Quick answer
A 40x80 concrete slab cost typically falls between $23,000 and $58,000, or about $7 to $18 per square foot, depending on thickness, reinforcement, base prep, and region. A 4-inch slab sits at the low end; a 6-inch reinforced slab with a deep granular base sits at the high end.
- 3,200 square feet at 4 inches needs about 40 cubic yards of concrete; at 6 inches, about 59 yards.
- Concrete alone is roughly 40 to 55 percent of the total slab cost; base prep and labor carry the rest.
- Thickness, reinforcement, and site access move the price more than any other variable.
- Get the base, vapor barrier, and joint layout priced before you compare concrete bids.
What Drives a 40x80 Concrete Slab Cost?
A 40 ft x 80 ft slab covers 3,200 square feet. At typical U.S. ranges of $6–$14 per square foot for a basic slab-on-grade, the all-in 40x80 concrete slab cost usually lands between about $19,200 and $44,800, with most residential and light commercial work clustering in the $22,000–$32,000 band. These are planning ranges, not bids, and they vary by region, scope, and date.
The single biggest cost lever is thickness and reinforcement. A 4-inch slab with wire mesh is a different animal from a 6-inch slab with #4 rebar at 18 inches on center, and the gap between them runs into thousands of dollars on 3,200 SF. Site conditions and access move the number as much as the concrete itself: over-excavation, imported gravel base, compaction, a vapor retarder, and a pump truck on a tight lot all add line items that a bare per-square-foot figure ignores.
Region, season, and local ready-mix pricing create real spread. The same 3,200 SF slab can price 30–40% higher in a high-cost metro than in a rural market, and winter placement with accelerators or heated water pushes it further. Those variables are exactly why a concrete slab cost formula built from measured quantities beats a national average every time.
Use the per-square-foot band to screen a budget, then build a real takeoff from your plans. For a firm number on a specific slab, a concrete estimating service will measure thickness, reinforcement, base, and sitework line by line instead of guessing at a blended rate.
Treat every per-square-foot number in this article as a screening range. The moment you fix thickness, reinforcement, and sitework, the real number can land well outside it.
Concrete Slab Cost per Square Foot: Real Ranges
Typical U.S. ranges for slab-on-grade break into three tiers. A 4-inch unreinforced or mesh slab with minimal site prep runs about $6–$8/SF. A 5–6-inch slab with rebar and a proper compacted base runs about $8–$11/SF. A 6–8-inch structural slab with thickened edges, heavy rebar, and engineered subgrade runs $11–$14+/SF. These ranges vary by region, scope, and date.
Those figures include ready-mix, reinforcement, forms, vapor retarder, gravel base, labor, and typical finishing. They exclude excavation, permitting, engineering, and specialty finishes unless you add them. That exclusion list is where budgets go wrong, because on a 40x80 slab the excavation and haul-off can be a five-figure line on its own.
Cost per square foot is a screening tool, not a bid. It hides thickness, reinforcement, and sitework, which is where the real money lives. For a 3,200 SF slab, every $1/SF change is $3,200 on the bottom line, so a 1-inch thickness change or a rebar upgrade is a five-figure decision you should make before you price, not after.
Use per-SF only to compare options at the same scope. Never compare a 4-inch mesh slab to a 6-inch rebar slab with a single blended rate, and never let a 40x80 concrete slab price from one market stand in for another. A material takeoff converts the range into quantities you can actually buy, and that is the only fair basis for comparison.
When you compare two quotes, normalize the scope first. A lower per-SF number on a thinner slab is not a saving if the slab fails under the intended load.
40x80 Concrete Slab Cost Breakdown
A complete breakdown should separate site prep and excavation, gravel base and compaction, formwork, vapor retarder, reinforcement (rebar or mesh), ready-mix concrete, placement and finishing labor, control and expansion joints, curing, and any thickened edges or footings. Each line gets its own unit: cubic yards for concrete, tons or linear feet for rebar, square feet for vapor retarder and forms, and man-hours for finishing.
On a typical 3,200 SF slab, concrete and reinforcement are the largest material lines, and labor for placement, screeding, and finishing is the largest labor line. Sitework is the most variable line and the one most often underestimated, because over-excavation, haul-off, and imported base depend on what is under the slab, not on the slab itself.
A line-item breakdown is what turns a per-SF guess into a defensible number you can bid or budget from. It also gives you a cost model you can flex: change the thickness, swap mesh for #4 rebar at 18 inches on center, or add a thickened edge, and you can see the delta immediately instead of re-guessing the whole slab.
For a contractor, the breakdown is also the basis for change orders when the owner adds thickness or a thickened edge after the fact. Pricing those changes against the original line items is far easier than arguing over a lump sum, and a change order estimating process built on unit rates keeps the conversation factual. If you want the breakdown built for you, a concrete estimating service will deliver it bid-ready.
Ask for the breakdown in units you can buy and install. A lump sum hides the thickness, reinforcement, and sitework assumptions that decide whether the number is real.
The Concrete Slab Cost Formula
Every credible 40x80 concrete slab cost starts with one equation: volume in cubic yards equals length in feet times width in feet times thickness in feet, divided by 27. That 27 is the number of cubic feet in a cubic yard, and it is the single most common place estimators drop the ball. For a 40x80 slab at 6 inches, 40 × 80 × 0.5 = 1,600 cubic feet, and 1,600 ÷ 27 = 59.26 cubic yards. If you want to run this arithmetic against your own dimensions, a 40x80 concrete slab calculator can handle the volume and waste factor in seconds.
-
Compute neat volume. Use the actual pour thickness, not the nominal slab thickness. If the slab is 6 inches and the thickened edge is 12 inches, break the takeoff into separate volumes and add them. Mixing them into one average produces a number that will not survive a bid review. Concrete thickness is the input that most often gets fudged, and it is the one that moves the cubic yard count the most.
-
Apply a waste factor. Add 5–10% for a slab-on-grade placed by pump or direct chute. Push that to 10–15% when access is tight, the pour is complex, or the ready-mix supplier has a long travel time. Waste is not optional; it is a real line item.
-
Price the material. Material cost equals the adjusted volume in cubic yards times your local ready-mix unit cost per cubic yard. That unit cost moves with mix design, slump, fiber, and distance from the plant.
-
Price the labor. Labor cost equals slab area in square feet times a local labor rate per square foot, adjusted upward for thickness, reinforcement density, and finish class. A broom finish and a hard-troweled floor are not the same labor number.
-
Add every other line. Total slab cost equals material plus reinforcement plus forms plus base plus vapor retarder plus labor plus equipment plus markup. Skip one and the bid is short.
The formula is simple; the discipline is in the inputs. Garbage thickness, garbage base, garbage number. If you want the arithmetic handled against your actual plans, concrete estimating services and quantity takeoff services exist for exactly that reason.
A 40x80 slab is 3,200 SF. At 6 inches that is 59.26 CY neat, so rounding to 60 CY without a waste factor already leaves you short on a pour that cannot be stopped once it starts.
Worked Example: 40x80 Slab at 6 Inches
Example only. Prices below are illustrative U.S. averages; substitute your local ready-mix, rebar, aggregate, and labor rates before you bid.
Step 1 — Area and volume. 40 ft × 80 ft = 3,200 SF. Thickness 6 in = 0.5 ft. Volume = 3,200 × 0.5 = 1,600 CF ÷ 27 = 59.26 CY.
Step 2 — Waste and concrete material. Add 8% waste: 59.26 × 1.08 = 64.0 CY. At $165/CY ready-mix, concrete material = 64.0 × $165 = $10,560.
Step 3 — Reinforcement. #4 rebar at 18 in O.C. each way. Bars running across the 40 ft dimension: 40 ÷ 1.5 = 26.7, round to 27 bars × 80 ft = 2,160 LF. Bars running across the 80 ft dimension: 80 ÷ 1.5 = 53.3, round to 54 bars × 40 ft = 2,160 LF. Total = 4,320 LF. Add 10% for laps and waste = 4,752 LF. At $1.10/LF installed, rebar = $5,227.
Step 4 — Gravel base. 4 in compacted = 3,200 × 0.333 = 1,066 CF ÷ 27 = 39.5 CY. Add 10% = 43.4 CY. At $45/CY delivered and placed, base = $1,953.
Step 5 — Vapor retarder and formwork. Vapor retarder: 3,200 SF + 10% laps = 3,520 SF at $0.15/SF = $528. Formwork: perimeter 240 LF at $6/LF = $1,440.
Step 6 — Labor. Placement, screeding, finishing, jointing, and curing at $2.75/SF × 3,200 = $8,800.
Step 7 — Subtotal and markup. Subtotal = $10,560 + $5,227 + $1,953 + $528 + $1,440 + $8,800 = $28,508. Add 15% overhead and profit = $32,784. Per SF = $32,784 ÷ 3,200 = $10.25/SF.
That $10.25/SF is the number to carry into your bid, not the ready-mix price alone. If you want this build-up run against your own drawings, a concrete estimating services takeoff or a full quantity takeoff services scope will show every line and its backup.
Rounding rebar counts down instead of up is the most common error in this example. You cannot place 26.7 bars; you place 27, and the extra length is real money.
Concrete Slab Cost by Thickness
Thickness drives volume, and volume drives the concrete line. For a 3,200 SF slab, the neat volumes before waste are shown below. At $165/CY, the concrete material alone moves from roughly $6,500 at 4 inches to about $13,000 at 8 inches, before waste, reinforcement, base, or labor.
| Thickness | Thickness (ft) | Neat Volume (CY) | Concrete Material at $165/CY |
|---|---|---|---|
| 4 in | 0.333 | 39.5 | $6,518 |
| 5 in | 0.417 | 49.4 | $8,151 |
| 6 in | 0.500 | 59.3 | $9,785 |
| 8 in | 0.667 | 79.0 | $13,035 |
Reinforcement scales with thickness and span. A thicker slab usually carries heavier loads, which means larger bar sizes, closer spacing, or both, and that compounds the cost beyond the concrete line alone. Use ACI 318 and ACI 332 as your reference for minimum thickness and reinforcement for the intended use; do not guess at either. A 4-inch slab is fine for a patio or a shed floor. A 6-inch slab with rebar is the practical minimum for vehicle traffic and most commercial floors.
When the slab is part of a larger foundation package, the thickness decision has to line up with the footing and grade beam design. Foundation estimating services covers that interface, and concrete estimating services handles the slab takeoff itself.
A 2-inch increase from 6 to 8 inches adds roughly 19.7 CY, or about $3,250 in concrete alone at $165/CY, before any reinforcement change. Confirm the thickness with the structural drawings before you price it.
Send Your 40x80 Slab Plans for a Bid-Ready Takeoff
Upload your drawings and get a line-item 40x80 slab estimate with concrete, base, rebar, and labor priced separately, bid-ready in 48 hours.
Material Costs for a 40x80 Slab
For a 40x80 slab, material costs are driven by the concrete mix design, reinforcement type, and under-slab components. Ready-mix concrete is specified by compressive strength and slump; a typical slab-on-grade uses 3,500–4,500 psi at a 4–5 inch slump, produced per ASTM C94 for ready-mixed concrete. Your batch plant ticket will list the mix ID, slump, and admixtures, so the estimator can tie the unit cost to a specific submittal rather than a generic "concrete" line.
Reinforcement is either welded wire mesh (ASTM A185) or deformed billet-steel bars (ASTM A615). Wire mesh is priced per square foot or per roll, while rebar is priced per pound or per linear foot installed, including chairs and tie wire. For a 40x80 slab, the reinforcement takeoff should account for lap splices, which add roughly 10–15% to the theoretical weight, and for any thickened edges or interior beams.
Under the slab, a vapor retarder is typically 10–15 mil polyethylene. It is cheap per square foot but non-negotiable under finished floors, and it must be lapped and sealed at penetrations. Below that, a gravel base is typically 4–6 inches of compacted crushed stone, placed in lifts and compacted to a specified percentage of maximum dry density per ASTM D698 or D1557.
Formwork is priced per linear foot of edge. A 40x80 slab has 240 LF of perimeter plus any interior bulkheads or thickened edges. If you need a detailed material takeoff for a 40x80 slab, our material takeoff services can itemize each component, and our concrete estimating services can price the full scope. A 40x80 slab material cost estimate should list concrete, mesh or rebar, vapor retarder, base gravel, and formwork as separate line items so you can see where the money goes. When you are pricing the cost of 3200 square foot slab, remember that concrete thickness and reinforcement density are the two variables that swing the total the most. For concrete slab cost for contractors, the unit cost per square foot is only useful if it is built from those same line items, not pulled from a national average.
Always verify the actual mix design and reinforcement submittals against the structural drawings; substituting a lower psi mix or lighter mesh can save material cost but may not meet the specified design.
Labor Cost for a 40x80 Slab
Labor for a slab-on-grade is usually priced per square foot and covers layout, form setting, base prep, vapor retarder, reinforcement placement, concrete placement, screeding, floating, troweling, joint cutting, and curing. Typical U.S. ranges run $2.00–$4.50 per square foot for standard flatwork, higher for laser screed, hard-troweled, or tight-tolerance floors. That range reflects differences in finish, access, and crew productivity, not just geography.
A 3,200 SF slab at $2.75/SF is $8,800 in labor; at $4.00/SF it is $12,800. That spread is real and depends on finish, access, and crew productivity. For a 40x80 slab labor cost, the same logic applies: the larger the pour, the more the finishing method and site logistics matter. A broom finish is faster and cheaper than a burnished power-troweled floor, and a laser screed can reduce labor hours on large open areas but adds equipment cost.
Overtime, night pours, and winter heating add labor cost that per-SF tables rarely capture. If the slab is placed in winter, you may need heated enclosures, accelerators, or blankets, all of which add labor and material. For a reliable 40x80 slab labor cost, build the estimate from crew hours and productivity rates rather than a single per-SF number. Our labor cost estimating services can help you build a crew-based labor model, and our concrete estimating services can price the complete slab package.
Ask your concrete subcontractor how they plan to finish the slab and whether they will use a laser screed or ride-on trowels; the method drives both labor hours and the final floor tolerance.
Site Prep, Base, and Subgrade Costs
Subgrade preparation includes stripping topsoil, proof-rolling, and compaction; unsuitable soils must be over-excavated and replaced. For a 40x80 concrete slab cost, these sitework items are often the most variable and the easiest to miss. If the geotechnical report calls for removal of soft spots, the excavation and backfill can add thousands of dollars before any concrete is placed.
A 4–6 inch gravel base is standard under a slab-on-grade; it is placed in lifts and compacted to a specified density. Compaction is verified by field density testing; failing compaction is a common cause of slab cracking and callbacks. The base material is typically crushed stone or bank run gravel, and the cost per ton depends on the distance from the quarry and the hauling method.
Site access drives cost: a pump truck adds several hundred to a few thousand dollars but can be cheaper than a long chute or wheelbarrow run. If the pour is in a backyard with no truck access, a pump is almost always required. Excavation, haul-off, and imported fill are often carried under a separate sitework or excavation scope; confirm who owns them. For a 40x80 concrete slab cost estimate, you need to know whether the excavation contractor is responsible for the subgrade, or whether the concrete contractor will do it. Our excavation estimating services and sitework estimating services can help you separate these scopes and avoid double-counting.
Before you price the slab, confirm the geotechnical report recommendations for subgrade preparation and base thickness; those requirements set the scope for both excavation and concrete.
Reinforcement, Control Joints, and Expansion Joints
Reinforcement and joint detailing are often underestimated in a 40x80 concrete slab cost. Control joints are saw-cut or tooled to control where the slab cracks; spacing is typically 2–3 times the slab thickness in feet (e.g., 10–15 ft for a 5-inch slab). Expansion joints isolate the slab from walls, columns, and other structures; they are a different detail from control joints and are priced separately. For a 3,200 SF slab, joint layout affects both cost and performance; a jointing plan should be part of the drawings. If your drawings lack a jointing plan, your concrete estimating services provider can develop one during takeoff.
Rebar or mesh placement matters: chairs and dobies keep reinforcement at mid-depth; steel on the ground does almost nothing. For a 40x80 slab, using #4 reinforcing bar at 18 inches on center each way requires about 2,400 linear feet of rebar plus chairs and tie wire. A rebar estimating service can verify quantities and lap splices. Thickened edges and footings add concrete and labor; they are common under load-bearing walls and at garage door openings. These details can add 10–15% to the concrete volume and require additional forming and excavation. Always clarify whether the scope includes thickened edges or footings, as they significantly affect the total cost.
Control joints must be cut within 6–12 hours of finishing to be effective; delayed cutting leads to random cracking.
Concrete Slab Cost per Yard
Ready-mix concrete is sold by the cubic yard, and the concrete slab cost per yard is a key driver of your total. A 40x80 slab at 6 inches needs about 59.3 CY before waste and about 64 CY with 8% waste. Typical U.S. ready-mix prices range from about $140 to $190 per cubic yard for standard 3,500–4,500 psi mixes, varying by region, mix design, and volume. For a 40x80 slab, you will likely need 60–65 cubic yards, which at $140–$190 per yard translates to $8,400–$12,350 for concrete alone.
Short loads, small quantities, and Saturday deliveries carry premiums; a 3,200 SF slab is usually large enough to avoid short-load fees. However, if your site has limited access, you may need a pump, which adds $800–$1,500 per day. Cost per yard is only the concrete line; it excludes reinforcement, base, forms, vapor retarder, labor, and finishing. When comparing quotes, ask whether the per-yard price includes the pump, the waste allowance, and any environmental or fuel surcharges. A material takeoff service can provide a detailed breakdown of concrete quantities and costs.
Always order 5–10% extra concrete to account for spillage, uneven subgrade, and waste; running short mid-pour is costly.
40x80 Slab Foundation Cost vs. Slab-on-Grade
A slab-on-grade is a flat concrete slab supported by the subgrade; a slab foundation (often called a slab-on-grade foundation) includes thickened edges, footings, and sometimes grade beams. The 40x80 slab foundation cost is higher than a simple slab-on-grade because of additional excavation, concrete, and reinforcement. For a 40x80 slab foundation, you can expect a 40x80 concrete slab price ranging from about $10 to $18 per square foot, depending on footing size, reinforcement, and site conditions. That puts the total for a 3,200 SF foundation between $32,000 and $57,600.
Structural slabs for heavy equipment, racking, or vehicles require engineering and often exceed $18 per square foot. These slabs may include thicker sections, additional rebar, and higher-strength concrete. The distinction matters for bidding: a foundation scope includes work that a flatwork scope does not. If you are bidding a project, ensure your estimate clearly separates foundation work from flatwork. A foundation estimating service can help you accurately price footings, thickened edges, and grade beams. For a complete concrete scope, consider a concrete estimating service that covers both flatwork and foundations.
Foundation slabs often require a vapor retarder and granular base, which are sometimes omitted in flatwork estimates; verify the scope.
How Project Type Changes the 40x80 Slab Cost
The same 3,200 SF footprint carries very different 40x80 concrete slab cost depending on what the slab has to do. A residential garage slab is typically 4–5 inches thick with welded wire mesh or light rebar, while a commercial shop or warehouse slab is often 6–8 inches with heavy rebar and a hard-troweled finish. Thickness, reinforcement, and finish are the three biggest cost levers, and project type sets all three.
A metal building or PEMB slab usually includes anchor bolt templates set to the column reactions, thickened edges at the column lines, and a strict flatness tolerance so the steel erects without shimming. An agricultural or equipment slab may need 8–10 inch thickness and doweled joints to carry wheel loads and impact. A parking or driveway slab needs a stronger mix, more reinforcement, and a different joint layout than an interior floor because it sees weather, deicing salts, and turning loads.
In the estimate, CSI MasterFormat Division 03 (Concrete) covers cast-in-place concrete, reinforcement, and finishes, and the scope split between divisions decides who carries what cost. If the slab is bid under a commercial estimating scope, the general contractor may own base, forms, and finish, while a residential package often bundles flatwork with the sitework trade. Confirm the division split before you price, or you will double-count or miss whole line items.
Project type sets thickness, reinforcement, and finish. Price those three first, then apply the 40x80 concrete slab cost formula.
Common Mistakes When Estimating a 40x80 Slab
- Forgetting waste. Ordering exactly the net volume leaves you short at the pump. For a 6-inch 40x80 slab the net is about 59.3 CY, and a 5–10% waste factor is standard, so order 62–65 CY. Waste covers spillage, over-excavation, and uneven subgrade.
- Ignoring the base. A slab placed on unprepared subgrade will crack and settle. Base material, compaction in lifts, and proof-rolling are real costs that belong in the estimate, not a line the field crew absorbs.
- Using the wrong thickness. A 4-inch slab under vehicle traffic is a callback waiting to happen. Match thickness to the loads the slab will actually see, not to the cheapest number in a per-SF table.
- Missing thickened edges and footings. Turn-down edges, grade beams, and column pads add concrete, rebar, and labor that per-SF tables often omit. Take them off separately.
- Underpricing finishing. A hard-troweled, tight-tolerance floor costs more than a broom finish. Machine troweling, curing compound, and flatness checks are labor-heavy line items.
- Not confirming who owns excavation, haul-off, and final grading. These are common scope gaps between trades. Write the assumption into your proposal so a concrete estimating scope review does not turn into a change order.
Run a second set of eyes over the takeoff with an estimate review before you submit, because a missed waste factor or base line is cheaper to fix on paper than on site.
The most expensive mistakes are omissions, not wrong unit prices. Check waste, base, thickness, edges, finish, and scope gaps before you bid.
When to Get a Professional 40x80 Slab Estimate
Use a professional takeoff when you are bidding, when the slab is part of a larger foundation scope, or when thickness, reinforcement, or site conditions are not yet defined. Those are the jobs where a per-SF rule of thumb breaks down and a real quantity takeoff pays for itself. A 40x80 concrete slab estimate built from your drawings gives you exact cubic yards, rebar tonnage, form LF, and base CY, priced with current local rates rather than a regional average.
For contractors, a third-party estimate is a check against your own numbers and a defense against missed scope. It is common to find a missing thickened edge, an understated waste factor, or a base line that never made it into the bid. For owners and developers, an independent estimate supports budgeting and lender requirements before you commit to a contract, and it gives you a defensible number at the right AACE estimate class for your stage of design.
Scope Precision Estimate can turn a 40x80 slab takeoff around in 24–48 hours, with same-day quotes and rush options. Upload your plans through our concrete estimating services or start with a quantity takeoff and we will return a bid-ready package. To get pricing on your slab, upload your plans here.
If the drawings do not yet define thickness, reinforcement, or base, a rule-of-thumb price is a guess. A takeoff turns those unknowns into quantities you can price.
Frequently asked questions
How much does a 40x80 concrete slab cost?
A 40x80 slab (3,200 square feet) typically runs $23,000 to $58,000, or about $7 to $18 per square foot. A 4-inch unreinforced slab on a shallow base lands near the bottom of that range; a 6-inch slab with rebar, a 6-inch compacted base, vapor barrier, and formed edges lands near the top. Region, haul distance, access, and whether you need footings or thickened edges all shift the number. Treat any single figure as a starting point and price your actual scope.
How many yards of concrete do I need for a 40x80 slab?
Use volume: length x width x thickness in feet, divided by 27. A 40x80 slab is 3,200 square feet. At 4 inches (0.333 feet) that is 3,200 x 0.333 = 1,066 cubic feet, or about 40 cubic yards. At 5 inches, about 49 yards. At 6 inches (0.5 feet), 1,600 cubic feet, or about 59 yards. Add a waste and spillage factor of roughly 5 to 10 percent, so order about 42 yards for the 4-inch case.
What is the cost per square foot for a 40x80 concrete slab?
Most 40x80 slabs price between $7 and $18 per square foot installed. Light-duty flatwork with mesh and a thin base sits near $7 to $10. A 6-inch slab with rebar, vapor barrier, thickened edges, and a compacted granular base runs $13 to $18. The spread comes from thickness, reinforcement, base depth, and site conditions, not from the concrete itself. For a line-item breakdown of your own plans, use a concrete estimating service that prices each assembly separately.
How thick should a 40x80 concrete slab be?
Thickness follows use, not size. Residential garage and shed slabs are commonly 4 inches. Driveways carrying passenger vehicles are often 4 to 5 inches. Slabs for heavy trucks, dumpsters, or equipment are typically 6 inches, sometimes 7 to 8 inches with a thicker edge. A 40x80 slab is large enough that control joints, reinforcement, and base compaction matter as much as thickness. Confirm the design with a structural engineer before you pour.
Do I need rebar or wire mesh for a 40x80 slab?
Both control cracking; neither replaces a proper base. Wire mesh (6x6-W2.9xW2.9) is common in residential flatwork and light commercial slabs. Rebar, typically #4 at 18 to 24 inches on center, is standard for vehicle traffic, heavy loads, or slabs on marginal subgrade. A 3,200-square-foot slab has enough area that shrinkage cracking is a real risk, so reinforcement plus a joint layout at roughly 10 to 12 feet on center is normal practice. Your engineer's drawings govern.
How much does labor cost for a 40x80 concrete slab?
Placing and finishing labor for a 40x80 slab commonly runs $2 to $5 per square foot, or roughly $6,400 to $16,000 for the 3,200-square-foot area. That covers forming, screeding, floating, troweling, joint cutting, and curing. It excludes excavation, base material, and concrete supply. Crew size, access, and finish type (broom, trowel, hardener) drive the spread. Large open slabs finish faster per square foot than cut-up areas with many edges.
What is the difference between a slab-on-grade and a slab foundation?
A slab-on-grade is a single concrete layer placed on compacted base, used for garages, shops, and light commercial floors. A slab foundation is a structural system: a slab plus thickened edges, grade beams, or footings that carry building loads and, in some regions, post-tensioned cables. Foundation work adds excavation, forming, reinforcement, and engineering, so it costs more per square foot. See foundation estimating services for how those assemblies are priced.
How long does it take to pour a 40x80 concrete slab?
A 3,200-square-foot slab is usually placed in one continuous pour of 4 to 8 hours, depending on thickness, crew size, and truck access. Base prep, forming, and reinforcement take longer than the pour itself, often 3 to 7 working days for a straightforward site. Finishing, joint cutting, and curing follow: concrete reaches usable strength in about 7 days and design strength near 28 days. Weather, pump needs, and inspection hold points can extend the schedule.