Office & Tenant Improvement Estimating

Send your architectural, MEP and finish plans or landlord work letter. We return a CSI-organized takeoff with quantities, units and ZIP-adjusted pricing in 24–48 hours.

24–48 hours for most projectsTypical turnaround
Excel + marked-up PDFsOrganized by CSI section
ZIP-code pricingLocal material and labor
Price confirmed firstBefore any work starts
Sample estimate sheet
Division 09 — FinishesSample format
Line itemQtyUnitArea
ACT ceiling 2x2 lay-in18,400SF18,400 SF
Carpet tile glue-down9,800SF9,800 SF
LVT 3mm glue-down4,200SF4,200 SF
Rubber base 4 in.3,100LF—
Paint walls primer + 2 coats22,600SF22,600 SF
Total finished area55,000 SF
Illustrative quantities. Waste factor applied as a separate line.
Ceiling height bands noted

What is office and tenant improvement estimating?

Office and tenant improvement estimating measures interior build-out scope from a plan set and prices it by CSI MasterFormat division. Takeoffs use units such as SF of ACT ceiling, LF of partition, EA of door and hardware set, and LF of sprinkler branch line. Deliverables are Excel and PDF takeoffs with marked-up plans, typically within 24–48 hours.

  • Units include SF, LF, EA, and CY for concrete, partitions, ceilings, doors, and MEP.
  • Typical waste factors range from 5% for carpet tile to 10% for drywall.
  • The most common costly miss is fire-rated partition and sprinkler head relocation scope.

You have a tenant improvement plan set — demising partitions, ceiling grid, MEP above ceiling, storefront and finish schedules — and need a number you can defend before a hard bid or GMP. We take off the interior build-out of an occupied or shell building, not ground-up shell construction. If your project also includes retail, restaurant or healthcare spaces, we can price those under Retail & Shopping Center Estimating, Restaurant Estimating Services or Healthcare & Hospital Estimating.

Deliverable
Excel estimate + marked-up PDF plans
Organized by
CSI MasterFormat section
Turnaround
24–48 hours for most projects
Pricing
ZIP-code-adjusted material and labor pricing
Software
Bluebeam Revu, PlanSwift, RSMeans data

We organize the takeoff by CSI MasterFormat division so your buyout packages line up with your subcontractor bids. Every line carries a unit you can check against the drawings: SF of acoustic ceiling tile, LF of partition type, EA of doors and hardware sets, LF of sprinkler branch line, EA of lighting fixtures. We mark up the plan set with color-coded highlights so you can see exactly where each quantity came from. Pricing uses ZIP-code-adjusted material and labor rates from RSMeans data, so a partition in a high-cost metro is not priced like the same assembly in a low-cost market. Turnaround is 24–48 hours for most projects, with rush available. If you are pricing a multi-tenant building or a mixed-use development, see Mixed-Use Development Estimating. For state-specific labor and code considerations, we have dedicated pages for Texas, California, Florida, New York and North Carolina.

As a tenant improvement estimating company, we run the quantity takeoff in Bluebeam Revu and PlanSwift, then price each line with unit price and labor productivity assumptions you can audit. Office tenant improvement takeoff is not just Division 09 finishes — it also carries Division 08 doors and frames, Division 10 specialties, Division 12 furnishings, Division 22 plumbing, Division 23 HVAC, Division 26 electrical, Division 27 communications and Division 28 electronic safety. If you need outsourced tenant improvement estimating for a single suite or a full floor, start with Get an estimate.

Services

What this tenant improvement quantity takeoff covers

We price the interior fit-out from the face of the demising partitions to the finished ceiling and floor. The scope follows the tenant's construction documents and the landlord work letter: what the base building provides versus what the TI contract must carry. If the work letter is silent on an item, we flag it as a scope gap rather than assume it into the number.

Selective Demolition

Measure removal of existing partitions, ceilings, flooring, and abandoned MEP. Price haul-off and dumpster counts.

SF · LF · EA

Partitions & Ceilings

Take off demising and corridor partitions by type and height, plus ACT grid, panels, and seismic bracing.

SF · LF

Doors & Hardware

Count interior doors, hollow metal frames, hardware sets, and access-control rough-in. Include storefront entries.

EA · LF

Millwork & Finishes

Measure reception desk, break-room cabinets, countertops, and shelving. Price floor finishes by room and base.

LF · SF · EA

Paint & Wall Covering

Calculate wall and ceiling areas for primer, paint, and accent colors. Include wall covering where specified.

SF

Plumbing & HVAC

Take off fixture rough-in, water coolers, floor drains, diffusers, VAV boxes, and test-and-balance allowance.

EA · LF

Electrical & Lighting

Count panel, branch circuits, devices, lighting fixtures, and controls. Include technology rough-in.

EA · LF

Fire Protection

Measure sprinkler head relocation, branch lines, and fire alarm device additions. Price by device and pipe length.

EA · LF

What every office & tenant improvement estimating takeoff includes

  • Selective demolition of existing partitions, ceilings, flooring and abandoned MEP
  • Demising and corridor partitions by type, including STC-rated and 1-hour assemblies
  • Acoustical ceiling grid, panels, perimeter trim and seismic bracing where required
  • Interior doors, hollow metal frames, hardware sets and access-control rough-in
  • Storefront framing, glazing and suite-entry door operators
  • Millwork: reception desk, break-room cabinets, countertops and shelving
  • Floor finishes by room: carpet tile, LVT, VCT, tile, sealed concrete and base
  • Paint and wall covering systems, including primer and accent colors
  • Plumbing fixture rough-in and trim, water coolers and floor drains
  • HVAC distribution, diffusers, VAV boxes and test-and-balance allowance
  • Electrical panel, branch circuits, devices, lighting and controls
  • Sprinkler head relocation, branch lines, fire alarm device additions
How we work

How we build a tenant improvement estimate

  1. Review work letter and plansWe read the landlord work letter against the architectural and MEP drawings to establish the demising line and what the base building provides. We note the shell condition: slab, structural deck, existing sprinkler main, electrical service and HVAC capacity. Any item not clearly assigned is logged as a scope gap for your review.
  2. Digitize and scale partitionsWe overlay the partition types on the floor plan in Bluebeam Revu and measure LF by type and height band. A 3-5/8 in. stud at 16 in. o.c. with one layer of 5/8 in. Type X each side is a different assembly than a 1-hour corridor wall with two layers and sound attenuation. We separate them so your drywall bid matches the schedule.
  3. Count openings and specialtiesDoor, frame and hardware sets are counted from the door schedule and plan. We verify each hardware set against the function: closers, exit devices, kick and mop plates, card-reader prep. Toilet compartments, accessories and fire extinguisher cabinets are counted from the enlarged plans and specs.
  4. Measure MEP above ceilingWe trace sprinkler branch lines and count heads by type, measure ductwork by size and count diffusers, and count plumbing fixtures and water coolers. Electrical devices, lighting fixtures and fire alarm devices are counted from the power and systems plans. We note where the ceiling height changes and whether the existing systems have capacity.
  5. Price with ZIP-adjusted ratesMaterial and labor rates are adjusted to the project ZIP code using RSMeans data. We apply waste factors as separate lines so you can see the net quantity and the allowance. The final estimate is organized by CSI MasterFormat division with a summary page and marked-up plan set.
  6. Quality check and deliverA second estimator reviews the takeoff against the drawings for missed items, unit errors and scope gaps. We check that every scheduled door, fixture and finish appears in the estimate and that quantities reconcile with the floor plan. We then package the Excel workbook, PDF estimate and marked-up plan set and send them to you within the agreed turnaround.

What we need from you

  • Plan setArchitectural, MEP, fire protection and finish plans, including enlarged restroom and millwork details.
  • Work letterLandlord work letter or lease exhibit defining base-building scope and tenant responsibility.
  • SpecificationsProject manual or spec sections for partition types, finishes, hardware and MEP equipment.
  • SchedulesDoor, hardware, finish, lighting and plumbing fixture schedules with model numbers.
  • Bid date and locationProject ZIP code for pricing adjustment and your bid due date so we can set turnaround.
  • Any addendaIssued addenda, RFI responses or alternates that change the scope from the base bid.
Sample output

Sample takeoff format

Each line shows the CSI section, a plain-language description with the spec detail, the measured quantity, the unit and the drawing reference. This is the format you receive in Excel and PDF.

Sample format — illustrative quantities
SectionLine itemQtyUnitRef.
02 41 19Selective demolition — existing partitions1,250SFA-101
05 40 00Cold-formed metal framing — 3-5/8 in. studs at 16 in. o.c.2,800LFA-201
09 21 16Gypsum board assemblies — 1 layer 5/8 in. Type X each side5,600SFA-201
09 51 13Acoustical panel ceilings — 2x2 lay-in, 15/16 in. grid18,400SFA-103
09 68 00Carpet tile — glue-down, 24x24 in.9,800SFA-104
09 65 16Resilient flooring — LVT 3mm glue-down4,200SFA-104
09 90 00Paints and coatings — primer + 2 coats walls22,600SFA-105
08 11 13Hollow metal frames — 16 ga. knockdown42EAA-601
08 14 16Flush wood doors — 1-3/4 in. solid core42EAA-601
22 40 00Plumbing fixtures — water closets, lavatories, sinks18EAP-101
23 31 13Metal ducts — galvanized, 24x12 in.180LFM-201
26 51 13Interior lighting — 2x4 LED troffers96EAE-201

Units and how we measure square feet and linear feet

Every quantity is measured from the drawings using the same unit your subcontractors will bid. We note the drawing sheet and detail where the quantity was taken.

ItemUnitHow it's measured
Demising partitionsSFArea of partition face by type and height band; studs, track and board layers are separate lines.
Acoustical ceilingSFCeiling area within the room boundary; grid and panel quantities are separated.
Carpet tileSFNet floor area plus a typical 5–10% waste factor shown as a separate line.
Interior doorsEAEach door leaf, frame and hardware set counted individually; hardware sets priced by function.
Plumbing fixturesEAEach water closet, lavatory, sink and water cooler; rough-in and trim priced separately.
Sprinkler headsEAEach head by type (pendent, sidewall, concealed) and branch line LF by pipe size.
DuctworkLFDuct length by size and gauge; diffusers, registers and grilles counted as EA.
Lighting fixturesEAEach fixture type from the lighting schedule; controls and wiring devices separate.
Storefront framingLFLength of aluminum framing at suite entry and corridor; glazing measured as SF.
Fire alarm devicesEAEach smoke detector, horn/strobe and pull station; panel capacity noted.

Worked example — takeoff of one demising partition and its finishes

Dimensions and quantities below are illustrative only. They show the calculation sequence we use, not a real project.

Given: a 60 ft long demising partition, 10 ft floor-to-structural-deck height, 1-hour rated, one layer of 5/8 in. Type X gypsum board each side, 3-5/8 in. studs at 16 in. o.c. A 3 ft x 7 ft door opening sits in the wall. The adjacent floor area is 1,200 SF with 2x2 ACT ceiling and carpet tile.

Step 1 — Gross partition area. 60 ft x 10 ft = 600 SF per face. Two faces = 1,200 SF of board.

Step 2 — Deduct the door opening. 3 ft x 7 ft = 21 SF per face. Net board per face = 600 − 21 = 579 SF. Both faces = 1,158 SF. We carry the door, frame and hardware as separate EA lines.

Step 3 — Studs. Studs at 16 in. o.c. = 0.75 studs per LF. 60 LF x 0.75 = 45 studs. Add one stud each side of the opening = 47 studs. Track: top and bottom = 2 x 60 LF = 120 LF.

Step 4 — Board waste. Typical waste for 5/8 in. Type X on a wall with openings runs 10–15%. At 12%: 1,158 SF x 1.12 = 1,297 SF. We show 1,158 SF net and 139 SF waste as separate lines so you can see the allowance.

Step 5 — Finishes tied to the partition. Paint both faces: 1,158 SF net, primer plus two coats. Rubber base: 60 LF minus the 3 ft opening = 57 LF.

Step 6 — Ceiling and floor in the adjacent area. ACT: 1,200 SF net, 2x2 lay-in in 15/16 in. exposed grid. Carpet tile: 1,200 SF net, glue-down 24x24 in. At a typical 7% waste: 84 SF waste, 1,284 SF purchased.

Step 7 — Head-of-wall firestopping. 60 LF at the deck, 1-hour rated assembly. Mineral wool and sealant priced by LF.

StepItemNet qtyUnitWastePriced qty
1–2Gypsum board, 5/8 in. Type X1,158SF139 SF1,297 SF
3Studs, 3-5/8 in. at 16 in. o.c.47EA2 EA49 EA
3Track, top and bottom120LF6 LF126 LF
5Paint, primer + 2 coats1,158SF—1,158 SF
5Rubber base, 4 in.57LF3 LF60 LF
6ACT, 2x2 lay-in1,200SF60 SF1,260 SF
6Carpet tile, glue-down1,200SF84 SF1,284 SF
7Head-of-wall firestop60LF—60 LF

Sample format — illustrative quantities.

We price each line with ZIP-code-adjusted material and labor rates from RSMeans data and mark the partition, opening and firestop on the plan set so you can trace every number back to the drawing.

Cost drivers

What drives tenant improvement cost estimating

Relative impact on a typical estimate for this trade, based on estimator judgment. Select a bar for details.

Scale: 1 = minor, 5 = major relative impact. Estimator judgment, not measured data.
Relative impact 5 / 5

MEP capacity and relocation

If the existing rooftop unit or VRF system cannot absorb the new occupant load, the HVAC cost changes from diffuser relocation to new equipment. Sprinkler head relocation is minor; adding branch lines because the ceiling layout changed is not.

Partition height and rating

A full-height demising partition from slab to structural deck carries more studs, board layers and firestopping than a partition that stops at the ceiling. The height band and STC or fire rating drive the assembly cost more than the floor area.

Ceiling system type

A 2x2 lay-in panel in a 15/16 in. exposed grid is the baseline. Tegular edges, concealed grid, seismic bracing or a specialty metal ceiling each add material and labor. The ceiling height also affects how much MEP must be rerouted above it.

MEP capacity and relocation

If the existing rooftop unit or VRF system cannot absorb the new occupant load, the HVAC cost changes from diffuser relocation to new equipment. Sprinkler head relocation is minor; adding branch lines because the ceiling layout changed is not.

Finish level

Carpet tile and LVT are commodity finishes. Polished concrete, large-format porcelain tile, architectural woodwork at reception and glass-fronted offices each move the cost per SF. The finish schedule, not the floor area, sets the number.

Occupied building conditions

Work in an occupied building adds temporary partitions, dust control, after-hours work premiums and phased turnover. These are Division 01 general requirements and are easy to leave out of a TI estimate if the plans do not call them out.

Demolition and existing conditions

Removing existing partitions, ceilings, flooring and abandoned MEP adds labor and disposal costs. The extent of demolition depends on the as-built conditions and what the landlord work letter requires the tenant to remove. Hazardous material abatement, if required, is a separate scope.

Code and accessibility upgrades

Adding or reconfiguring restrooms, corridors or exits may trigger upgrades to meet current accessibility standards (ADA) and local building codes. These can include door widths, hardware, clearances, signage and fire-rated assemblies. The adopted code edition varies by jurisdiction and must be confirmed with the local building department.

Storefront and entry systems

Storefront framing, glazing, entry doors and hardware are priced by LF and EA. Custom systems, automatic operators, card readers and security interlocks add cost. The size and number of entries, and whether they are part of the base building or tenant scope, affect the estimate.

Fire protection modifications

Relocating sprinkler heads is common; adding branch lines or a new riser because the ceiling layout or occupancy changed is more costly. Fire alarm device additions and panel upgrades depend on the existing system capacity and the tenant's occupancy classification. We count devices and note the panel model.

Electrical and technology rough-in

New circuits, panel capacity, devices and lighting controls are driven by the power and systems plans. Low-voltage cabling, AV and security rough-in beyond conduit and back-boxes are typically by others. We count breakers, devices and fixtures and note the panel schedule.

Scope gaps

Scope gaps we catch in a bid package

These are the items that most often fall between the landlord work letter and the tenant contract. We flag them on the marked-up plans and list them separately so you can decide who carries them.

  • Landlord work letter versus tenant scope: what the base building provides (shell, HVAC capacity, sprinkler main, electrical service) versus what the TI contract must carry. We compare the two documents line by line.
  • Demising partition from slab to structural deck versus to ceiling only. The height band changes stud, board and firestop quantities. We scale the partition on the section, not just the plan.
  • Head-of-wall firestopping and deflection joints at rated partitions. These are often shown as a detail on the architectural sheets but omitted from the partition schedule.
  • Sprinkler head relocation and adding branch lines when the new ceiling height or layout differs from the shell design. We count heads by type and measure new branch line LF.
  • HVAC capacity balance: whether the existing rooftop unit or VRF system can absorb the new occupant load, economizer and ventilation per ASHRAE 62.1. We note the required CFM and compare to the equipment schedule.
  • Electrical panel spare capacity, new circuits, and whether the tenant panel is fed from the landlord's distribution. We count breakers and note the panel schedule.
  • Restroom build-out or remodel if the shell did not include core toilet rooms, including ADA clearances and fixture counts. We check the plumbing plan against the accessibility details.
  • Fire alarm device additions and panel capacity when a new tenant panel is required. We count devices and note the panel model.
  • Door hardware keying, card-reader and access-control rough-in, and exit device coordination with the door schedule. We verify each hardware set against the function.
  • Temporary partitions, dust control and after-hours work premiums in an occupied building. These are Division 01 items that do not appear on the architectural plans.
  • Permit, plan review, inspection and impact fees, and the jurisdiction's adopted code edition. We list them as a separate allowance and tell you to confirm with the local building department.
  • Millwork and equipment not shown on architectural plans but listed in the tenant's furniture, fixture and equipment package. We cross-check the FF&E list against the millwork elevations.

Materials and assemblies that drive the number

These are the assemblies we compare line by line. Each has a unit cost per SF or LF and a performance or code requirement behind the selection.

Assembly / materialTypical spec referenceUnitCost driver
Demising partition, 3-5/8 in. studs, 1 layer Type X each side09 21 16SFStud gauge and spacing, board layers, STC rating, height band
1-hour corridor partition, 2 layers Type X each side09 21 16SFFire rating, head-of-wall firestop, deflection track
Acoustical ceiling, 2x2 lay-in, 15/16 in. exposed grid09 51 13SFPanel NRC and edge detail, grid type, seismic bracing
Carpet tile, glue-down 24x24 in.09 68 00SFBacking, yarn system, pattern match, waste factor
LVT, 3mm glue-down09 65 16SFWear layer, adhesive, substrate prep, transitions
Polished concrete, 800-grit03 35 00SFExisting slab condition, aggregate exposure, densifier and sealer
Aluminum-framed storefront with tempered glazing08 41 13LF / SFFrame finish, glazing make-up, entry door and operator
Hollow metal frame and flush wood door08 11 13 / 08 14 16EAFrame gauge, door core, hardware function, finish
Paint, primer plus two coats09 90 00SFSubstrate, sheen, accent colors, exposed structure
Sprinkler head, pendent or concealed21 13 13EAHead type, ceiling height, branch line additions, NFPA 13 light hazard spacing
Codes and standards

Codes and standards that change the takeoff

Model codes

Office and tenant improvement work is governed primarily by the International Building Code (IBC) for occupancy classification, construction type, fire-rated assemblies and means of egress. The International Existing Building Code (IEBC) often applies to remodels and can allow alternative compliance paths. The International Energy Code (IECC) and ASHRAE 90.1 drive lighting power density, controls and envelope requirements. The NEC governs electrical circuits and devices, and NFPA 13 governs sprinkler design and head spacing. Which edition is adopted varies by state and city, so confirm the adopted edition with the local building department before you price.

Industry standards

Estimators should reference the Gypsum Association GA-216 for board application and GA-600 for fire-resistance design, ASTM C840 for gypsum board installation, ASTM C636 for ceiling grid installation, and SMACNA duct construction standards for HVAC. NFPA 13 light hazard spacing controls sprinkler head counts, and ASHRAE 62.1 ventilation rates drive outside air and equipment sizing. These standards change quantities, not just methods: a higher STC assembly adds board layers and batt insulation, and a tighter ventilation rate can add equipment capacity.

Specification sections

Read Division 01 for general requirements, submittals and temporary facilities. Division 09 sections 09 21 16, 09 29 00, 09 51 13, 09 65 16, 09 68 00 and 09 90 00 control partition, ceiling, floor and paint quantities. Division 08 sections 08 11 13, 08 14 16, 08 71 00 and 08 41 13 control door, hardware and storefront counts. Division 21, 22, 23 and 26 sections control sprinkler, plumbing, HVAC and electrical counts. The finish and door schedules are often where the actual model numbers and quantities live.

Local amendments

Adopted code editions and local amendments vary widely. Some jurisdictions amend egress width, accessibility clearances, seismic bracing or sprinkler requirements. Others require additional fire alarm notification or energy commissioning. These amendments can add devices, bracing or testing that is not on the base drawings. Always confirm the adopted edition and any local amendments with the local building department, and carry a separate allowance for permit, plan review and inspection fees.

Who we provide estimates for

Who uses this tenant improvement estimate for contractors

General contractors

You need a division-by-division number to compare against subcontractor bids and to decide whether to bid. The takeoff gives you quantities by trade so you can see which package is driving the cost.

Tenant improvement subcontractors

You bid drywall, ceilings, flooring or MEP and need quantities for your scope only. We can extract your division and provide the marked-up plans showing where the quantities came from.

Developers and owners

You are underwriting a lease or a build-to-suit and need a budget before design is complete. The estimate shows the cost drivers and the scope gaps so you can set a realistic allowance.

Architects

You want a cost check on your design before bidding. The takeoff tells you which assemblies and finish choices are moving the number, so you can adjust the specifications early.

Where we provide estimates

Office & Tenant Improvement Estimating in 20 states

Pricing is adjusted to the project ZIP code. Select a highlighted state to see the cities we cover there.

States we coverSelected
TX

Office & Tenant Improvement Estimating in Texas

Nation's largest construction market; Sun Belt population growth, data centers, semiconductor plants, and single-family home building.

Texas estimating services
Property types

Project types we price

The takeoff changes with the building condition and how much of the base building the landlord delivers. These are the common TI scenarios we see.

Shell space first-generation build-out

Full partition, ceiling, MEP distribution, storefront and finish takeoff from bare slab and deck.

Watch for: Confirm what the shell provides: sprinkler main, HVAC capacity, electrical service, restroom core.

Second-generation remodel in occupied building

Selective demolition plus new partitions and finishes; after-hours and dust control allowances.

Watch for: Existing conditions not on the drawings; verify as-built partition locations and abandoned MEP.

Multi-tenant floor with demising walls

Demising partitions by height band and rating, plus separate MEP and finish counts per suite.

Watch for: Landlord work letter limits: who builds the demising wall and who pays for the corridor.

Medical or dental office suite

Adds plumbing fixture counts, medical gas rough-in, casework and specialty HVAC.

Watch for: Medical gas and healthcare systems are outside our standard scope; confirm with the spec.

Build-to-suit office for a single tenant

Full interior takeoff from core to perimeter, including reception millwork and entry storefront.

Watch for: Core restroom build-out and whether the base building includes it.

Speculative office with tenant allowance

Baseline finish package plus alternates for upgraded carpet, ceiling and lighting.

Watch for: Alternates must be priced separately so the owner can choose without re-bidding.

Lab or tech office with benching

Adds fume hood, specialty exhaust, power density and casework; standard office partitions remain.

Watch for: Exhaust duct routing and make-up air can drive the HVAC scope beyond a standard TI.

Retail or restaurant tenant within a mixed-use building

Adds grease duct, hood, walk-in cooler and higher power density to the base TI takeoff.

Watch for: Coordinate with our retail and restaurant estimating pages for the specialty scope.

Deliverables

What you receive

  • Excel workbook organized by CSI MasterFormat division with quantities, units and ZIP-adjusted pricing.
  • PDF estimate with a summary page and division detail you can send to your team or lender.
  • Marked-up plan set in Bluebeam Revu showing color-coded takeoff highlights for each quantity.
  • Scope gap list separating landlord work letter items from tenant contract items.
  • Assumption and exclusion page so you know what is not in the number.
  • Waste factor and allowance lines shown separately from net quantities.
  • Turnaround in 24–48 hours for most projects, with rush available.
Checklist

Pre-bid checklist for a TI estimate

  • Confirm the landlord work letter scope against the tenant contract.
  • Verify the adopted code edition with the local building department.
  • Check that the door and hardware schedules match the plan counts.
  • Confirm partition height bands and ratings on the sections.
  • Verify sprinkler head spacing and whether branch lines are added.
  • Check HVAC capacity against the new occupant load and ventilation.
  • Confirm electrical panel spare capacity and new circuit counts.
  • Review restroom fixture counts and ADA clearances.
  • Confirm fire alarm device additions and panel capacity.
  • Check for after-hours, dust control and temporary partition requirements.
  • Verify millwork and FF&E items not shown on architectural plans.
  • Confirm permit and inspection fee allowances with the jurisdiction.
Client reviews

What clients say about Scope Precision Estimate

10 client reviews
DT
Daniel ThompsonCommercial Contractor

Very impressed with the accuracy and turnaround time. Their estimate gave us a clear picture of material and labor costs before starting the project.

SH
Steven HarrisCommercial Builder

The quality of the estimate exceeded our expectations. Their detailed breakdown of labor, materials, and project costs gave us confidence in our bid.

MA
Michael AndersonGeneral Contractor

The cost estimate was detailed, accurate, and easy to understand. It helped us prepare our bid confidently and stay competitive without overlooking important costs.

AW
Andrew WilsonGeneral Contractor

Highly recommended for construction cost estimating. The quantities were accurate, the pricing was well organized, and the final report was easy to review.

MD
Matthew DavisConstruction Manager

Their construction estimate was thorough and professionally prepared. It made our budgeting process much easier and helped us identify potential cost issues early.

CM
Christopher MillerResidential Builder

We needed a quick and accurate construction cost estimate, and they delivered exactly what we needed. Great attention to detail and a very responsive team.

FAQ

Office & Tenant Improvement Estimating questions

What is the difference between a TI estimate and a ground-up commercial estimate?

A TI estimate prices the interior fit-out of an existing or shell building: demolition, demising partitions, ceiling grid, MEP above ceiling, storefront and finishes. A ground-up estimate includes structure, exterior envelope, site work and shell MEP. If your project includes both, we can price the shell under our commercial estimating services and the interior under this page, or combine them into one division-by-division estimate.

How do you handle the landlord work letter?

We read the work letter line by line and compare it to the tenant's plans and specifications. Items the landlord provides — shell, HVAC capacity, sprinkler main, electrical service — are listed as exclusions or as landlord scope. Items not clearly assigned are flagged as scope gaps. You get a separate list so you can decide who carries each item before you bid.

Do you price demolition and existing conditions?

Yes. We take off selective demolition of existing partitions, ceilings, flooring and abandoned MEP from the demolition plans and notes. If the as-built conditions are not documented, we note the assumption and carry a unit rate per SF or LF that you can adjust. Hazardous material abatement is excluded and should be priced by a specialty contractor.

Can you break the estimate down by subcontractor package?

Yes. The estimate is organized by CSI MasterFormat division, so drywall, ceilings, flooring, doors and hardware, MEP and fire protection each fall into their own section. We can also extract a single division if you only bid one trade. The marked-up plan set shows where each quantity came from, so your subcontractors can verify the counts.

What if the plans are incomplete or only a work letter is available?

We can estimate from a work letter and a preliminary floor plan by using typical assemblies and unit rates. The estimate will carry more assumptions and allowances than a full plan set. We list every assumption so you know what to confirm as design develops. This is common for early budgets and lease underwriting.

How do you handle MEP above ceiling when the ceiling height changes?

We measure the new ceiling height and compare it to the existing MEP routing. If the ceiling drops below the existing duct or sprinkler main, we count the rerouting or relocation as a separate line. Sprinkler head relocation is priced by EA; new branch lines are priced by LF. Duct modifications are priced by LF and EA of diffusers. This is one of the most common scope gaps.

Do you include fire alarm and sprinkler modifications?

Yes. We count sprinkler heads by type and measure new branch lines by pipe size. Fire alarm devices — smoke detectors, horn/strobes, pull stations — are counted from the systems plans, and we note the existing panel model and capacity. If a new panel is required, we flag it as a separate line. Inspection and testing fees are listed as an allowance.

What is your turnaround and what do you need to start?

Turnaround is 24–48 hours for most projects, with rush available. To start, we need the architectural, MEP and finish plans, the landlord work letter, specifications, schedules (door, hardware, finish, lighting, plumbing) and the project ZIP code for pricing. If you have addenda or RFI responses, send those too so we price the current scope.

How do you price labor and material for different markets?

We use ZIP-code-adjusted material and labor rates from RSMeans data. A partition in a high-cost metro is priced with the local wage and material factors, not a national average. We also note the prevailing wage or union requirement if the project has one, since that changes the labor rate. The estimate shows the adjusted rate so you can see the basis.

Can you estimate a multi-tenant floor with separate suites?

Yes. We take off the demising partitions by height band and rating, then count MEP and finishes per suite. If the suites have different finish schedules or MEP layouts, we price them separately so you can compare. The summary shows the cost per suite and the shared corridor and core scope. This is common for speculative office and mixed-use buildings.

What about restroom build-out and ADA clearances?

If the shell does not include core toilet rooms, we take off the full restroom build-out: partitions, fixtures, accessories, finishes and ADA clearances. We check fixture counts and clearances against the plumbing plan and accessibility details. If the restroom is existing and being remodeled, we include selective demolition and any upgrades required by the adopted code.

Do you provide a marked-up plan set with the estimate?

Yes. We mark up the plan set in Bluebeam Revu with color-coded highlights for each quantity. Partition types, ceiling areas, floor finishes, doors, fixtures and MEP devices are highlighted so you can trace every line back to the drawing. The marked-up set is delivered as a PDF along with the Excel workbook and PDF estimate.

What does an office tenant improvement takeoff include?

It includes a full quantity takeoff by CSI division: Division 09 finishes (drywall, acoustic ceiling tile, flooring, paint), Division 08 doors and frames, Division 10 specialties, Division 12 furnishings, and the MEP divisions — Division 22 plumbing, Division 23 HVAC, Division 26 electrical, Division 27 communications and Division 28 electronic safety. Quantities are reported in square feet, linear feet and each, with on-screen takeoff markups in PlanSwift and Bluebeam Revu so you can trace every line back to the sheet.

How does tenant improvement cost estimating handle a landlord work letter?

We read the work letter as the scope boundary. Anything the landlord delivers — base building HVAC capacity, sprinkler main, electrical service to the panel, shell restroom core — is excluded and listed as a clarification. Anything the tenant funds — distribution above ceiling, branch wiring, demising partitions, finishes — is taken off in full. Where the work letter is silent, we flag it as an open item in the bid package so your subcontractors price the same scope.

Can you provide a tenant improvement estimate for contractors bidding multiple suites?

Yes. We take off each suite separately and roll the quantities into a summary sheet, so you can carry a per-suite unit price or a floor total. Core-and-shell items shared across suites — corridor finishes, common restrooms, main distribution — are isolated so they are not double-counted. This format works for hard bid, GMP and negotiated work, and it lets you compare your subcontractor quotes line by line against the takeoff.

RH

Reviewed by Ryan H.

Senior Estimator, 15+ years in construction estimating and cost planning. is a Senior Estimator with more than 15 years of professional experience in construction estimating and cost planning.

  • Construction cost estimating
  • Quantity takeoffs
  • Material and labor cost analysis
  • Bid preparation and evaluation
  • Drawing and specification review
  • Project budgeting

Guides on this topic

Send your plans and work letter

Send your TI plan set or landlord work letter and we will return a division-by-division takeoff with quantities and ZIP-adjusted pricing in 24–48 hours.

  1. We review the set and check for missing sheets or addenda.
  2. You get a quote with a price and a delivery date.
  3. You approve and we start the takeoff.
  4. You receive the Excel estimate and marked-up plans.
Upload plans for a quote