Scope Precision EstimateContact Us

Schedule Delay & Time Impact Analysis

Send us your baseline schedule, monthly updates, daily reports, and RFI log. We return a forensic time impact analysis with delay days, float consumption, and time-related cost buildup.

24–48 hours for most projectsTypical turnaround
Excel + marked-up PDFsOrganized by CSI section
ZIP-code pricingLocal material and labor
Price confirmed firstBefore any work starts
Sample estimate sheet
Division 01 — Schedule Delay & Time Impact AnalysisSample format
Line itemQtyUnitDelay
Baseline CPM schedule approval1EA1 EA
Monthly schedule updates reviewed18EA18 EA
Delay events analyzed (TIA)9EA9 EA
Critical path activities traced142EA142 EA
Float days consumed (total float)27DA27 DA
Total delay days quantified27 DA
Illustrative quantities. Float consumption calculated per update window.
As-built reconciliation included

What is a schedule delay and time impact analysis?

A forensic comparison of the as-planned critical path against actual events, organized under CSI MasterFormat Division 01 sections 01 32 16.23 and 01 32 16.29. The deliverable is an Excel workbook and PDF narrative with marked-up schedules, showing each activity's start, finish, duration, float, and delay attribution. Turnaround is 24–48 hours for most projects.

  • Units: schedule activities, days of delay, float consumption, and time-related cost periods.
  • Typical float consumption ranges from 5 to 15 days per event, but confirm contract allowances.
  • Most common costly miss: failing to insert delay events at the correct data date, which corrupts the critical path.

A schedule delay analysis is a forensic comparison of the as-planned critical path against what actually happened in the field. You need it when a project misses substantial completion, when change orders extend the schedule, or when you must prove entitlement to an extension of time. The analysis isolates compensable delay, contractor-caused delay, and concurrent delay, then measures how each event consumed total float and pushed the completion date. We apply the critical path method and the method described in AACE International Recommended Practice 29R-03, which is recognized in standard construction contracts such as AIA A201 and ConsensusDocs 200.

Deliverable
Excel estimate + marked-up PDF plans
Organized by
CSI MasterFormat section
Turnaround
24–48 hours for most projects
Pricing
ZIP-code-adjusted material and labor pricing
Software
Bluebeam Revu, PlanSwift, RSMeans data

We build the analysis from the same records a claims reviewer will ask for: the approved baseline schedule, every monthly update with its data date, daily reports, superintendent logs, request for information and submittal logs, change order registers, and weather records. Each delay event is inserted into the schedule at the point it occurred, not retroactively, so the critical path at the time of the event is preserved. We run impacted as-planned and collapsed as-built scenarios, and where the record supports it, a fragnet for each discrete event. Force majeure and differing site conditions are tagged separately so the other party cannot merge them into one bucket.

Our deliverable is organized by CSI MasterFormat Division 01 — 01 32 16.23 Time Impact Analysis and 01 32 16.29 Schedule Delay Analysis — with a marked-up plan set, a written narrative, and an Excel workbook showing each activity's start, finish, duration, float, and delay attribution. Turnaround is 24–48 hours for most projects. If you need a baseline schedule built first, see our CPM Scheduling Services or Primavera P6 Scheduling Services. For projects in Texas, California, Florida, New York, or North Carolina, we apply ZIP-code-adjusted labor and equipment rates to time-related cost roll-ups. For MS Project files, see MS Project Scheduling Services; for a full view of our scheduling work, see Construction Scheduling Services: CPM, P6, MS Project and Delay Analysis.

Services

What the Delay Claim Analysis Covers

We analyze the schedule records you provide and produce a time impact analysis that ties each delay event to specific activities, dates, and float consumption. The scope follows the contract's notice and documentation requirements, typically under 01 32 16.23 and 01 32 16.29.

Baseline Validation

Review approved baseline schedule for logic ties, constraints, calendars, and critical path validity before any delay analysis begins.

Activities · Logic ties · Calendars

Update Analysis

Analyze each monthly update with data date, percent complete, remaining duration, and actual start/finish dates.

Updates · Data dates · Percent complete

As-Built Reconstruction

Rebuild as-built schedule from daily reports, inspection records, and superintendent logs to establish actual sequence and durations.

Days · Activities · Work hours

Critical Path Tracking

Identify critical and near-critical paths at each update, tracking total float and free float consumption by activity and responsible party.

Float days · Paths · Activities

Time Impact Analysis

Insert each delay event into the schedule at the point it occurred, measuring impact on completion date and entitlement.

Delay days · Events · Completion date

Window Analysis

Bracket analysis periods between consecutive schedule updates to isolate delay causes and apportion responsibility.

Windows · Periods · Days

Concurrent Delay Evaluation

Evaluate overlapping owner and contractor delays, apportioning impact using standard industry methods and contract terms.

Days · Parties · Apportionment

Time-Related Cost Roll-Up

Build time-related general conditions costs by period, including supervision, temporary facilities, and equipment standby.

Months · Cost periods · Line items

What every schedule delay & time impact analysis takeoff includes

  • Baseline schedule review and validation of logic ties and constraints
  • Monthly update analysis with data date, percent complete, and remaining duration
  • As-built schedule reconstruction from daily reports and inspection records
  • Critical path and near-critical path identification at each update
  • Total float and free float consumption by activity and responsible party
  • Time impact analysis for each compensable and excusable delay event
  • Window analysis periods bracketed by consecutive schedule updates
  • Concurrent delay evaluation and apportionment between parties
  • Weather day analysis against contract allowance and abnormal weather records
  • Suspension and stop-work period documentation with affected activities
  • Acceleration and mitigation measure review, including added crews and overtime
  • Time-related general conditions cost buildup by period
How we work

How We Perform Time Impact Analysis Services

  1. Collect and validate recordsWe start with the approved baseline schedule and every monthly update in native format — P6 XER or MS Project MPP. We check that each update has a data date, actual start and finish dates, remaining durations, and percent complete. Missing updates are flagged because gaps in the update sequence weaken the window analysis and may force assumptions that reduce recoverable delay days. We also verify that activity IDs and calendars are consistent across updates so that logic ties can be traced.
  2. Reconstruct the as-built scheduleFrom daily reports, superintendent logs, concrete pour tickets, steel erection reports, and inspection records, we build an as-built schedule showing actual start and finish dates for each activity. We reconcile discrepancies between the update files and field records, then document which source controls. For example, if an update shows a concrete pour complete on March 15 but daily reports show it finished March 20, we use the field record and note the variance. This step ensures the as-built critical path reflects actual field progress.
  3. Identify delay events and noticeWe log each delay event from RFIs, change directives, submittal logs, and meeting minutes. For each event we record the date of notice, the contract notice period, the affected activities, and the predecessor-successor logic. Events without timely notice are noted separately because they may affect entitlement. We also cross-reference the event to specific drawing sheets or specification sections to tie the delay to a definable scope item, such as a late structural steel shop drawing for grid lines B–F.
  4. Perform window analysisWe divide the project into windows bracketed by consecutive schedule updates. In each window we compare the as-planned critical path to the as-built critical path, then insert each delay event to measure its impact on the then-current critical path. This preserves the critical path at the time of the event rather than at the end of the project. For example, a delay event in window 5 is inserted into the schedule as it existed at the start of that window, not into the final as-built schedule.
  5. Quantify float consumptionFor each delay event we calculate total float and free float before and after the event. We identify whether the event consumed float, pushed the critical path, or both. Float ownership language in the contract is applied — some contracts treat float as owned by the project, others by the owner. We document the float values at each update and show how many days of total float and free float were consumed by each party's delay events.
  6. Evaluate concurrent delayWe compare owner-caused and contractor-caused delays that occurred in the same window. If both affected the critical path simultaneously, we apportion the delay using the method specified in the contract or the method most defensible for your jurisdiction. Concurrent delay can reduce or defeat recovery. We document the specific activities, dates, and float consumption for each concurrent event and show the apportionment calculation in the workbook.
  7. Roll up time-related costsWe build a daily or monthly time-related cost for extended general conditions: supervision, temporary facilities, equipment rental, and field office. These costs are tied to the delay periods and separated from original contract work. ZIP-code-adjusted rates are applied for labor and equipment. For example, a 30-day delay may include 30 days of superintendent salary, 30 days of temporary power, and 30 days of crane rental, each priced at local rates.

What We Need From You

  • Baseline scheduleThe approved baseline CPM schedule in native format (P6 XER or MS Project MPP) with approval date and any revisions.
  • Monthly updatesEvery monthly schedule update from notice to proceed through the last available data date, including native files and PDFs.
  • Daily reportsSuperintendent daily reports showing manpower, equipment, weather, and work locations for the delay period.
  • RFI and submittal logsComplete logs with dates of issuance, response, and any impact on schedule activities.
  • Change order registerLog of all change orders and directives with dates of notice, pricing, execution, and time extensions granted or requested.
  • Weather recordsDaily weather observations from an on-site station or nearest NOAA reporting location for the project duration.
  • Contract documentsGeneral conditions, supplementary conditions, and any special scheduling specifications including float ownership and notice provisions.
  • Meeting minutesOwner-architect-contractor meeting minutes that document delay discussions, directives, and schedule status.
Sample output

Sample Construction Schedule Analysis Output

The table below shows how we present each delay event with its schedule reference, quantity of delay days, and the source document. Quantities are illustrative.

Sample format — illustrative quantities
SectionLine itemQtyUnitRef.
01 32 16.23Owner-caused delay — late structural steel shop drawings12WDRFI-047
01 32 16.23Owner-caused delay — delayed permit for MEP rough-in8WDCO-012
01 32 16.29Contractor-caused delay — insufficient crew for concrete pours5WDDaily 2024-03-15
01 32 16.29Concurrent delay — weather and owner access conflict3WDWeather log
01 32 16.33Float consumed — electrical rough-in near-critical path7DAUpdate 14
01 32 16.36Acceleration — added second shift for drywall6WDCO-019
01 32 16.23Owner-caused delay — late release of elevator cab design10WDRFI-052
01 32 16.29Contractor-caused delay — rework of fireproofing at Level 34WDDaily 2024-04-02
01 32 16.33Float consumed — HVAC ductwork near-critical path5DAUpdate 16
01 32 16.36Acceleration — overtime for curtain wall installation7WDCO-022

Units and Measurement Basis

Delay analysis uses time-based units tied to schedule activities and contract milestones. The table below shows how each unit is measured and where it appears in the analysis.

ItemUnitHow it's measured
Calendar days of delayDAElapsed days from original completion date to actual or forecast completion
Work days of delayWDWorking days per contract calendar, excluding weekends and holidays
Total floatDADays an activity can slip without delaying project completion
Free floatDADays an activity can slip without delaying its successor's early start
Critical path lengthWDLongest continuous path of activities from start to completion
Activity durationWDOriginal or remaining duration in working days per update
Time-related costUSDDaily or monthly general conditions cost during delay period
Earned valueUSDBudgeted cost of work performed against planned value at data date

Worked Example: Time Impact Analysis for a Late Structural Steel Shop Drawing

This example is illustrative. Dimensions, dates, and quantities are invented to show the calculation sequence, not a real project.

Scenario: A 4-story office building. The approved baseline schedule shows structural steel erection on the critical path. The owner's structural engineer returns the shop drawing for grid lines B–F 12 work days late. The contractor's erection crew is delayed.

Step 1 — Establish the baseline critical path.

  • Baseline schedule: steel erection activity 2,400 LF of beams and columns, duration 20 work days, total float 0.
  • Baseline start: March 1. Baseline finish: March 28 (working days only).

Step 2 — Insert the delay event at the time it occurred.

  • Shop drawing submitted: February 1.
  • Contract review period: 10 work days. Required return: February 15.
  • Actual return: March 3. Delay = 12 work days.
  • The delay event is inserted into the schedule as it existed on February 15, not into the final as-built schedule.

Step 3 — Measure float consumption.

  • At the February 15 update, steel erection had 0 total float and 0 free float.
  • The 12-day shop drawing delay pushes steel erection start from March 1 to March 17.
  • Float consumed: 0 days. Critical path impact: 12 work days.

Step 4 — Check for concurrent delay.

  • Daily reports for February 15–March 3 show the concrete foundation at grid B–F was also 4 work days late due to a contractor-caused rework of anchor bolts.
  • Concurrent delay = 4 work days.
  • Apportionment: owner-caused delay = 12 − 4 = 8 work days; contractor-caused = 4 work days.

Step 5 — Convert work days to calendar days.

  • Contract calendar: 5 work days per week.
  • 8 work days ÷ 5 = 1.6 weeks = 11.2 calendar days. Round to 12 calendar days.

Step 6 — Roll up time-related costs.

  • Extended general conditions: superintendent $1,150/day × 12 days = $13,800.
  • Temporary power: $85/day × 12 days = $1,020.
  • Tower crane rental: $950/day × 12 days = $11,400.
  • Total time-related cost = $26,220.

Step 7 — Document the source.

  • RFI-047, shop drawing transmittal log, daily reports February 15–March 3, and the February 15 schedule update.

Result: 8 work days of owner-caused delay, 4 work days of concurrent contractor-caused delay, 12 calendar days of time extension, and $26,220 in time-related costs. The same method applies to each delay event in the window analysis.

Cost drivers

What Drives the Cost and Outcome of a Delay Claim

Relative impact on a typical estimate for this trade, based on estimator judgment. Select a bar for details.

Scale: 1 = minor, 5 = major relative impact. Estimator judgment, not measured data.
Relative impact 5 / 5

Record quality

The single biggest driver is whether the baseline schedule and every monthly update exist in native format. Missing updates force assumptions that weaken the window analysis and may reduce recoverable delay days. Daily reports that log manpower and weather by location are equally important. For example, if daily reports show 20 electricians on site but the update shows 10, we must reconcile the discrepancy and document which source controls.

Record quality

The single biggest driver is whether the baseline schedule and every monthly update exist in native format. Missing updates force assumptions that weaken the window analysis and may reduce recoverable delay days. Daily reports that log manpower and weather by location are equally important. For example, if daily reports show 20 electricians on site but the update shows 10, we must reconcile the discrepancy and document which source controls.

Notice compliance

Contracts require written notice within a set number of days after a delay event. If notice was late or missing, the analysis must address waiver and estoppel arguments. We document notice dates against the contract requirement for each event. For example, if the contract requires notice within 7 days and the RFI was issued on day 10, we note the late notice and its potential impact on entitlement.

Float ownership

Some contracts state that float is owned by the project, others by the owner, and some are silent. The ownership language determines whether a delay that consumes float but does not push completion is compensable. We apply the contract language and note where it is ambiguous. For example, if the contract says float is project-owned, a delay that consumes 10 days of total float but does not delay completion may not be compensable.

Concurrent delay

When owner-caused and contractor-caused delays overlap on the critical path, recovery can be reduced or eliminated. The method of apportionment — day-by-day, window, or gross — affects the result. We apply the method most defensible for your contract and jurisdiction. For example, if both parties delay the same activity in the same window, we may apportion the delay equally or based on the actual days each party caused.

Update frequency

Monthly updates are standard. Less frequent updates create longer windows with less precision. If updates are missing, we may need to reconstruct intermediate windows from daily reports, which increases analysis time and cost. For example, if updates are quarterly, we may need to reconstruct two intermediate windows per quarter using daily reports and inspection records, adding several days to the analysis.

Schedule file format

Native P6 XER and MS Project MPP files allow full logic and float analysis. PDF-only schedules limit us to visual critical path review. Excel schedules are workable but often lack predecessor-successor logic and constraints. For example, a PDF-only schedule may show a bar chart but not the logic ties, so we cannot calculate float consumption or trace the critical path with certainty.

Contract scheduling specifications

The contract's scheduling specifications dictate the required analysis method, notice periods, float ownership, and submission requirements. We review these provisions to ensure the analysis meets the contract's technical requirements. For example, if the contract requires a time impact analysis for each change order, we perform a separate TIA for each event rather than a single cumulative analysis.

Scope gaps

Common Gaps That Weaken a Schedule Delay Claim

Most delay claims fail not because the delay did not happen, but because the records do not support the analysis. These are the gaps we see most often and how we address them.

  • Missing baseline schedule approval: the baseline is not signed or dated, so the starting point is disputed. We search meeting minutes and transmittals for approval evidence and note the gap.
  • Undated RFIs and submittals: logs without dates cannot establish notice periods or response delays. We cross-reference transmittals and email records to reconstruct dates where possible.
  • Float ownership ignored: the contract says float is project-owned but the analysis treats it as available. We apply the contract language and show the impact on recoverable days.
  • Updates treated as as-built: monthly updates show planned dates, not actual. We reconcile actual start and finish dates from daily reports before building the as-built schedule.
  • Concurrent delay missed: contractor-caused delays in the same window are not documented, so the owner argues the delay was on the contractor. We identify and apportion concurrent delay.
  • Weather records missing: general statements about bad weather are not enough. We require daily observations from an on-site station or nearest NOAA location.
  • Out-of-sequence progress: activities shown as complete in updates actually started late or out of order, masking the true critical path. We compare update logic to field records to detect it.
  • No daily resource loading: daily reports that lack manpower and equipment counts make it difficult to verify productivity and delay impacts. We request detailed logs and cross-check with payroll records.
  • Missing as-built drawings: without marked-up as-built drawings, we cannot verify actual installation dates and locations. We request red-line sets and compare them to schedule updates.

Schedule File Formats and Record Sources

The comparison axis for delay analysis is the schedule file format and the records you provide. Each format limits or enables different parts of the analysis.

Schedule file formatWhat it enablesWhat it limitsRecords needed to supplement
Primavera P6 XERFull logic, float, constraints, calendars, and resource loading analysis.Requires P6 software or conversion; large files may need cleanup.Daily reports, RFI logs, change orders, weather records.
MS Project MPPLogic ties, float, and critical path review; easier to open and share.Resource loading and multiple calendars may be simplified.Same as P6; plus baseline approval transmittals.
Excel scheduleActivity dates, durations, and simple float calculations.Often lacks predecessor-successor logic and constraints.Daily reports and meeting minutes to reconstruct logic.
PDF bar chartVisual critical path and milestone review only.No logic ties, no float calculation, no schedule file manipulation.Native files if available; otherwise daily reports and updates.
No schedule at allRequires reconstruction from daily reports and inspection records.Cannot calculate float or critical path with certainty; assumptions needed.Daily reports, inspection logs, concrete tickets, steel erection reports.
Codes and standards

Codes and Standards That Affect Delay Analysis

Model codes

Delay analysis is not a code-compliance service, but model codes affect the schedule activities and inspection hold points that appear on the critical path. The IBC and IRC set inspection requirements for structural, electrical, plumbing, and mechanical work; each inspection is a schedule activity with a predecessor and successor. The IECC adds envelope and mechanical commissioning activities that can extend the schedule. NEC, IPC/UPC, and NFPA 13 govern electrical, plumbing, and fire protection installations, each with its own rough-in and final inspection sequence. Confirm the adopted code edition with the local building department because inspection durations and sequencing change by edition.

Industry standards

AACE International Recommended Practice 29R-03 is the primary forensic schedule analysis standard. It defines the method, the use of as-planned versus as-built schedules, and the window analysis technique. AACE 38R-06 covers delay analysis documentation. The Construction Industry Institute (CII) publishes best practices for schedule management. The Project Management Institute (PMI) PMBOK and practice standards for scheduling provide definitions for total float, free float, and critical path. ASTM E2921 covers schedule delay analysis terminology. These standards do not set legal entitlement but define the technical method a claims reviewer expects.

Specification sections

Read Division 01 scheduling specifications before starting the analysis. 01 32 16 Construction Schedule defines the baseline and update requirements. 01 32 16.23 Time Impact Analysis specifies the method for each delay event. 01 32 16.29 Schedule Delay Analysis defines the as-built and window analysis requirements. 01 32 16.33 Schedule Float states float ownership. 01 32 16.36 Schedule Acceleration covers acceleration and mitigation. 01 32 19 Schedule of Values ties payment to schedule activities. Each section changes the analysis scope, notice periods, and submission requirements.

Local amendments

Adopted code editions vary by state and municipality. Some jurisdictions adopt the IBC with local amendments that change inspection sequencing or add requirements for fire-rated assemblies. Others adopt the IRC for residential work with different inspection hold points. Local amendments can also affect permit issuance timelines, which are common owner-caused delay events. Always confirm the adopted code edition and any local amendments with the local building department before finalizing the schedule activities and delay analysis.

Who we provide estimates for

Who Uses This Analysis

General contractors

To support time extension requests and defend against liquidated damages. The analysis ties each delay event to the critical path and quantifies float consumption, giving you a defensible position in negotiations or claims.

Subcontractors

To show that your work was delayed by others and to support pass-through claims. The analysis isolates delays caused by the prime or owner that affected your scope and quantifies the time impact on your activities.

Owners and developers

To evaluate contractor time extension requests and determine whether delays are compensable. The analysis separates owner-caused, contractor-caused, and concurrent delay so you know what you are paying for.

Attorneys and claims consultants

To build or rebut a delay claim with a schedule-based analysis that follows AACE 29R-03. The workbook and narrative provide the technical foundation for expert reports and depositions.

Architects and construction managers

To review schedule updates and assess whether the critical path is accurately represented. The analysis highlights logic gaps, out-of-sequence progress, and float consumption that affect project completion.

Where we provide estimates

Schedule Delay & Time Impact Analysis in 20 states

Pricing is adjusted to the project ZIP code. Select a highlighted state to see the cities we cover there.

States we coverSelected
TX

Schedule Delay & Time Impact Analysis in Texas

Nation's largest construction market; Sun Belt population growth, data centers, semiconductor plants, and single-family home building.

Texas estimating services
Property types

Project Types and What Changes in the Delay Analysis

The delay analysis method is consistent, but the records, critical path, and float behavior change by project type. The table below shows what to watch for.

Commercial office building

Core and shell critical path often runs through structural steel, curtain wall, and MEP rough-in; tenant fit-out adds parallel paths.

Watch for: Watch for owner-caused submittal delays on long-lead items and concurrent contractor delays in MEP coordination.

Healthcare facility

Infection control, medical gas certification, and equipment commissioning drive the critical path more than structural work.

Watch for: Watch for owner-furnished medical equipment delays and inspection hold points that are not in the baseline schedule.

Data center

Electrical gear, UPS, and cooling systems are long-lead and often owner-furnished; commissioning is a major critical path segment.

Watch for: Watch for vendor delay documentation and whether the schedule includes commissioning activities with proper logic ties.

K-12 school

Summer break and school opening dates create hard milestones; weather and permit delays compress the schedule.

Watch for: Watch for liquidated damages tied to school opening and concurrent delays from owner-directed changes during the school year.

Multifamily residential

Vertical construction repeats floor-by-floor; the critical path may shift between trades as floors stack.

Watch for: Watch for out-of-sequence progress between floors and float consumption on near-critical paths like drywall and cabinets.

Industrial warehouse

Site work, foundations, and tilt-up or steel erection dominate; MEP is often less complex than commercial.

Watch for: Watch for weather delays on earthwork and owner-caused delays in utility coordination or permit issuance.

Road and bridge

Linear scheduling and work zone restrictions drive the critical path; weather and utility relocations are common delay events.

Watch for: Watch for seasonal restrictions, utility owner delays, and concurrent delays from traffic control changes.

Deliverables

What you receive

  • A written narrative report explaining the delay events, critical path impacts, and float consumption by period.
  • An Excel workbook with activity-level detail showing start, finish, duration, total float, free float, and delay attribution for each update window.
  • A marked-up plan set highlighting the areas of work affected by each delay event.
  • A time impact analysis for each compensable and excusable delay event, inserted at the time of the event.
  • A concurrent delay evaluation with apportionment between owner-caused and contractor-caused delays.
  • A time-related general conditions cost buildup by period, with ZIP-code-adjusted labor and equipment rates.
  • A source document index linking each delay event to RFIs, change orders, daily reports, and meeting minutes.
Checklist

Pre-Analysis Checklist

  • Confirm the approved baseline schedule exists in native format.
  • Collect every monthly update from notice to proceed through the last data date.
  • Verify each update has a data date, actual dates, and remaining durations.
  • Gather daily reports with manpower, equipment, and weather by location.
  • Compile RFI and submittal logs with issuance and response dates.
  • Assemble the change order register with notice, pricing, and time extension dates.
  • Obtain daily weather records from an on-site station or nearest NOAA location.
  • Read the contract's scheduling specifications for notice and float ownership.
  • Collect meeting minutes that document delay discussions and directives.
  • Check for out-of-sequence progress in updates against field records.
  • Identify all owner-furnished equipment and long-lead items with delivery dates.
  • Confirm the contract calendar and work-day definitions for time conversions.
Client reviews

What clients say about Scope Precision Estimate

10 client reviews
MA
Michael AndersonGeneral Contractor

The cost estimate was detailed, accurate, and easy to understand. It helped us prepare our bid confidently and stay competitive without overlooking important costs.

AW
Andrew WilsonGeneral Contractor

Highly recommended for construction cost estimating. The quantities were accurate, the pricing was well organized, and the final report was easy to review.

MD
Matthew DavisConstruction Manager

Their construction estimate was thorough and professionally prepared. It made our budgeting process much easier and helped us identify potential cost issues early.

CM
Christopher MillerResidential Builder

We needed a quick and accurate construction cost estimate, and they delivered exactly what we needed. Great attention to detail and a very responsive team.

BT
Brian TaylorProject Estimator

Fast, accurate, and dependable estimating service. They understood the project requirements quickly and provided a detailed estimate without unnecessary delays.

RW
Robert WilliamsEstimating Manager

Professional and reliable estimating service. The detailed quantity takeoff helped us reduce pricing errors and submit our proposal on time.

FAQ

Schedule Delay & Time Impact Analysis questions

What is the difference between a time impact analysis and a delay analysis?

A time impact analysis inserts a single delay event into the schedule as it existed at the time of the event to measure that event's impact. A delay analysis is broader: it reconstructs the as-built critical path, performs window analysis across the project, evaluates concurrent delay, and apportions responsibility. We typically perform both — a TIA for each event and a delay analysis for the overall claim.

Do you need the native P6 or MS Project files, or are PDFs enough?

Native files are required for a full analysis. P6 XER and MS Project MPP files allow us to trace logic ties, calculate total and free float, and insert delay events at the correct point in the schedule. PDF bar charts show the visual critical path but not the logic, so we cannot calculate float consumption or verify predecessor-successor relationships. If native files are missing, we reconstruct what we can from daily reports and updates.

How do you handle concurrent delay?

We identify owner-caused and contractor-caused delays that occurred in the same window and affected the critical path simultaneously. We document the specific activities, dates, and float consumption for each concurrent event. Apportionment follows the contract language or the method most defensible for your jurisdiction — day-by-day, window, or gross. Concurrent delay can reduce or defeat recovery, so we quantify it explicitly rather than ignore it.

What does float ownership mean for my claim?

Float ownership determines whether a delay that consumes total float but does not push completion is compensable. If the contract says float is project-owned, a delay that consumes float without extending completion may not be compensable. If float is owned by the owner, the contractor may have less protection. We apply the contract language and note where it is ambiguous, then show the impact on recoverable days.

Can you analyze a project that has no baseline schedule?

Yes, but the analysis is limited. Without a baseline, we reconstruct an as-built schedule from daily reports, inspection records, and meeting minutes. We can identify actual start and finish dates and sequence, but we cannot calculate float or establish the original critical path with certainty. The result is a factual as-built sequence that supports delay arguments but may not meet the contract's technical requirements for a time impact analysis.

How do you convert work days to calendar days for a time extension?

We use the contract calendar. If the contract defines a 5-day work week, we divide work days by 5 and multiply by 7 to get calendar days, then adjust for holidays and weather days. If the contract uses a 6-day work week, the conversion changes. We document the calendar used in the baseline schedule and apply it consistently across the analysis so the time extension matches the contract's measurement basis.

What records do you need to prove owner-caused delay?

You need the RFI or change directive with its issuance date, the contract notice period, the affected schedule activities with predecessor-successor logic, and the schedule update showing the critical path at the time of the event. Daily reports and meeting minutes that document the delay discussion strengthen the record. We also cross-reference the event to specific drawing sheets or specification sections to tie it to a definable scope item.

How do you handle weather delays?

We compare daily weather observations from an on-site station or the nearest NOAA reporting location against the contract's weather allowance. Days that exceed the allowance and affect critical path activities are quantified as excusable delay. General statements about bad weather are not enough. We require daily records with temperature, precipitation, and wind, and we tie each weather day to the specific activities that were delayed.

Can you separate acceleration costs from the original contract work?

Yes. We identify acceleration measures from change orders, meeting minutes, and daily reports — added crews, overtime, second shifts, and additional equipment. We tie each measure to the affected schedule activities and the delay period it was intended to mitigate. Acceleration costs are presented separately from original contract work so they can be evaluated as a distinct claim element.

What is the turnaround time for a delay analysis?

Turnaround is 24–48 hours for most projects. The actual time depends on the number of schedule updates, the volume of daily reports, and the number of delay events. Projects with 18 monthly updates and 9 delay events typically require more time than a project with 6 updates and 2 events. Rush service is available. We confirm the schedule and deliverables before starting.

Do you provide expert witness testimony?

Expert witness testimony is provided separately under a professional services agreement. Our standard delay analysis deliverable includes a written narrative, an Excel workbook with activity-level detail, a marked-up plan set, and a source document index. These documents provide the technical foundation for an expert report or deposition, but the analysis itself is not legal advice or a legal opinion on entitlement.

How do you present the analysis to the other party or a claims reviewer?

We organize the deliverable by CSI MasterFormat Division 01 sections — 01 32 16.23 Time Impact Analysis and 01 32 16.29 Schedule Delay Analysis — with a written narrative, an Excel workbook showing start, finish, duration, total float, free float, and delay attribution for each update window, and a marked-up plan set highlighting affected work areas. A source document index links each delay event to RFIs, change orders, daily reports, and meeting minutes.

What is construction claims consulting and how does it differ from a delay claim analysis?

Construction claims consulting covers the full dispute: entitlement, causation, quantum, and presentation. A delay claim analysis is one part of that work. We build the critical path method comparison, tag compensable delay and inexcusable delay, and produce the workbook and narrative a claims reviewer will test. If you also need cost loading, productivity rate adjustments, or a recovery schedule, we can extend the same model. The output is organized by CSI MasterFormat Division 01 so it drops into your claim file without reformatting.

Can you provide outsourced delay analysis for a claim I am already defending?

Yes. We start from the as-planned schedule, the monthly updates, and the record set you already have. We rebuild the critical path at each data date, run impacted as-planned and collapsed as-built scenarios, and test each event with a fragnet. Force majeure, differing site conditions, and owner-directed changes are separated so concurrent delay is not overstated. The deliverable is an Excel workbook and a written narrative, not a legal opinion. We can also review the other side's time impact analysis services and point out where the method departs from AACE 29R-03.

What does a delay analysis company need to run a construction schedule analysis on my project?

Send the native Microsoft Project or P6 file, not a PDF, plus every update with its data date. We also need the contract and AIA A201 or ConsensusDocs 200 general conditions, the RFI and submittal logs, daily reports, change order register, weather records, and any look-ahead schedule or procurement schedule that shows long lead item dates. If the project is in Texas, California, Florida, New York, or North Carolina, ZIP-code-adjusted rates apply to time-related cost roll-ups. Turnaround is 24–48 hours for most projects.

RH

Reviewed by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning. is a Senior Estimator with more than 15 years of professional experience in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review
  • Project budgeting

Send Your Schedule Records

Send your baseline schedule, monthly updates, daily reports, and RFI log for a forensic time impact analysis with delay days, float consumption, and time-related cost buildup.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.
Upload plans for a quote
Call Us