Volume = 9,600 SF × 0.4167 ft = 4,000 CF (rounded).

Step 4 — Convert to cubic yards.

  • 1 CY = 27 CF.
  • 4,000 CF ÷ 27 = 148.1 CY (neat).

Step 5 — Apply waste factor.

  • Waste = 148.1 CY × 0.05 = 7.4 CY.
  • Total concrete = 148.1 + 7.4 = 155.5 CY.

Step 6 — Determine SOV line structure.

  • The SOV line will read: "Slab-on-grade, 5" thick, 4,000 psi" | 155.5 | CY | Ref. S-102.
  • Formwork and reinforcing are separate lines: formwork at the slab edge (LF) and reinforcing (TON) from placing drawings.

Step 7 — Note the billing basis.

  • This is a unit-price line: the contractor bills per cubic yard placed and accepted. The quantity 155.5 CY is the estimated total for the contract; actual payment is based on field-measured placement.

Step 8 — Drawing reference.

  • The quantity is taken from structural drawing S-102. The SOV line includes this reference so the architect can verify the takeoff.

This line is then mapped to the CPM activity "Place slab-on-grade" for percent-complete reconciliation. If the field reports 50% of the slab placed, the SOV line should show 50% complete, and the pay application will bill 77.75 CY (155.5 × 0.50).

We apply the same method to every SOV line: measure from the drawings, convert to the billing unit, separate waste, and note the drawing reference. This keeps the SOV defensible when the architect or lender asks how a quantity was derived. For example, if the slab is thickened at column piers, we add that volume separately: four piers, each 3 ft × 3 ft × 1.5 ft deep, yield 4 × 13.5 CF = 54 CF, or 2.0 CY, which is added to the neat quantity before waste. We also check for slab depressions at toilets and floor drains, which add small volumes that are easy to miss. Each of these adjustments is noted on the takeoff sheet and carried into the SOV line so the billed quantity matches the installed work.

Cost drivers

What drives schedule of values cost estimating

Relative impact on a typical estimate for this trade, based on estimator judgment. Select a bar for details.

Scale: 1 = minor, 5 = major relative impact. Estimator judgment, not measured data.
Relative impact 5 / 5

Line-item count

A 40-line SOV is fast to build and fast to approve. A 400-line SOV takes longer but survives audit better because every sub's invoice maps to a line. We set granularity to match how your subs bill, not to a fixed template. For example, if your electrical sub bills per device, we create lines for receptacles EA, switches EA, and light fixtures EA rather than a single lump sum for Division 26.

Line-item count

A 40-line SOV is fast to build and fast to approve. A 400-line SOV takes longer but survives audit better because every sub's invoice maps to a line. We set granularity to match how your subs bill, not to a fixed template. For example, if your electrical sub bills per device, we create lines for receptacles EA, switches EA, and light fixtures EA rather than a single lump sum for Division 26.

Contract type

Lump-sum contracts need fewer lines and more attention to billing rules. Cost-plus contracts need open-book backup for every line. Unit-price work needs lines that stay open all job so field-measured quantities can be billed without a change order. We adjust the SOV structure to the contract type, so billing is straightforward and audit-ready.

Lender requirements

Lender-funded projects often cap mobilization at 1–3%, require stored materials documentation, and tie the SOV to the CPM. Meeting those requirements at setup is faster than fixing rejections during the first draw. We review your loan agreement or draw schedule and build the SOV to match, including any special line items the lender requires.

Allowance count

Each allowance in Division 01 2100 becomes its own SOV line. Projects with owner-selected finishes, fixtures, or equipment can carry a dozen allowance lines, each needing a selection date and a billing rule. We track these separately so you can see what is still uncommitted and what has been selected but not yet purchased.

Change order volume

Every approved change order should become a new SOV line. If they are billed against original lines, percent-complete distorts and retainage gets applied to the wrong scope. We set up the change order structure at the start, with a dedicated change order log and CSI sections, so each change is tracked separately and billed correctly.

Schedule linkage

An SOV tied to CPM activities can be reconciled to earned value each period. Without that link, percent-complete is a judgment call, and judgment calls get challenged by architects and lenders. We map each line to one or more schedule activities, so you can pull a percent-complete from the schedule and compare it to the SOV.

Number of trades and subcontracts

A project with 30 subcontracts needs more SOV lines than one with 10, because each sub bills separately. We build lines that match your subcontract structure, so when a sub sends an invoice, you can code it to a specific SOV line without splitting or combining. This reduces billing errors and speeds up pay application preparation.

Scope gaps

Common gaps we catch in a schedule of values template

Most SOV disputes trace back to setup, not field performance. These are the failures we look for before your first pay application goes out.

  • Front-end loading: general conditions and mobilization billed ahead of field progress. We map these lines to time elapsed and cap mobilization per contract, so the draw matches the work in place. If a lender sees mobilization billed at 10% when the contract allows 2%, the draw gets rejected and your cash flow stalls.
  • Allowances left inside the base lump sum. We pull every 012100 allowance into its own SOV line with a selection date, so owner delays do not stall the whole draw. When an allowance is buried, you cannot bill for it until the owner selects, and you lose visibility into what is still uncommitted.
  • Change orders billed against original lines. We set up new lines with their own CSI sections, which keeps percent-complete and retainage accurate on both original and changed work. If a change order is absorbed into an existing line, your percent-complete on that line no longer reflects the original scope, and retainage gets applied incorrectly.
  • Overhead and profit buried in trade lines. We show them as Division 01 lines so the owner can see the fee separately from the cost of the work. This transparency reduces disputes and makes it easier to negotiate change order markups, because the owner can see your fee structure from the start.
  • Stored materials billed without documentation. We flag the lines that require a bill of sale, photos, and insurance rider before they can be included in the draw. Lenders often reject stored materials without proper backup, so we make sure you know what is required before you submit.
  • Unit-price items missing from the SOV. Rock excavation, unsuitable backfill, and similar field-measured work gets its own line so overruns can be billed without a change order. If these items are not set up as unit-price lines, you either absorb the cost or wait for a change order, which delays payment.
  • Closeout costs absorbed at the end. As-builts, O&M manuals, and training get dedicated lines so they are funded throughout the job, not squeezed into the final draw. When closeout is not broken out, it often gets underfunded, and you end up paying for it out of pocket.
  • Retainage applied incorrectly. We verify that retainage is applied per line on G703 column E at the contract rate, and that it is reduced or released as the contract allows. Incorrect retainage can tie up cash for months and complicate final payment.
  • No reconciliation to job cost. We build the SOV so each line can be tied to your job cost system, allowing you to compare billed amounts to actual costs. Without this, you cannot see overruns or underbilling until it is too late to correct.

Line-item granularity by billing basis

The same scope can be broken out at different levels. This table shows how the SOV line structure changes with the billing basis, using a concrete slab as the example.

Billing basisSOV line structureUnitWhen to use
Lump sum (trade level)Concrete package, including formwork, reinforcing, and placementLSSmall projects or when the sub bills one price for the scope
Lump sum (sub-trade level)Concrete placement, formwork, and reinforcing as separate LS linesLSWhen the GC wants visibility into sub-trade costs but the sub bills lump sum
Unit price (material level)Concrete by CY, formwork by SF, reinforcing by TONCY, SF, TONWhen quantities are field-measured and billed as installed
Unit price (phase level)Slab-on-grade by building or floor, each with its own CY quantityCYWhen the project is phased and billing must follow the phase
Cost-plus (open book)All material, labor, and equipment lines with markup shown separatelyVariousWhen the contract requires open-book accounting and audit
Codes and standards

Codes and standards that affect SOV line items

Model codes

Model codes set minimum requirements that change quantities and therefore SOV line items. The International Building Code (IBC) governs structural concrete, fire ratings, and egress, which drive concrete thickness, rebar, and gypsum board quantities. The International Energy Code (IECC) affects insulation thickness, glazing U-values, and HVAC sizing, adding or changing line items. The National Electrical Code (NEC) dictates device counts, conduit fill, and grounding, which change electrical EA lines. Plumbing codes (IPC/UPC) set fixture counts and pipe sizes. Confirm the adopted code edition with the local building department, as editions vary by jurisdiction.

Industry standards

Industry standards define testing, tolerances, and installation methods that estimators must price. ACI 318 covers reinforced concrete design and minimum thickness, affecting concrete CY and rebar TON. ASTM standards for concrete testing (ASTM C31, C39) and soil compaction (ASTM D698) influence testing allowances in Division 01. SMACNA standards for ductwork fabrication affect sheet metal quantities and insulation. Gypsum Association GA-216 provides installation requirements that impact board SF and fastener counts. NRCA guidelines for roofing systems determine insulation layers and flashing details. These standards are referenced in specifications and must be reflected in the SOV.

Specification sections

CSI MasterFormat sections provide the line-item structure for the SOV. Division 03 30 00 Cast-in-Place Concrete specifies mix designs, reinforcement, and curing, which separate concrete CY from formwork SF and reinforcing TON. Division 05 12 00 Structural Steel defines fabrication, erection, and painting, which may be separate SOV lines. Division 09 21 16 Gypsum Board Assemblies details board type, thickness, and fire rating, driving SF quantities. Division 23 00 00 HVAC and 26 00 00 Electrical specify equipment and devices, often billed by EA. Read these sections to capture all cost components and avoid omitting required items.

Local amendments

Local amendments to model codes change quantities and billing. For example, some jurisdictions require stricter seismic detailing, adding rebar TON; others mandate higher insulation R-values, increasing insulation SF. Fire codes may require additional sprinkler heads, affecting EA counts. Energy codes may mandate solar-ready provisions or EV charging infrastructure, adding electrical lines. Because adopted editions and amendments vary by city and state, always confirm with the local building department. We build the SOV to the code edition referenced in your contract documents, but field verification is your responsibility.

Who we provide estimates for

Schedule of values for contractors and owners

General contractors

You need an SOV that maps to your subcontracts and survives architect review each month. We build it from the same takeoff that produced your budget, so percent-complete reconciles to the CPM and your PM is not defending line items at the draw meeting.

Subcontractors

You bill your GC against their SOV lines, not yours. We build a matching SOV for your scope so your invoice lines up with the prime contract and your retainage is tracked correctly from the first pay application.

Owners and developers

You need to see what is committed, what is allowance, and what is contingency. We separate those categories on the SOV so your draw request shows exactly where the money is going each period.

Lenders and construction managers

You review pay applications against the SOV. We build the SOV to your requirements for mobilization caps, stored materials, retainage, and CPM linkage, which reduces back-and-forth during the draw cycle.

Project managers

You reconcile the SOV to job cost each month. Unit-price lines, change order lines, and allowance lines stay visible so you can see overruns and underbilling before they become a cash problem.

Where we provide estimates

Schedule of Values Preparation in 20 states

Pricing is adjusted to the project ZIP code. Select a highlighted state to see the cities we cover there.

States we coverSelected
TX

Schedule of Values Preparation in Texas

Nation's largest construction market; Sun Belt population growth, data centers, semiconductor plants, and single-family home building.

Texas estimating services
Property types

Project types and how the SOV changes

The structure of the schedule of values shifts with project type, contract form, and billing requirements. These are the patterns we see most often.

Commercial office build-out

SOV lines follow tenant improvements: drywall SF, ACT SF, electrical devices EA, HVAC terminals EA.

Watch for: Watch for landlord allowances and base-building vs. tenant scope separation.

Multifamily residential

SOV broken by building and floor: concrete CY per deck, framing LF per floor, fixtures EA per unit.

Watch for: Watch for unit-type repetition and shared vs. unit-specific costs.

K-12 school renovation

SOV phased by summer break and occupied areas; general conditions billed by phase.

Watch for: Watch for occupied-building restrictions and off-hours work premiums.

Healthcare or hospital addition

SOV includes infection control, ICRA barriers, and medical gas lines as separate items.

Watch for: Watch for owner-furnished equipment and specialized testing requirements.

Industrial warehouse

SOV emphasizes slab SF, structural steel TON, and site paving SY with unit-price rock lines.

Watch for: Watch for soil conditions and rock excavation billed by CY.

Public infrastructure (water/wastewater)

SOV uses unit-price lines for excavation CY, pipe LF, and concrete CY by structure.

Watch for: Watch for prevailing wage, certified payroll, and retainage rules.

Deliverables

What you receive

  • Excel schedule of values organized by CSI MasterFormat division, formatted for G703 import.
  • PDF schedule of values for submission with the pay application.
  • Marked-up plan sets showing where each quantity was measured.
  • Line-by-line billing basis notes: lump sum, unit price, or percentage of time elapsed.
  • Allowance and contingency lines broken out separately from committed scope.
  • Change order structure set up as new lines with their own CSI sections and retainage treatment.
  • CPM mapping table tying each SOV line to the activities that install it.
Checklist

Pre-bid SOV checklist

  • Confirm contract sum matches estimate and buyout
  • List all allowances from Division 01 2100
  • Check mobilization cap in contract or lender requirements
  • Verify retainage rate and application method
  • Identify unit-price items for field measurement
  • Review stored materials requirements and documentation
  • Map SOV lines to CPM activities for earned value
  • Separate general conditions billing by time elapsed
  • Ensure change orders have dedicated SOV lines
  • Check sales tax and freight treatment in material lines
  • Confirm closeout and training costs are included
  • Verify overhead and profit shown as separate Division 01 line
Client reviews

What clients say about Scope Precision Estimate

10 client reviews
RW
Robert WilliamsEstimating Manager

Professional and reliable estimating service. The detailed quantity takeoff helped us reduce pricing errors and submit our proposal on time.

JR
James RichardsonConstruction Project Manager

Excellent construction estimating service. The team provided a comprehensive takeoff and cost breakdown that saved us hours of manual work.

KM
Kevin MartinezCivil Contractor

Great experience from start to finish. The detailed material takeoff and cost estimate helped us prepare a much more accurate project budget.

DT
Daniel ThompsonCommercial Contractor

Very impressed with the accuracy and turnaround time. Their estimate gave us a clear picture of material and labor costs before starting the project.

SH
Steven HarrisCommercial Builder

The quality of the estimate exceeded our expectations. Their detailed breakdown of labor, materials, and project costs gave us confidence in our bid.

MA
Michael AndersonGeneral Contractor

The cost estimate was detailed, accurate, and easy to understand. It helped us prepare our bid confidently and stay competitive without overlooking important costs.

FAQ

Schedule of Values Preparation questions

How detailed should a schedule of values be for a $5 million project?

For a $5 million project, we typically produce 80 to 150 lines. The right number depends on how your subcontractors bill. If a sub bills one lump sum for Division 09, one line works. If they bill per board type and fire rating, we break it out. We match granularity to your subcontracts so your PM can code invoices without splitting lines. Too few lines hides overruns; too many creates administrative work without benefit.

Can you prepare a schedule of values from a budget without a full takeoff?

Yes, but the SOV will be less precise. A budget-based SOV uses allowances and square-foot costs, which work for early billing but may not match field quantities. We prefer to start from a takeoff so each line has a measurable quantity and unit. If you only have a budget, we can still build a defensible SOV with clear notes on which lines are estimated and need field verification.

How do you handle change orders in the schedule of values?

We set up each approved change order as a new SOV line with its own CSI section and retainage treatment. This keeps original scope separate from changed work. When you bill, the change order line shows its own percent-complete. If a change order is billed against an original line, percent-complete distorts and retainage gets misapplied. We also provide a change order log that maps each CO to its SOV line.

What documentation is required to bill stored materials?

Lenders typically require a bill of sale, photographs of the stored materials, and an insurance rider naming the lender as loss payee. Some also require a stored materials affidavit and evidence of segregation from other inventory. We flag the SOV lines that require this backup and note the documentation needed. Without it, the lender may reject the line and delay your draw. Requirements vary, so confirm with your lender.

How does retainage work on the G703?

Retainage is applied per line on G703 column E at the rate stated in your contract, commonly 5% or 10%. It reduces the amount due on each line. Some contracts allow retainage reduction at 50% completion, or separate rates for stored materials versus installed work. We apply the contract rate consistently and note any special provisions. Incorrect retainage can tie up cash for months, so we verify the rate and method before the first pay application.

Can you tie the schedule of values to the CPM schedule?

Yes. We map each SOV line to one or more CPM activities so percent-complete can be reconciled to earned value. For example, an SOV line for elevated deck concrete maps to the activities for formwork, rebar, and concrete placement. When the scheduler reports 40% complete on those activities, the SOV line should read 40%. This mapping catches front-end loading before the lender does and speeds up your monthly billing.

What is front-end loading and why is it a problem?

Front-end loading is billing general conditions, mobilization, or early trade work at a rate that outpaces actual field progress. It improves early cash flow but is often prohibited by contract or lender requirements. Lenders reject draws that show mobilization billed at 10% when the contract caps it at 2%. We set billing rules at setup so your draw matches the work in place, avoiding rejections and keeping your cash flow predictable.

How do you handle allowances in the schedule of values?

Each allowance from Division 01 2100 becomes its own SOV line with a selection date and billing rule. We keep allowances separate from committed scope so the owner can see what is not yet purchased. When the owner selects, the allowance line is converted to a purchase order or subcontract line. If an allowance is left inside the base lump sum, you cannot bill for it until selection, and you lose visibility into uncommitted funds.

What unit-price lines should be included in the SOV?

Any work that is field-measured and paid by unit should have an open SOV line. Common examples include rock excavation by CY, unsuitable backfill by CY, and asphalt paving by TON. These lines stay open all job so overruns can be billed without a change order. If they are not set up, you either absorb the cost or wait for a change order, which delays payment. We identify these items during setup and include them.

How do you ensure the SOV matches the architect's expectations?

We organize the SOV by CSI MasterFormat division, matching the specification book and your estimate. This makes it easy for the architect to review and verify quantities. We also include drawing references for each line, so the architect can check the takeoff. If a line is estimated rather than measured, we note it. This transparency reduces back-and-forth and speeds up approval of your pay application.

Can you prepare a schedule of values for a subcontractor?

Yes. Subcontractors often need an SOV that matches the prime contract's structure so their invoice lines up with the GC's billing. We build a matching SOV for your scope, using the same CSI sections and units. This helps your invoice get approved without rework and ensures your retainage is tracked correctly. Send us the prime contract SOV and your subcontract, and we will align the line items.

What is the turnaround time for SOV preparation?

Most SOVs are delivered within 24 to 48 hours after we receive your contract, budget, plans, and subcontracts. Rush service is available for an additional fee. Complex projects with many allowances or change orders may take longer. We will confirm the schedule when we review your documents. The Excel file is formatted for G703 import, and the PDF is ready for submission with your pay application.

What is a construction schedule of values?

A construction schedule of values is the line-item billing breakdown attached to your contract, usually submitted on AIA G703 and summarized on the G702 application for payment. Each line carries a cost code, a unit of measure, a scheduled value, and columns for work completed this billing period and stored materials. We build it from your takeoff so quantities, not round numbers, drive the values. Confirm the owner's required format and any cost code structure before you submit the first draw.

How do you prepare a schedule of values from a schedule of values template?

A schedule of values template is only a shell until the line items, units, and values are filled from the estimate. We map your takeoff to CSI divisions, assign cost codes and units of measure, separate allowances and unit-price lines, and set retainage per the contract. The result is a schedule of values Excel file plus a PDF for the architect, with a marked-up plan set showing quantity sources. If your template uses Uniformat, we can crosswalk it to MasterFormat 2020.

Can you provide a schedule of values example for a subcontractor?

Yes. A subcontractor SOV is narrower than a general contractor's: it covers only your scopes, so we break out Division 3 concrete, Division 5 metals, Division 9 finishes, or Division 26 electrical at the level your pay application requires. We tie each line to your subcontract value, your own cost codes, and your billing period, and we flag stored materials and retainage. Send the subcontract, your takeoff, and any RFI or submittal log that affects quantities.

RH

Reviewed by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning. is a Senior Estimator with more than 15 years of professional experience in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review
  • Project budgeting

Guides on this topic

Ready to build a defensible schedule of values?

Send your contract, plans, and budget through our get an estimate page, and we will return a CSI MasterFormat SOV in Excel and PDF within 24–48 hours.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.
Upload plans for a quote
Call Us