Scope Precision EstimateContact Us

Primavera P6 Scheduling

Send your plans, specs and contract milestones. We return a logic-driven P6 schedule, coded and resource-loaded, with XER and PDF reporting for owner review.

24–48 hours for most projectsTypical turnaround
Excel + marked-up PDFsOrganized by CSI section
ZIP-code pricingLocal material and labor
Price confirmed firstBefore any work starts
Sample estimate sheet
Division 01 — General RequirementsSample format
Line itemQtyUnitMan-hours
Mobilization and site setup12EA96 HR
Structural concrete activities48EA3,840 HR
Structural steel erection22EA1,760 HR
Exterior enclosure and glazing18EA1,080 HR
MEP rough-in coordination36EA4,320 HR
Total man-hours11,096 HR
Illustrative quantities. Resource loading applied separately.
Calendars assigned per activity

What is Primavera P6 scheduling?

Primavera P6 scheduling is the process of building and maintaining a CPM network in P6 to define activity durations, logic ties, calendars, and float under CSI 01 32 16. Deliverables include native XER files, Gantt charts, activity tables, S-curves, and resource histograms.

  • Activities are measured in days, with logic ties (FS, SS, FF, SF) and lag.
  • Typical float thresholds for critical path are 0–5 days, but confirm with contract.
  • The most common costly miss is unlinked open ends that hide true critical path.

A Primavera P6 schedule is a contractual document. Under CSI 01 32 16, it defines activity durations, logic ties, work calendars and float, and it becomes the measuring stick for progress payments and delay claims. When you need a baseline that survives owner review, a monthly progress update that reconciles actual dates without breaking logic, or a time impact analysis that isolates a single change event, you need a primavera p6 scheduler who works in the tool daily.

Deliverable
Excel estimate + marked-up PDF plans
Organized by
CSI MasterFormat section
Turnaround
24–48 hours for most projects
Pricing
ZIP-code-adjusted material and labor pricing
Software
Bluebeam Revu, PlanSwift, RSMeans data

We are a primavera p6 scheduling company serving general contractors, construction managers and owners. Our primavera p6 schedule development starts with your contract schedule specifications, a work breakdown structure tied to your cost codes, and a basis of schedule memo. We set activity relationships — finish-to-start, start-to-start, finish-to-finish — assign calendars, and run a critical path method pass before anything is submitted. The result is a primavera p6 baseline schedule you can defend at schedule approval.

Ongoing primavera p6 schedule updating covers out-of-sequence progress, remaining durations and schedule variance against the baseline. Where the contract requires earned value management, we tie activities to the schedule of values so cost and schedule reporting reconcile. For delay events, our Schedule Delay & Time Impact Analysis service produces fragnets and window analyses. If you are comparing platforms, see our CPM Scheduling Services and MS Project Scheduling Services pages.

All schedules are built in P6 Professional or P6 EPPM and can be structured as a single project or a multi-project EPS. We deliver native XER and XML file exports plus PDF and Excel reporting, including Gantt charts, activity reports, network diagrams, cost curves and resource histograms. Turnaround is 24–48 hours for most projects, with rush available. Send plans, specs and contract milestones to start.

Services

What our Primavera P6 scheduling company delivers

We build, review and update P6 schedules for construction projects. Every schedule starts with your contract milestones, spec section 01 32 16 and the project's WBS. We set up activity IDs, calendars, logic ties and resource loading, then run schedule checks before delivery. You get native XER files, PDF layouts and Excel exports.

Baseline Schedule Development

Build WBS, activities, durations, logic ties, calendars, and milestones from plans and specs.

Days · Activities

Schedule Updates

Incorporate actual dates, remaining durations, and revise logic for monthly or weekly updates.

Updates · Months

Time Impact Analysis

Insert fragnets for change events, run window analysis, and quantify delay days.

Fragnets · Days

Resource and Cost Loading

Assign labor, equipment, and material resources; link costs to schedule of values.

Hours · Dollars

Schedule Health Checks

Audit for open ends, negative lags, constraints, and out-of-sequence progress.

Checks · Issues

Reporting and Layouts

Produce Gantt charts, activity tables, S-curves, and resource histograms in PDF and Excel.

Reports · Pages

Multi-Project EPS Setup

Structure multiple projects in a single EPS with shared resources and calendars.

Projects · EPS

XER Export and Handoff

Deliver native XER files with audit trail of changes for owner or CM review.

Files · XER

What every primavera p6 scheduling takeoff includes

  • Baseline schedule development with WBS by phase, area and CSI division
  • Activity coding and naming convention aligned to your cost codes
  • Logic ties: FS, SS, FF, SF with lag, reviewed for open ends
  • Calendar setup: project, resource, weather and holiday calendars
  • Milestone tracking: contract, permit, substantial completion, turnover
  • Critical path and near-critical path analysis with float thresholds
  • Resource and cost loading matched to the schedule of values
  • Monthly and weekly schedule updates with actual dates and remaining durations
  • Time impact analysis fragments for change orders and delay events
  • Layout and report production: Gantt, activity table, S-curve, histogram
  • Schedule health checks: open ends, negative lags, constraints, out-of-sequence
  • XER export and handoff with audit trail of changes
How we work

How we build a P6 schedule: WBS, activity relationships and calendars

  1. Review contract and specsWe read Division 01 sections 01 32 16, 01 32 16.13 and 01 32 19 for schedule requirements, float ownership, update frequency and reporting formats. We extract milestones, notice periods and any specified activity codes. We also check the general conditions for liquidated damages and interim milestones that affect logic. We note the required schedule float, any owner-mandated constraints, and the submission and approval cycle for the baseline. This review sets the rules we build to, so the schedule passes review the first time.
  2. Set up WBS and codingWe build a WBS by phase, area, building and CSI division, then create activity ID and naming conventions. Activity codes are mapped to your cost codes and schedule of values. We set up calendars for project, resources, weather and holidays, and assign the correct calendar to each activity to avoid duration distortion. We also define activity code dictionaries for responsibility, area, and phase, so you can filter and group the schedule for reporting. The WBS becomes the backbone for cost and resource loading.
  3. Develop logic and durationsWe sequence activities with FS, SS, FF and SF relationships, applying lag only where the trade sequence requires it. Durations come from your productivity data, RSMeans crew rates or historical averages. We tie procurement, submittal and fabrication activities to installation logic so long-lead items drive the schedule correctly. We also check for open ends and ensure every activity has at least one predecessor and successor. Durations are reviewed against calendar assignments to avoid distortion.
  4. Load resources and costsWe assign crews, equipment and man-hours to activities, then load costs to match the schedule of values. Resource histograms and S-curves are generated to show labor and cost over time. We check for over-allocation and level resources where the contract requires it. We also verify that cost accounts align with your accounting system and that resource units are consistent. This step ensures the schedule supports pay applications and cash flow projections.
  5. Run schedule checksWe run P6 schedule health checks: open-ended activities, dangling logic, negative lags, hard constraints, out-of-sequence progress and excessive float. We verify the critical path and near-critical path using total float thresholds. Any issues are corrected or documented before baseline approval. We also check for activities with unrealistic durations, missing logic, and calendars that don't match the project work week. The output is a clean, logic-driven schedule ready for owner review.
  6. Baseline and deliverWe save the approved baseline in P6 and export the XER file, PDF layouts and Excel reports. You receive a schedule that can be updated monthly without rebuilding logic. We also provide a brief narrative explaining the critical path, major milestones and assumptions. The baseline includes all activity codes, resource assignments, and cost loading. We confirm the baseline is locked and that any subsequent changes are tracked against it.
  7. Update and maintainFor monthly updates, we collect actual start and finish dates, remaining durations and percent complete. We apply retained logic and document out-of-sequence progress. Each update includes a comparison to baseline, variance reports and a revised critical path. We keep an audit trail of who changed dates and when. We also review the schedule for new open ends or negative lags introduced during the update. The result is a current schedule that reflects actual progress and supports timely decision-making.

What we need from you

  • Contract milestonesContract start, substantial completion, turnover and any interim milestones with calendar dates and notice periods.
  • Plans and specsCurrent drawing set and Division 01 sections 01 32 16, 01 32 16.13, 01 32 19 for schedule requirements and float ownership.
  • WBS and cost codesYour preferred WBS structure, activity ID scheme and cost code list for coding and cost loading.
  • Productivity dataHistorical crew rates, man-hours per unit or RSMeans data to set realistic activity durations.
  • Procurement scheduleLong-lead item submittal, fabrication and delivery dates to tie into installation logic.
  • Calendar requirementsWork week, holidays, weather days and any owner-mandated non-work periods.
  • Reporting formatRequired layouts, report types and update frequency per the contract.
Sample output

Sample P6 schedule activity table

This excerpt shows how activities are coded, sequenced and referenced to drawings.

Sample format — illustrative quantities
SectionLine itemQtyUnitRef.
01 32 16Mobilization and site setup1EAC-101
03 30 00Foundation concrete, footings and slab48EAS-201
05 12 00Structural steel erection, columns and beams22EAS-301
08 44 13Exterior glazing and curtain wall18EAA-501
23 00 00HVAC rough-in and ductwork36EAM-601
26 00 00Electrical rough-in and panel installation32EAE-701
22 00 00Plumbing rough-in and fixture set24EAP-801
09 29 00Drywall, tape and finish60EAA-901
09 65 00Flooring installation40EAA-1001
01 32 16.13Project closeout and turnover1EAC-1101

Units and measures we use in P6 schedules

P6 schedules are built from activities, durations and relationships. These are the units you will see in our deliverables.

ItemUnitHow it's measured
Activity durationwork daysElapsed working days from start to finish, excluding non-work periods per calendar.
Activity countEANumber of activities in the schedule, including detail and summary levels.
Relationship countEANumber of logic ties between activities, by type and lag.
Total floatdaysTime an activity can slip before delaying the project finish, per calendar.
Free floatdaysTime an activity can slip before delaying its earliest successor.
Percent complete%Duration-weighted or cost-weighted progress, as specified in the contract.
Man-hoursHRLabor hours loaded to activities for resource histograms and productivity checks.
Cost loading$Dollars assigned to activities, reconciled to the schedule of values.
Milestone datescalendar daysFixed dates for contract milestones, permit approvals and turnovers.

Worked example: Building a baseline schedule for a small commercial building

This example is illustrative. The dimensions and quantities are not from a specific project. We show how a takeoff of activities, durations and logic ties feeds into a P6 baseline schedule. The scope is a 12,000 SF single-story office building.

Step 1: Define the WBS and activity count. We start with the CSI MasterFormat divisions that apply. From Division 03 (Concrete), we identify footings, slab-on-grade and elevated slab. Division 05 (Metals) includes structural steel. Division 08 (Openings) covers doors, frames and glazing. Division 23 (HVAC), 26 (Electrical) and 22 (Plumbing) are the MEP trades.

We estimate the number of activities by area and system:

  • Foundations: 8 activities (excavate, form, rebar, pour footings, cure, form slab, pour slab, cure)
  • Structural steel: 6 activities (shop drawings, fabrication, delivery, erect columns, erect beams, bolt-up)
  • Exterior enclosure: 10 activities (framing, sheathing, windows, curtain wall, roofing, flashing, etc.)
  • MEP rough-in: 18 activities (underground plumbing, overhead duct, electrical rough, etc.)
  • Interior finishes: 14 activities (drywall, tape, paint, flooring, ceilings, etc.)
  • Closeout: 4 activities (punch list, testing, commissioning, turnover)

Total: 60 activities for the core scope. To this we add procurement and submittal activities for long-lead items: steel (2), switchgear (2), HVAC equipment (2), and elevator (2). Total activity count: 70.

Step 2: Set durations from productivity data. Using RSMeans crew rates and historical data, we assign durations. For example, foundation concrete: 48 cubic yards of footings at a crew rate of 12 CY per day = 4 days. Slab-on-grade: 12,000 SF at 3,000 SF per day = 4 days. Steel erection: 22 pieces at 4 pieces per day = 6 days. We round to full work days and assign the project calendar (5-day work week, 8-hour days).

Step 3: Apply logic ties. We sequence activities with finish-to-start relationships. For example, footings must finish before slab-on-grade starts. Steel erection must follow foundation. MEP rough-in follows steel and roof dry-in. We add lag where required: a 2-day cure for concrete, a 5-day lag for steel fabrication after shop drawing approval. We check for open ends and ensure every activity has at least one predecessor and successor.

Step 4: Calculate float and critical path. After running the schedule, we identify the critical path: mobilization → excavation → footings → slab → steel erection → roof → MEP rough-in → drywall → finishes → closeout. Total project duration: 120 work days. Total float on non-critical activities ranges from 2 to 15 days. We flag activities with less than 5 days total float as near-critical.

Step 5: Load resources and costs. We assign crews to each activity. For example, concrete crew: 1 foreman, 3 laborers, 1 equipment operator. Man-hours: 4 days x 8 hours x 5 crew = 160 man-hours. We load costs to match the schedule of values: footings = $45,000, slab = $60,000, steel = $120,000, etc. The total loaded cost matches the SOV.

Step 6: Run schedule checks. We run P6 checks: open ends (0), negative lags (0), constraints (2: a start-on-or-after for permit approval and a finish-on-or-before for owner occupancy). We document these constraints. We also check for out-of-sequence progress and retained logic settings. The schedule passes all checks.

Step 7: Baseline and deliver. We save the baseline in P6 and export the XER file, PDF layouts and Excel reports. The baseline includes all activity codes, resource assignments and cost loading. We provide a narrative explaining the critical path and assumptions. This baseline is ready for owner review and monthly updates.

This example shows the level of detail we apply to every P6 schedule, regardless of project size. The activity count, durations and logic will vary with your specific scope, but the process remains the same.

Cost drivers

What drives the cost of a P6 schedule

Relative impact on a typical estimate for this trade, based on estimator judgment. Select a bar for details.

Scale: 1 = minor, 5 = major relative impact. Estimator judgment, not measured data.
Relative impact 5 / 5

Activity count

A 500-activity schedule takes less time to build and check than a 5,000-activity schedule. More activities mean more logic ties, more calendars and more time spent on schedule health checks. We price by activity count and update frequency. For example, a 2,000-activity schedule may require 40 hours to build and check, while a 5,000-activity schedule may require 100 hours. The effort scales with the number of relationships and the complexity of the WBS.

Activity count

A 500-activity schedule takes less time to build and check than a 5,000-activity schedule. More activities mean more logic ties, more calendars and more time spent on schedule health checks. We price by activity count and update frequency. For example, a 2,000-activity schedule may require 40 hours to build and check, while a 5,000-activity schedule may require 100 hours. The effort scales with the number of relationships and the complexity of the WBS.

Update frequency

Monthly updates require collecting actual dates, applying retained logic and producing variance reports. Weekly updates double the effort. We quote a per-update rate based on the number of activities and the reporting detail required. For a 1,000-activity schedule, a monthly update may take 8–12 hours, while a weekly update may take 16–24 hours. The update process includes data entry, schedule checks, and report generation.

Resource loading

Loading crews, equipment and man-hours to activities adds time, especially when cost loading must reconcile to the schedule of values. If resource leveling is required, that is an additional step. Resource loading for a 1,000-activity schedule may add 10–15 hours, and leveling can add another 5–10 hours. We also check for over-allocation and adjust assignments to match available resources.

Time impact analysis

A time impact analysis fragment for a single change event requires isolating the impacted activities, running a window analysis and documenting the delay. Multiple fragnets or complex windows increase the effort. A single fragnet may take 8–12 hours, while a multi-window analysis can take 20–30 hours. We follow AACE International Recommended Practice 29R-03 for forensic schedule analysis.

Software environment

P6 Professional versus P6 EPPM or Cloud affects setup and export. Multi-project EPS structures require additional coding and security setup. We work in your environment or ours. If you use P6 EPPM, we may need to coordinate with your IT for access and permissions. The setup effort can range from 2–4 hours for a single project to 8–16 hours for a multi-project EPS.

Schedule health check depth

A basic open-end check takes less time than a full forensic review. If your contract requires a detailed schedule health report with metrics like number of open ends, negative lags, and constraints, that adds time. A basic check may take 2–4 hours, while a full review with documentation can take 8–12 hours. We use P6's built-in checks and custom reports to identify issues.

Reporting requirements

Standard reports like Gantt charts and activity tables are quick to produce. Custom layouts, S-curves, and resource histograms require additional setup. If you need reports in specific formats or with specific filters, that adds time. A standard report package may take 2–3 hours, while custom reporting can take 6–10 hours. We work with you to define the reporting needs upfront.

Scope gaps

Common schedule gaps we catch in a P6 schedule review

These are the issues that cause owner rejections, delay claims to fail or updates to break logic.

  • Open-ended activities and dangling logic break the critical path calculation. They hide in activities without successors or predecessors. We run a P6 open-end check and tie every activity to at least one predecessor and successor.
  • Calendars applied per activity rather than a single project calendar distort durations. This shows up when activities use a 5-day calendar while the project runs on a 6-day calendar. We audit calendar assignments and correct mismatches.
  • Out-of-sequence progress and retained logic settings not documented cause incorrect remaining durations. We document the retained logic setting and apply it consistently.
  • Constraints and hard stops override logic and hide float. They appear as start-on-or-after or finish-on-or-before constraints. We list all constraints and justify each one.
  • Float ownership and whether total float is contractually shared or owned by the owner is often missed. We read Division 01 32 16.16 and flag the float ownership clause.
  • Weather-day allowances and non-work periods not reflected in the calendar push the finish date. We add weather calendars based on historical data for the project location.
  • Procurement, submittal and fabrication durations compressed or omitted from the logic cause unrealistic schedules. We tie these activities to installation and verify lead times.
  • Lag types (driving vs. non-driving) and negative lags used to force dates are common. We review every lag and replace negative lags with proper logic.
  • Level-of-effort activities not tied to their driving predecessors create false float. We tie LOE activities to the work they support.
  • Resource and cost loading left unmatched to the schedule of values causes payment disputes. We reconcile loaded costs to the SOV line by line.
  • Baseline not saved in P6 before the first update means variance reporting starts from the wrong date. We save the baseline immediately after approval.
  • XER export settings, layout versioning, and audit of who changed dates and when are often overlooked. We provide a full audit trail with each update.

Schedule deliverable types and software handoff

The table compares the main P6 deliverables you can request, what inputs they need, and what you receive.

DeliverablePrimary inputsTypical turnaroundWhat you receive
Baseline scheduleContract milestones, plans, specs, WBS, productivity data5–10 business daysXER file, PDF Gantt, activity table, resource histogram
Monthly updateActual dates, remaining durations, percent complete, change orders2–3 business daysUpdated XER, baseline vs. actual variance report, revised critical path
Time impact analysisChange order details, impacted activities, as-planned vs. as-built3–5 business daysFragnet, window analysis report, delay days and cost impact
Schedule health checkExisting XER file, contract requirements1–2 business daysReport listing open ends, negative lags, constraints, out-of-sequence progress
Resource-loaded scheduleCrew rates, man-hours, equipment, cost codes7–12 business daysXER with resource assignments, histograms, S-curves, cost loading
Multi-project EPSMultiple project schedules, coding standards, security setup10–15 business daysEPS structure, roll-up reports, cross-project dependencies
Forensic schedule analysisAs-planned schedule, as-built updates, contemporaneous records10–20 business daysDetailed report per AACE 29R-03, with charts and calculations
Codes and standards

Codes and standards that affect P6 scheduling

Model codes

Model codes set the inspection and approval milestones that must appear in your schedule. The International Building Code (IBC) requires special inspections for structural steel, concrete and soils, which add hold points and inspection activities. The International Energy Conservation Code (IECC) drives envelope and mechanical commissioning activities. The National Electrical Code (NEC) and International Plumbing Code (IPC) or Uniform Plumbing Code (UPC) require rough-in inspections before cover. NFPA 13 sprinkler inspections are separate hold points. These code-driven inspections become schedule activities with durations and predecessors. Confirm the adopted code edition with your local building department, as editions vary by jurisdiction.

Industry standards

AACE International Recommended Practice 29R-03 defines forensic schedule analysis methods, including time impact analysis and window analysis. The Associated General Contractors of America (AGC) publishes schedule specifications that many owners adopt. The Construction Industry Institute (CII) provides best practices for schedule development. For resource loading, RSMeans data provides crew rates and productivity factors. ASTM standards for concrete curing and steel erection affect activity durations. These standards influence how we build logic, calculate float and document delays.

Specification sections

Division 01 sections are the primary source for schedule requirements. Section 01 32 16 Construction Schedule defines submittal requirements, activity coding, float ownership and update frequency. Section 01 32 16.13 Network Analysis Schedules specifies CPM requirements, including activity durations and logic ties. Section 01 32 16.16 Float defines who owns total float and how it is used. Section 01 32 19 Project Schedule Updating and Reporting sets update frequency and reporting formats. Section 01 26 00 Contract Modification Procedures and 01 29 00 Payment Procedures tie schedule updates to change orders and pay applications. Read these sections carefully; they change the cost of your schedule.

Local amendments

Local jurisdictions adopt model codes with amendments that can affect scheduling. For example, some cities require additional inspections for fire-rated assemblies or seismic bracing. Others have specific noise ordinances that limit work hours, adding non-work periods to your calendar. Coastal areas may have wind-borne debris requirements that affect glazing installation sequences. Always confirm the adopted code edition and local amendments with the local building department before finalizing your schedule. These amendments can add activities, extend durations or change logic, so they must be reflected in your P6 baseline.

Who we provide estimates for

Who uses our P6 scheduling services

General contractors

You need a baseline schedule that meets owner requirements and supports monthly pay applications. We build and update schedules that align with your cost codes and schedule of values.

Construction managers

You manage multiple projects and need consistent reporting. We build multi-project EPS structures and provide roll-up reports across projects.

Owners and developers

You want to verify that the contractor's schedule is realistic and that milestones are protected. We review submitted schedules and provide independent schedule health checks.

Subcontractors

You need to show your work sequence and durations within the prime schedule. We build fragnets or detailed activities that tie into the master schedule.

Project controls staff

You maintain the schedule and need a clean handoff. We deliver XER files, layouts and documentation so you can update without rebuilding logic.

Where we provide estimates

Primavera P6 Scheduling in 20 states

Pricing is adjusted to the project ZIP code. Select a highlighted state to see the cities we cover there.

States we coverSelected
TX

Primavera P6 Scheduling in Texas

Nation's largest construction market; Sun Belt population growth, data centers, semiconductor plants, and single-family home building.

Texas estimating services
Property types

Project types and what changes in the P6 schedule

Different project types require different scheduling approaches. The table below shows how the scope and logic change for common project types.

Commercial office building

More activities for MEP coordination and tenant fit-out; longer procurement for switchgear and elevators.

Watch for: Watch for owner-furnished equipment and phased occupancy milestones that drive logic.

Healthcare facility

Adds infection control, ICRA barriers, and medical equipment coordination; more inspections and commissioning activities.

Watch for: Watch for interim life safety measures and owner-mandated shutdown windows for utility tie-ins.

K-12 school

Seasonal constraints: work must finish before school year; summer break drives schedule compression.

Watch for: Watch for school board approval milestones and separate contracts for furniture and technology.

Multifamily residential

Repetitive floor cycles; schedule uses typical floor templates and unit turnover milestones.

Watch for: Watch for mock-up unit approvals and phased certificate of occupancy requirements.

Industrial warehouse

Long-lead steel and racking; tilt-up concrete panels or metal building systems drive logic.

Watch for: Watch for owner-supplied racking and conveyor installation that ties to substantial completion.

Data center

High density of MEP activities; commissioning and integrated systems testing are critical path.

Watch for: Watch for redundancy testing and owner security clearances that affect crew access.

Road and bridge

Linear scheduling with multiple work fronts; weather-sensitive activities like paving and striping.

Watch for: Watch for DOT lane closure restrictions and seasonal weight limits on haul routes.

Deliverables

What you receive

  • Native P6 XER file with full logic, calendars and resource loading.
  • PDF layout of the baseline schedule showing Gantt chart, activity table and critical path.
  • Excel export of activities, relationships, resources and costs for analysis.
  • Monthly update reports with baseline vs. actual variance and revised critical path.
  • Time impact analysis fragments for change orders, with window analysis documentation.
  • Schedule health check report listing open ends, negative lags, constraints and out-of-sequence progress.
  • Audit trail of changes showing who modified dates and when, exported from P6.
Checklist

Pre-bid schedule checklist

  • Confirm contract milestones and notice periods.
  • Read Division 01 32 16 for schedule requirements.
  • Identify float ownership clause in 01 32 16.16.
  • Obtain current plans and specs for activity takeoff.
  • Establish WBS and activity ID scheme.
  • Collect productivity data for crew rates.
  • List long-lead procurement items and lead times.
  • Define project calendar: work week, holidays, weather days.
  • Determine update frequency and reporting formats.
  • Check for owner-mandated constraints or interim milestones.
  • Verify software environment: P6 Professional or EPPM.
  • Plan for schedule health checks and audit trail.
Client reviews

What clients say about Scope Precision Estimate

10 client reviews
MA
Michael AndersonGeneral Contractor

The cost estimate was detailed, accurate, and easy to understand. It helped us prepare our bid confidently and stay competitive without overlooking important costs.

AW
Andrew WilsonGeneral Contractor

Highly recommended for construction cost estimating. The quantities were accurate, the pricing was well organized, and the final report was easy to review.

MD
Matthew DavisConstruction Manager

Their construction estimate was thorough and professionally prepared. It made our budgeting process much easier and helped us identify potential cost issues early.

CM
Christopher MillerResidential Builder

We needed a quick and accurate construction cost estimate, and they delivered exactly what we needed. Great attention to detail and a very responsive team.

BT
Brian TaylorProject Estimator

Fast, accurate, and dependable estimating service. They understood the project requirements quickly and provided a detailed estimate without unnecessary delays.

RW
Robert WilliamsEstimating Manager

Professional and reliable estimating service. The detailed quantity takeoff helped us reduce pricing errors and submit our proposal on time.

FAQ

Primavera P6 Scheduling questions

What is the difference between P6 Professional and P6 EPPM, and which do you use?

P6 Professional is a desktop application for single-user or small-team scheduling. P6 EPPM is a web-based enterprise system for multi-project portfolios with role-based security. We work in both. If you need a multi-project EPS with roll-up reporting, we use EPPM. For a single project, Professional is often sufficient. We can deliver XER files that work in either environment. If you use EPPM, we coordinate with your IT for access and permissions.

Can you update a schedule that was built by another company?

Yes. We review the existing XER file, check the logic, calendars and constraints, and then apply updates. We document any issues we find, such as open ends or negative lags, and correct them. If the original schedule is poorly built, we may recommend a rebuild. We provide a schedule health check report before starting updates so you know what we are working with.

How do you handle out-of-sequence progress in P6?

Out-of-sequence progress occurs when an activity starts before its predecessor finishes. In P6, we document the retained logic setting and apply it consistently. We use the 'Progress Override' or 'Retained Logic' setting as specified in the contract. We also review the impact on remaining durations and the critical path. Each update includes a note on any out-of-sequence activities and how we handled them.

What is a time impact analysis and when do I need one?

A time impact analysis (TIA) isolates the schedule impact of a single change event. It uses a fragnet inserted into the schedule at the time of the event, then runs the schedule forward to measure delay. You need a TIA when you have a change order, delay claim or excusable delay event. We follow AACE 29R-03 for forensic schedule analysis. The deliverable includes the fragnet, window analysis and a report of delay days.

Do you provide resource loading and leveling?

Yes. We assign crews, equipment and man-hours to activities, then load costs to match the schedule of values. We generate resource histograms and S-curves. If the contract requires resource leveling, we adjust assignments to resolve over-allocation. We also check that resource units are consistent and that cost accounts align with your accounting system. Resource loading is an additional step and is priced separately.

How do you handle weather days in the schedule calendar?

We create a separate weather calendar based on historical data for the project location. This calendar includes expected non-work days due to weather, such as rain or extreme temperatures. We assign the weather calendar to weather-sensitive activities like concrete pours, paving and roofing. This prevents unrealistic durations and provides a defensible basis for weather delays. The weather calendar is documented in the schedule narrative.

What is the difference between total float and free float?

Total float is the amount of time an activity can slip before it delays the project finish date. Free float is the amount of time an activity can slip before it delays its earliest successor. In P6, both are calculated based on the network logic. We report both in our activity tables. Float ownership is defined in the contract, typically Division 01 32 16.16. We flag the float ownership clause and ensure our schedule reflects it.

Can you build a schedule from a set of plans and specs without a contractor's input?

Yes, but the schedule will be based on our assumptions for durations, crew sizes and sequencing. We use RSMeans data and historical averages to set durations. We document all assumptions in a narrative. This type of schedule is useful for feasibility studies, owner reviews or bid comparisons. For construction execution, we recommend input from the contractor's superintendent and trade partners to validate durations and logic.

What is a schedule health check and why is it important?

A schedule health check reviews the P6 schedule for common issues: open-ended activities, negative lags, hard constraints, out-of-sequence progress and excessive float. These issues can hide the true critical path and make the schedule unreliable for delay analysis. We run P6's built-in checks and custom reports. The output is a report listing each issue with recommendations. We recommend a health check before baseline approval and periodically during updates.

How do you handle multiple contracts or phases in one P6 schedule?

We use a multi-project EPS structure or separate projects within one EPS. Each contract or phase gets its own project with its own WBS, calendars and activity codes. We then create cross-project dependencies where needed. This allows roll-up reporting across the program while maintaining separate baselines. We also set up security so each contractor sees only their project. The EPS structure is defined during setup and documented in the schedule narrative.

What is the turnaround time for a baseline schedule?

For a typical 500-activity schedule, we deliver a baseline in 5–10 business days after receiving all inputs. Larger schedules with 2,000+ activities may take 10–15 business days. Rush service is available for an additional fee. The turnaround depends on the completeness of your input data, the number of review cycles and the complexity of the logic. We provide a firm schedule after reviewing your requirements.

Do you provide training on how to update the schedule in P6?

Yes, we offer optional training sessions for your project controls staff. We cover how to enter actual dates, apply retained logic, run schedule checks and produce reports. Training can be conducted remotely or on-site. We also provide a written procedure document tailored to your schedule. This helps you maintain the schedule between updates and reduces reliance on outside schedulers.

What does a Primavera P6 schedule analysis cover?

A primavera p6 schedule analysis reviews logic, calendars, constraints and float to confirm the schedule is buildable and contract-compliant. We check for open-ended activities, excessive mandatory constraints, negative float, and leads that hide real durations. We compare total float and free float, trace the critical path, and flag schedule quality issues before the owner's representative or architect sees them. Where the contract calls for it, we run a DCMA 14-point assessment and return a written schedule log with recommended corrections.

How does Primavera P6 resource loading work in your schedules?

Primavera P6 resource loading assigns labor crews, equipment and materials to activities so the schedule shows demand over time. We build resource assignments from your productivity rates and work calendar, then run what-if analysis and leveling to see whether the plan fits your crews. The output includes resource histograms and cost curves. If your contract requires cost loading, we tie activities to the schedule of values so earned value management reporting lines up with pay applications. Resource loading is most useful when it is set up before the baseline is approved.

When do I need Primavera P6 delay analysis?

You need primavera p6 delay analysis when a change event, weather, or owner-directed work pushes completion and you intend to request time. We use time impact analysis: insert a fragnet into the accepted baseline, run the schedule forward, and measure the shift in the critical path. Window analysis compares as-built schedule dates against the baseline period by period. Under AIA G702, AIA G703 and AIA G704, or ConsensusDocs and EJCDC forms, the schedule submittal and notice requirements differ, so confirm the contract schedule specifications before filing.

RH

Reviewed by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning. is a Senior Estimator with more than 15 years of professional experience in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review
  • Project budgeting

Guides on this topic

Ready to build or update your P6 schedule?

Send your plans, specs and contract milestones to get a baseline schedule that survives owner review and supports your delay analysis.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.
Upload plans for a quote
Call Us