Scope Precision EstimateContact Us
Cost Types, Labor & Budget Control

Feasibility Study in Construction: Steps and Template

A step-by-step guide to the construction feasibility study: site, technical, regulatory and financial analysis, estimate accuracy at concept stage, and a template you can reuse.

Quick answer

A feasibility study in construction tests whether a project can be built, permitted and paid for before you spend design money. It covers site constraints, zoning and code, utility capacity, a conceptual estimate, and a pro forma showing cost, schedule and return. The output is a go, no-go or revise decision.

  • Feasibility ends in a decision, not a design: go, no-go, or go with conditions.
  • Use AACE Class 4 or 5 estimates at this stage, typically -15% to -30% low and +20% to +50% high.
  • Site and entitlement risk kills more deals than construction cost does.
  • A written template keeps site, technical, regulatory and financial findings comparable across sites.

What Is a Feasibility Study in Construction?

A feasibility study in construction is a structured pre-construction investigation that tests whether a project is technically buildable, legally permissible, financially viable, and worth pursuing before design money is committed. It is the document that tells an owner, developer, or lender whether to spend the next dollar on architects and engineers or walk away. For a deeper look at how cost planning fits into this phase, see cost planning and feasibility studies.

The study runs four core tests. Site and technical feasibility asks whether the ground, utilities, access, and structure can support the program. Regulatory and zoning feasibility asks whether the local jurisdiction will permit the use, height, density, and parking. Financial feasibility asks whether the pro forma produces a return that justifies the risk. Schedule and market feasibility asks whether the project can be delivered in time to meet demand and lease-up assumptions.

A feasibility study is not a business case. The business case justifies the investment to decision-makers against other uses of capital. The feasibility study produces the technical and cost evidence the business case relies on. Confusing the two leads to optimistic pro formas built on assumptions nobody tested.

The output is a feasibility study report, not construction documents. Its accuracy depends on the level of design information available at the time. A study run from a site survey and a program statement carries wider cost ranges than one run from a concept set. Owners, developers, general contractors chasing a CM-at-risk role, and institutional clients with funding gates all commission these studies. Developers in particular use them to decide whether to option land, and developer and owner estimating is often the first cost input into that decision.

If your feasibility report does not state its estimate class and range, decision-makers will treat a Class 5 number as if it were a bid. Label the accuracy.

Feasibility Study vs Business Case: Where Each Fits

The two documents answer different questions and go to different audiences. A feasibility study answers whether the project can be built, permitted, and paid for. A business case answers whether the organization should fund it against its other options. Mixing them produces a report that satisfies neither the design team nor the investment committee.

ElementFeasibility StudyBusiness Case
Primary questionCan this be built, permitted, and paid for?Should we fund this over alternatives?
AudienceOwner's project team, design team, lenders' technical advisorsBoard, investment committee, capital partners
Core inputsSite survey, geotechnical report, zoning analysis, concept design, conceptual estimateFeasibility report, financing structure, tax treatment, opportunity cost
Cost outputConceptual estimate by UniFormat or CSI MasterFormatTotal development cost and sources-and-uses
Financial outputPro forma, cash flow, return on investment, NPV, IRR, paybackRisk-adjusted return versus hurdle rate and strategic fit
Decision supportedProceed to design or kill the siteApprove funding or redirect capital

A project feasibility analysis feeds the business case with four hard artifacts: a conceptual estimate, a site plan, a schedule, and a risk register. The business case then layers on financing structure, tax treatment, opportunity cost, and strategic fit. Without the feasibility inputs, the business case is opinion.

The common failure is skipping feasibility and writing a business case on a pro forma built from a broker's back-of-napkin numbers. That pro forma usually omits soft costs, escalation, contingency, and infrastructure. When the real estimate arrives, the return on investment collapses and the deal dies late, after money has been spent. Investors who want defensible underwriting often start with real estate investor estimating to pressure-test the cost side before the business case is written. A construction feasibility study example makes the split clear: the study prices the site analysis and the build, while the business case prices the money. If you are learning how to conduct a feasibility study, keep the two documents separate from the first draft. A pre construction feasibility study is the cost-and-buildability half; the business case is the capital-allocation half. Contractors who understand this distinction can advise owners earlier, and that is where a feasibility study for contractors earns its place on the team. Every construction project benefits when the cost basis is settled before the funding decision.

If a broker or land seller hands you a pro forma, treat it as a hypothesis, not an input. Rebuild the cost side from a program and a site plan before you rely on it.

Construction Feasibility Study Steps, Start to Finish

The sequence below is the order that keeps a study honest. Each step produces an artifact the next step depends on, so skipping ahead weakens everything downstream. If you want to know how to conduct a feasibility study, follow the steps in order and resist the urge to price anything before the program is fixed.

  1. Define the program. Fix gross square footage, unit count, use type, phasing, and target completion date. A program that shifts mid-study invalidates the estimate, so get the owner to sign off on the program statement before anyone prices it. Parking count, amenity square footage, and structured versus surface parking belong in this step.

  2. Run the site feasibility study. Pull title, ALTA survey, geotechnical report, utility availability, access and curb cut options, floodplain maps, wetlands delineation, and environmental impact screening. This step kills bad deals early. A site that needs deep foundations, a retaining wall, or a utility extension changes the cost basis before design starts. Civil scope here often needs its own pricing pass through civil estimating services.

  3. Complete the regulatory review. Confirm zoning, setbacks, height limits, floor area ratio, parking ratios, and the building code family that applies. Most commercial and multi-family work falls under the IBC; detached one- and two-family dwellings fall under the IRC. Check fire apparatus access, sprinkler thresholds, and the entitlement timeline. Entitlement duration is a cost, not just a schedule item.

  4. Produce concept design and a conceptual estimate. Price at AACE Class 4 or 5, which correspond to roughly 1% to 15% and 0% to 2% of project definition respectively. Use UniFormat to organize systems (A through G) and CSI MasterFormat divisions for trade-level backup. State the range and the basis of the estimate. This is the step where preliminary and conceptual estimating does the heavy lifting.

  5. Build the financial feasibility study. Convert the estimate into a pro forma, a cash flow, and the return metrics: return on investment, net present value, internal rate of return, and payback period. Test the pro forma against realistic lease-up and absorption assumptions, not best-case ones.

  6. Close with risk review and a go/no-go recommendation. Compile a risk register with cost, schedule, entitlement, and market risks, each with a mitigation and an owner. Package the findings in a feasibility study report format the client can circulate to lenders and investors without editing.

Steps 1 through 3 can run in parallel if you have the survey and geotechnical report in hand. Steps 4 and 5 are sequential because the pro forma consumes the estimate. Step 6 is where you either recommend proceeding to design or recommend walking, and both are valid outcomes of a well-run study. For a construction feasibility study example, walk a 40,000-square-foot self-storage site through these six steps and you will see where the cost drivers sit: site analysis, entitlement, and the conceptual estimate. A pre construction feasibility study follows the same path but stops before the pro forma, giving the design team a cost basis to design against. Contractors who run this sequence before bidding protect their margin; that is the core of a feasibility study for contractors. Every construction project that skips these steps pays for it later in change orders and redesign.

AACE Class 5 estimates carry a range of roughly -20% to -50% on the low side and +30% to +50% on the high side. Never present a Class 5 number as a single figure.

Site Feasibility Study: The Checklist That Kills Bad Deals Early

A site feasibility study is where most projects are won or lost before a single line of the conceptual estimate is priced. Work through the items below in order, because each one can invalidate the others.

  • Survey and title. Confirm boundary lines, easements, rights-of-way, and any encroachments. Pull mineral and air rights if the jurisdiction separates them from the surface estate.
  • Geotechnical report. Review boring logs, groundwater elevation, rock depth, expansive soils, and allowable bearing capacity. Each one drives foundation type and cost, from spread footings to drilled piers or a mat. Foundation scope feeds directly into our foundation estimating services.
  • Utilities. Check the capacity of water, sanitary sewer, storm, gas, and electrical service at the nearest main. Note any offsite extension, and price it in site utilities estimating services terms.
  • Environmental. Order a Phase I ESA, delineate wetlands, and pull the floodplain elevation. Stormwater management requirements often set the site plan footprint more than zoning does.
  • Access and traffic. Verify curb cuts, sight distance, DOT permits, and any required turn-lane improvements. These are frequently the largest unbudgeted offsite cost.
  • Earthwork balance. Compare cut and fill volumes in cubic yards, import or export haul distance, and shoring needs. A balanced site saves money; an unbalanced one adds hauling and disposal. Our excavation estimating services and sitework estimating services teams quantify this early.

Treat this list as a gate. If any item is unresolved, the financial feasibility study that follows is built on sand.

A geotechnical report and a Phase I ESA are cheap relative to the cost of discovering rock, groundwater, or a wetland after you close on the land.

Technical and Regulatory Feasibility: Zoning, Code, and Entitlements

Technical feasibility answers one question: can this program legally and physically be built on this site? Start with zoning. Use classification, density, floor area ratio, height, setbacks, parking minimums, and any overlay districts set the envelope. Your architect and engineer translate that envelope into a test-fit, and the test-fit tells you whether the program fits before you spend on design.

Building code review comes next. The IBC occupancy group and construction type drive egress, sprinkler, and fire-resistance requirements; the IRC applies to one- and two-family dwellings instead. Confirm MEP capacity, transformer size, and whether the local AHJ requires a fire pump or dedicated water supply. These are not details to defer, because they change the mechanical room, the service entrance, and the cost per square foot.

Entitlement has its own clock: sketch plan, public hearing, site plan approval, building permit. Each step has a review period you cannot compress. Flag code-driven cost swings early. A change from Type V-B to Type II-A construction can add significant cost per square foot, and that swing belongs in the feasibility model, not in a change order. Public projects add a layer of review, which our public works estimating services team tracks closely. For private work, commercial estimating services translate the code-driven scope into a defensible number.

A one-line zoning change can move the pro forma more than a 10% swing in construction cost. Verify the code path before you sharpen the estimate.

Send Plans for a Feasibility-Stage Estimate

Send your site information, program and any sketches, and we will return a bid-ready conceptual estimate in 48 hours.

Same-Day QuotesBid-Ready in 48 Hrs20% Off
Upload plans

Financial Feasibility Study: Pro Forma, Cash Flow, and Returns

NPV = Σ (Cash flow_t ÷ (1 + r)^t) − Initial investmentDiscount each period's net cash flow at the developer's rate r; a positive NPV means the deal clears the return threshold.

A financial feasibility study takes the conceptual estimate as its input, not a target rent roll. Build the pro forma from hard costs, soft costs, contingency, and financing carry. If you start from the rent you want and back into cost, you are writing a wish, not a feasibility study.

Lay out cash flow by month: land close, design, permits, construction draws, lease-up or sellout, and debt service. Timing matters as much as totals, because carry cost accrues while nothing is earning. Then compute the return metrics: net present value at the developer's discount rate, internal rate of return, and payback period. If the IRR only clears the hurdle at the optimistic rent, the deal is not feasible yet.

Run sensitivity at ±10% construction cost, ±10% rent, and a 6-month schedule slip. The schedule slip alone often breaks a marginal deal through added carry. For contingency, owners typically carry 5–10% on feasibility-stage hard costs, and higher for renovation or unknown site conditions. Our estimating for developers group builds these models, and construction cost control keeps them honest through construction.

Sensitivity is not optional. A deal that only works at the midpoint of every assumption is a deal that will not survive the first schedule slip.

Feasibility Study Cost and the Conceptual Estimate

Conceptual estimate range = Point estimate × (1 + accuracy factor)Apply the AACE class range to your point estimate to show the owner the low and high bound.

The feasibility study itself is a soft cost, and its fee is driven by scope, not by project size. A single-site, single-use study with a clear program costs far less than a multi-site study with entitlement risk, environmental review, and three massing options. When you budget the study, separate the consultant fees from the construction cost you are trying to predict. The accuracy of the conceptual estimate you produce inside the study matters more than the study fee, because it sets the loan amount, the equity ask, and the go/no-go decision.

Estimate accuracy is classified by AACE International. A Class 5 estimate, typical at the feasibility stage, carries an accuracy range of -50% to +100%. A Class 4 estimate, prepared once the program and site are defined, carries -30% to +50%. A Class 3 estimate, based on more advanced design, carries -20% to +30%. State the class on the cover of your estimate. Owners who treat a Class 5 number as a fixed budget create the disputes that show up later as change orders.

Build the conceptual estimate in UniFormat first, from A substructure through G building sitework. UniFormat is element-based, so it survives design changes and lets you compare options without redoing the whole estimate. Then back the same scope into CSI MasterFormat divisions for trade pricing and bid packages. A work breakdown structure keeps every line mapped to a quantity takeoff unit: square foot, cubic yard, linear foot, each, ton, or lump sum. If a line has no unit, you cannot verify it.

Benchmark the result against construction cost per square foot ranges from published cost data, then adjust for region, date, and scope. A budget estimating service can build the UniFormat model and the MasterFormat backup in parallel, and RSMeans-based estimating gives you a defensible starting point for the benchmark. Never carry a benchmark number into the pro forma without adjusting for local labor, code, and site conditions.

Label every feasibility-stage estimate with its AACE class. An unlabeled number will be treated as a bid, and the gap between a Class 5 and a Class 3 estimate can exceed 30% of hard cost.

Worked Example: A 40,000 SF Mixed-Use Feasibility Estimate

Total feasibility budget = Hard cost + Sitework + Soft costs + ContingencyShow each line separately so the owner can see which assumptions drive the total.

Example only. Program: 40,000 SF mixed-use building, 30,000 SF residential over 10,000 SF ground-floor retail, Type III-A construction, surface parking. The numbers below are illustrative and must be replaced with current local data before you rely on them.

Step 1 — Hard cost benchmark. A blended hard cost of $225/SF is applied to the gross floor area.

40,000 SF × $225/SF = $9,000,000

Step 2 — Sitework. Clearing 1.5 acres, a 4,000 CY cut/fill balance, and 12,000 SF of asphalt paving at $6/SF, plus utilities and landscaping.

Asphalt paving: 12,000 SF × $6/SF = $72,000 Utilities: $180,000 Landscaping: $95,000 Sitework subtotal: $72,000 + $180,000 + $95,000 = $347,000

Step 3 — Soft costs. Architecture, engineering, permits, legal, insurance, and fees at 18% of hard cost.

0.18 × $9,000,000 = $1,620,000

Step 4 — Contingency. 8% applied to hard plus soft cost.

0.08 × ($9,000,000 + $1,620,000) = 0.08 × $10,620,000 = $849,600

Step 5 — Total feasibility-stage budget.

$9,000,000 + $347,000 + $1,620,000 + $849,600 = $11,816,600

Per square foot: $11,816,600 ÷ 40,000 SF = $295.42/SF

Use a mixed-use estimating service to build the residential and retail scopes separately, because their unit costs diverge. A preliminary estimating service can produce this level of conceptual estimate in 24–48 hours so your feasibility study is not waiting on the number.

The 4,000 CY cut/fill balance assumes the site balances. If you have to export or import soil, add haul-off or borrow cost per cubic yard before you call the sitework number final.

Feasibility Study Template: Sections and What Goes in Each

  • Executive summary. State the program, site, total budget, return metrics, and a clear recommendation. One page. If the reader only reads this page, they should know whether to proceed.

  • Site and regulatory. Include the survey, geotechnical report, zoning analysis, applicable code, environmental findings, and the entitlement path with expected durations. This section is where most feasibility studies fail, so do not summarize it away.

  • Design concept. Show massing, unit mix, gross and net square footage, and parking count. Net-to-gross efficiency belongs here because it drives the revenue side of the pro forma.

  • Cost estimate. Start with a UniFormat summary, attach the CSI MasterFormat backup, state the AACE estimate class, and show contingency and escalation as separate lines. A cost planning and feasibility study should produce this section with a quantity takeoff behind every major line.

  • Financial. Include the pro forma, cash flow, NPV, IRR, payback, and a sensitivity table. Run at least three cases: base, downside, and upside.

  • Schedule and risk. Provide a milestone schedule with permit durations, and list the top 10 risks with a mitigation for each. Rank them by cost and schedule impact.

  • Appendix. Attach the quantity takeoff backup, vendor quotes, correspondence, and an assumptions log. The assumptions log is what lets a reviewer test your numbers later. A construction estimating service can prepare the cost and takeoff sections in the template format your lender or investment committee expects.

Keep the assumptions log in the appendix, not buried in the body. When a reviewer challenges a number, the log is the fastest way to show where it came from.

How Feasibility Work Differs by Project Type

The math behind a feasibility study in construction does not change, but the risk that can kill the deal does. For ground-up commercial work, entitlement risk and parking ratios dominate the model. A site that cannot hit the local parking minimum, or that needs a variance the planning commission may refuse, is a dead deal before cost per square foot even matters. Cost per square foot is relatively stable across office and retail, so the estimating by project type comparison mostly confirms the program fits the site.

Residential and multifamily feasibility turns on unit mix, absorption, and per-unit hard cost. You model rent or sale price by unit type, subtract hard and soft cost per unit, and test how many months of absorption the developer can carry. A developer or general contractor running this model needs the same discipline a subcontractor applies to a bid: quantify first, price second.

Industrial and warehouse projects hinge on clear height, column spacing, truck court depth, and power capacity. A building with 32-foot clear height and 50-foot by 50-foot bays prices differently from one with 36-foot clear and 60-foot bays, and the warehouse construction estimating breakdown shows why those dimensions drive both steel and slab cost. Renovation and adaptive reuse add existing conditions, hazardous materials, and structural capacity as the largest unknowns. Healthcare, data center, and cold storage push cost per square foot well above typical commercial because MEP and redundancy requirements set the budget, not the shell.

Matching the model to the risk

Ask which single variable, if wrong by 20 percent, breaks the return. For a warehouse it is often power capacity or truck court depth. For a multifamily project it is absorption. For an adaptive reuse it is the structural and hazmat survey. Spend the feasibility budget on that variable first.

If you can name the one assumption that would kill the deal, you know where to spend your feasibility dollars. Everything else can stay at a lower level of detail.

Common Feasibility Study Mistakes to Avoid

  • Using a broker's pro forma as the cost basis. A pro forma built for marketing uses round numbers and often omits scope. A quantity-based conceptual estimate built by an estimator gives you a defensible number you can carry into the next phase.
  • Ignoring offsite work. Utility extensions, road improvements, and stormwater detention can add six or seven figures that never appear in a building-only budget. Walk the site and check the utility map before you finalize the number.
  • Assuming a permit timeline without checking the AHJ's review queue. Call the authority having jurisdiction and ask for current review times for your project type. A three-month assumption against an eight-month reality changes the carrying cost and the pro forma.
  • Omitting escalation between feasibility date and construction midpoint. If you price today and build in 18 months, you need an escalation allowance on the trades most exposed to material and labor movement. State the midpoint date the estimate is priced to.
  • Treating contingency as padding instead of a defined allowance tied to AACE class. A Class 5 estimate needs a much larger contingency than a Class 2 estimate. Label the class and the contingency so the reader knows what is covered.
  • Skipping the geotechnical report and assuming standard spread footings. Soil conditions can force deep foundations, dewatering, or ground improvement. A second-opinion estimate review will flag a foundation assumption that has no geotech behind it.

Most of these mistakes share one root cause: the project feasibility analysis was built by someone selling the deal rather than someone pricing it. An independent construction estimating consultant can pressure-test the number before you commit capital.

Write down the source of every major assumption in your feasibility model. If you cannot name the source, treat that line as a risk item, not a fact.

Who Does What on a Feasibility Team

The owner or developer sets the program, the budget target, and the return hurdle. Everything downstream is measured against those three things, so they need to be written down before anyone prices a square foot. If the program changes mid-study, the estimate changes with it.

The architect tests massing and code compliance, and the engineer sizes structure and MEP. Their work turns a program into a building that can actually be permitted and built. An architect and designer cost support workflow keeps the design and the cost model moving together instead of in sequence.

The estimator builds the conceptual estimate and quantity takeoff from the drawings and site data available at that stage. The general contractor may provide constructability input, means-and-methods review, and local market pricing. On larger projects, subcontractors can supply budget pricing on major packages at feasibility stage, which anchors the MEP and structural numbers to real trade input rather than published averages.

A third-party estimator or consultant gives an independent check on the GC's number. That independent view matters most when the GC is also a development partner, because the incentive to keep the number low is real. A dedicated construction estimator working only on your project avoids the split-attention problem that comes with sharing staff across active bids.

Keeping roles clean

Define who owns each assumption. If the architect owns the gross floor area and the estimator owns the unit costs, someone must own the reconciliation when the two do not agree. Put that person's name on the model.

The fastest way to lose a feasibility argument is to have two people own the same assumption. Assign one owner per line and reconcile differences in writing.

When to Bring In a Professional Estimate or Takeoff

You should bring in a professional estimator when the go/no-go decision hinges on a number you cannot defend line by line. A feasibility study in construction often starts with a rough order of magnitude, but as the project moves toward a capital commitment, the estimate must be backed by a quantity takeoff, not a lump sum from memory. If you cannot show the excavation cubic yards, the concrete formwork square feet, or the rebar tonnage behind your cost per square foot, you are guessing.

For contractors chasing a CM-at-risk or design-build role, a bid-ready conceptual estimate supports the interview and the guaranteed maximum price. Owners and developers benefit from an independent estimate review to catch optimism bias before the loan closes. A professional estimator can also help you stress-test the pro forma by adjusting quantities for site conditions, code triggers, and market escalation. The goal is not precision at the feasibility stage, but traceability.

Scope Precision Estimate offers same-day quotes, bid-ready in 48 hours, 20% off, with 24–48 hour turnaround on most projects and rush available. Whether you need a full cost planning and feasibility study or a quantity takeoff to back up your numbers, getting a second set of eyes early can save you from a costly misstep. If you are ready to move forward, get an estimate and see how a professional takeoff can strengthen your feasibility study.

If your feasibility estimate lacks a quantity takeoff, treat it as a placeholder, not a budget. Bring in an estimator before you sign a purchase agreement or submit a GMP.

Frequently asked questions

How long does a construction feasibility study take?

For a single site with a clear program, a desktop feasibility study usually takes two to four weeks. Add two to six weeks when you need a boundary or topographic survey, geotechnical borings, utility capacity letters, or a zoning verification from the local jurisdiction. Larger or contested sites, rezoning cases and multi-phase master plans can run two to four months. The financial model is rarely the long pole; site due diligence and agency response times are.

How much does a feasibility study cost?

Typical U.S. ranges: a desktop feasibility study with a conceptual estimate runs about $3,000 to $15,000 for a small commercial or residential project. Add $5,000 to $30,000 or more for survey, geotech, environmental Phase I, traffic or utility studies on a larger site. Entitlement and zoning counsel add legal fees on top. Costs vary by region, site condition, scope and date, so treat these as planning ranges and confirm with local quotes.

What is the difference between a feasibility study and a business case?

A feasibility study answers whether the project is physically, legally and financially possible, and it compares options. A business case answers whether the organization should fund it, covering strategic fit, funding sources, alternatives including doing nothing, and the approval path. Feasibility comes first and feeds the business case. On private developments the two often merge into one document, but the analysis and the decision rights are different.

What level of estimate accuracy should I expect at feasibility stage?

Expect AACE International Class 5 or Class 4 accuracy. Class 5, based on capacity or unit cost per square foot, is typically -20% to -50% low and +30% to +100% high. Class 4, based on a rough takeoff of major elements, is typically -15% to -30% low and +20% to +50% high. Carry a contingency of 15% to 30% and state the basis of estimate so readers know what is and is not included.

Can I do a feasibility study without an architect?

Yes, for the early pass. You can test zoning envelope, floor area ratio, parking ratios, unit count and rough cost per square foot without drawings. What you cannot do reliably without design input is test building code compliance, egress, structural system selection, MEP capacity and constructability. Most teams bring in an architect once the site passes the first screen, then revise the study with a schematic layout.

What is included in a site feasibility study?

A site feasibility study covers title and legal description, boundary and topographic survey, zoning and land use designation, setbacks, height and floor area ratio, parking requirements, geotechnical conditions, floodplain and wetlands, environmental history, utility availability and capacity, access and traffic, easements, and demolition or abatement needs. Each item is scored as a constraint, a cost, or a deal-breaker. See our sitework and civil estimating pages for how those costs get built up.

How do I know if my project is financially feasible?

Build a pro forma with hard costs, soft costs, land, financing, contingency and a construction schedule that drives the interest carry. Then test the return against your hurdle: yield on cost, unlevered IRR, equity multiple, or residual land value. Run sensitivity cases on rent, absorption, construction cost and interest rate. If the project only works at the top of every range, it is not feasible yet. A third-party conceptual estimate tightens the cost side.

Do I need a feasibility study for a renovation or tenant improvement?

Yes, but it is shorter and focused. For a renovation or tenant improvement, the study centers on existing conditions: as-built drawings, structural capacity, ceiling plenum depth, panel and service capacity, ADA and egress compliance, sprinkler and HVAC adequacy, and landlord work letter obligations. The cost side is a conceptual estimate by trade rather than a full site study. Tenant improvement estimating pages cover how those scopes are priced.

RH

Written by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review

Keep reading

Send Plans for a Feasibility-Stage Estimate

Same-day quotes, bid-ready in 48 hours, and 20% off.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.
Upload plans for a quote
Call Us